HomeMy WebLinkAbout915 - Ordinances - ADDING CHAPTER 15.38 TO MUNICIPAL CODE - EV CHARGING STATIONS ORDINANCE NO. 915
AN ORDINANCE OF THE CITY COUNCIL OF RANCHO
CUCAMONGA, CALIFORNIA, ADDING CHAPTER 15.38 TO THE
RANCHO CUCAMONGA MUNICIPAL CODE TO ESTABLISH AN
,EXPEDITED PERMITTING PROCESS FOR EV CHARGING
STATIONS.
The City Council of the City of Rancho Cucamonga does ordain as follows:
SECTION 1: Chapter 15.38 is hereby added to the Rancho Cucamonga Municipal Code to
read as follows:
"Chapter 15.38 Expedited Permitting for Electric Vehicle Charging Stations
15.38.010 Applicability
This chapter applies to applications for expedited building permits for electric vehicle
charging stations consistent with California Government Code Section 65850.7.
15.38.020 Definitions
The following definitions shall apply for purposes of this chapter:
A. "Electric vehicle charging station" or "charging station" means any level of electric
vehicle supply equipment station that is designed and built in compliance with Article
625 of the California Electric Code, as it read on January 1, 2016, and delivers
electricity from a source outside of an electric vehicle into a plug-in electric vehicle.
B. "Electronic submission" means a submission of an application utilizing email, the
internet, and/or facsimile transmission.
C. "Specific, adverse impact" means a significant, quantifiable, direct, and unavoidable
impact, based on objective, identified, and written public health or safety standards,
policies, or conditions as they existed on the date an application was deemed
complete.
15.38.030 Process
A. The building official shall adopt a checklist of all application requirements for expedited
building permits for electric vehicle charging stations. The checklist shall substantially
conform to the most current version of the "Plug-In Electric Vehicle Infrastructure
Permitting Checklist" found in the "Zero-Emission Vehicles in California: Community
Readiness Guidebook" published by the Governor's Office of Planning and Research.
The checklist, application form, and any other documents required by the building
official shall be published on the City's website.
B. Anyone seeking to install an electric vehicle charging station at any site within the City
shall apply to the building official for an expedited nondiscretionary building permit.
C. An application for an expedited building permit for an electric vehicle charging station,
and all associated documentation, may be submitted to the building official in person,
Ordinance No. 915 - Page 1 of 3
by mail, or by electronic submission. Electronic signatures may be used in lieu of wet
signatures.
D. An application that, in the opinion of the building official, satisfies the information
requirements of the checklist adopted by the City shall be deemed complete.
E. If an application for an expedited building permit is deemed incomplete, the building
official shall provide a written correction notice of the deficiencies and the additional
information required to complete the application.
F. If the building official determines that an application for an expedited building permit is
complete, the building official shall review the application. If the building official
determines that the proposed charging station meets all health and safety
requirements of state and federal law, and would not have a specific, adverse impact
upon the public health or safety, the application shall be approved and a building
permit shall be issued.
G. If the building official finds, based on substantial evidence, that a proposed charging
station could have a specific, adverse impact upon the public health or safety, the City
may require the applicant to apply for an electric vehicle charging station use permit
in order to install the proposed charging station.
H. An application for an electric vehicle charging station use permit shall be reviewed by
the building official. The building official shall not deny such an application without
making written findings, based upon substantial evidence in the record, that the
proposed charging station would have a specific, adverse impact upon the public
health or safety which could not feasibly be satisfactorily mitigated or avoided. The
written findings required for rejection of an electric vehicle charging station use permit
application shall include the building official's basis for rejecting any potentially feasible
alternatives that could mitigate or prevent the alleged adverse impact. Pursuant to
Government Code Section 65850.7, the building official's review shall be limited to
health and safety issues. Aesthetic concerns, or other items not related to public
health or safety may not be considered.
I. A decision of the building official made pursuant to paragraphs F, G, or H of this
subsection may be appealed to the Planning Commission. The Planning
Commission's review shall also be limited to health and safety issues.
J. Any condition imposed on an application for an expedited building permit or electric
vehicle charging station use permit shall be designed to mitigate the specific, adverse
impact upon health and safety at the lowest possible cost."
SECTION 2: The City Clerk shall certify to the adoption of this Ordinance.
Ordinance No. 915— Page 2 of 3
PASSED, APPROVED, AND ADOPTED this 6th day of September 2017.
A&/
is Mich , May
ATTEST:
odln6
ice C. Reynolds, Cit Jerk
STATE OF CALIFORNIA )
COUNTY OF SAN BERNARDINO ) ss
CITY OF RANCHO CUCAMONGA )
I, JANICE C. REYNOLDS, CITY CLERK of the City of Rancho Cucamonga,
California, do hereby certify that the foregoing Ordinance was introduced at a Regular Meeting of
the City Council of the City of Rancho Cucamonga held on the 16th day of August 2017, and was
passed at a Regular Meeting of the City Council of the City of Rancho Cucamonga held on the
6th day of September 2017.
AYES: Alexander, Kennedy, Michael, Spagnolo, Williams
NOES: None
ABSENT: None
ABSTAINED: None
Executed this 7th day of September 2017, at Rancho Cucamonga, California.