HomeMy WebLinkAbout2009/12/01 - Agenda Packet DESIGN REVIEW COMMITTEE MEETING
TUESDAY DECEMBER 1, 2009 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
ACTION AGENDA
Committee Members: Lou Munoz Pam Stewart Corkran Nicholson
Alternates: Ray Wimberly Frances Howdyshell Richard Fletcher
CONSENT CALENDAR
NO ITEMS SUBMITTED.
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant regarding
their development application. The following items do not legally require any public testimony, although
the Committee may open the meeting for public input.
7:00 p.m.
(Steve/Willie) DEVELOPMENT REVIEW DRC2009-00413 - STANTEC CONSULTING -
COMERICA BANK - A request to construct a 3,982 square foot retail bank with a
drive thru at an existing retail center within the Industrial Park District, Subarea 7,
located at 12035 Foothill Boulevard: APN: 0229-023-05. On January 24, 2007, a
Mitigated Negative Declaration was adopted by the Planning Commission for
Tentative Parcel Map SUBTPM17818. The California Environmental Quality Act
provides that no further environmental review or Negative Declaration is required for
subsequent projects or minor revisions to projects within the scope of a previous
Mitigated Negative Declaration.
PUBLIC COMMENTS
There were no public comments.
ADJOURNMENT
The meeting adjourned at 7:50 p.m.
DESIGN REVIEW COMMENTS
7:00 p.m. Steve Fowler December 1, 2009
DEVELOPMENT REVIEW DRC2009-00413 - STANTEC CONSULTING - COMERICA BANK - A request
to construct a 3,982 square foot retail bank with a drive thru at an existing retail center within the
Industrial Park District, Subarea 7, located at 12035 Foothill Boulevard: APN: 0229-023-05. On
January 24, 2007, a Mitigated Negative Declaration was adopted by the Planning Commission for
Tentative Parcel Map SUBTPM17818. The California Environmental Quality Act provides that no further
environmental review or Negative Declaration is required for subsequent projects or minor revisions to
projects within the scope of a previous Mitigated Negative Declaration.
Design Parameters: The applicant is proposing to construct a 3,982 square foot bank building with a
drive thru ATM at 12035 Foothill Boulevard. This site is on the south side of Foothill Boulevard in the
Industrial Park District, Subarea 7.
At the Design Review Committee Meeting held on October 6, 2009, the applicant was asked to change
the roofing material from standing seam metal to light weight concrete tile. The applicant was proposing
a Charcoal Grey blend tile. They now would like to change the color to a Charcoal Brown Blend slate
tile. The exterior of the building is proposed to use a mixture of Mountain Rose colored brick veneer for
the wall plans, a Frosted Almond colored brick veneer band around the lower part of the entire building,
and a stone veneer for the tower element and columns around the entire building.
Staff Comments: The following comments are intended to provide an outline for Committee discussion
regarding this project.
Major Issues: The applicant worked hard with staff to follow the criteria outlined in the Development
Code, but there is still a color issue with the roof tile. Staff feels the color Charcoal Brown Blend gives a
monotone appearance to the building, and the Charcoal Grey blend would be a better fit for the project.
Staff recommendation: Staff feels the color Charcoal Brown Blend gives a monotone appearance to
the building and the Charcoal blend would be a better fit for the project. Staff recommends that the
Design Review Committee keep with its previous recommendation of the Charcoal Blend tile.
•
Design Review Committee Action:
Members Present: Munoz, Wimberly, Nicholson
Staff Planner: Steve Fowler
Yvonne Buan, Renee Webber, and the representative from Comerica Bank, presented a revision to the
roof color previously approved by the Design Review Committee for the propose_Comerica Bank at
12035 Foothill Boulevard. The proposal was to change the roof color to a Charcoal Brown blend from
the approved Charcoal Grey blend. The applicant revisited the standing seam metal roof, and the
Committee again requested the roof to be concrete tile. The Committee members supported the
approved color citing continuity with the other building in the center. The applicant responded back to
DRC ACTION AGENDA
DRC2009-00413— SANTEC CONSULTING —COMERICA BANK
December 1, 2009
Page 2
the Committee that they had to discuss this with Comerica Bank because they have final approval on all
the color choices with the site. The Committee members strongly recommended the applicant stay with
the approved color but agreed to review any revisions the applicant submits.
DESIGN REVIEW COMMENTS
December 1, 2009
ADJOURNMENT
The meeting adjourned at 7:50 p.m.
s ctfully st6 lLe
Corkran W. Nicholson