HomeMy WebLinkAbout07-01 - Agenda Packet
If you need special assistance or accommodations to participate in this meeting, please
contact the Planning Department at (909) 477-2750. Notification of 48 hours prior to the
meeting will enable the City to make reasonable arrangements to ensure accessibility.
Listening devices are available for the hearing impaired.
JULY 1, 2025- 6:00 P.M.
DESIGN REVIEW COMMITTEE
MEETING AGENDA
RAINS ROOM
CITY HALL
10500 Civic Center Drive
Rancho Cucamonga, CA 91730
A. Call to Order
Roll Call: Vice Chairman Al Boling
Commissioner James Daniels
B. Public Communications
This is the time and place for the general public to address the Committee on any item listed or not
listed on the agenda. The Committee may not discuss any issue not included on the agenda but set
the matter for a subsequent meeting.
C. Consent Calendar
C1. Consideration to adopt Meeting Minutes of June 17th, 2025.
D. Project Review Items
D1. ZONING MAP AMENDMENT, MASTER PLAN, DEVELOPMENT AGREEMENT,
TENTATIVE MAP, DESIGN REVIEW AND CONDITIONAL USE PERMIT - To allow for the
development and operation of three buildings totaling 985,329 square feet within approximately
2,805,809 gross square feet in lot size on certain property (and two remaining parcels) bounded
by the BNSF/Metrolink Railway to the north, Etiwanda Avenue to the east, and industrial land
uses to the south and west; APNs: 0229-283-79. Primary Case File No. DRC2021-00484.
E. Adjournment
The Design Review Committee has adopted Administrative Regulations that set an 11:00 p.m. adjournment
time. If items go beyond that time, they shall be heard only with the consent of the Committee.
I, Elizabeth Thornhill, Executive Assistant of the City of Rancho Cucamonga, or my designee,
hereby certify that a true, accurate copy of the foregoing agenda was posted seventy-two (72)
hours prior to the meeting per Government Code 54954.2 at 10500 Civic Center Drive, Rancho
Cucamonga, California and on the City’s website.
Design Review Committee
Meeting Agenda
June 17, 2025
DRAFT MINUTES
Rancho Cucamonga, CA 91730
New Time: 6:00 p.m.
A. Call to Order
The meeting of the Design Review Committee held on June 17, 2025. The meeting was called to order by
Jennifer Nakamura, Staff Coordinator, at 6:00 p.m.
Design Review Committee members present: Vice Chairman Boling and Commissioner Daniels
Staff Present: Kirt Coury, Contract Planner
B. Public Communications
Staff Coordinator opened the public communication and after noting there were no public comments,
closed public communications.
C. Consent Calendar
C1.
Consideration to adopt Meeting Minutes of June 3, 2025.
Item C1. Motion carried 2-0 vote as amended and posted online.
D. Project Review Items
D1. ZONING MAP AMENDMENT, MASTER PLAN, DEVELOPMENT AGREEMENT,
TENTATIVE MAP, DESIGN REVIEW AND CONDITIONAL USE PERMIT - To allow for the
development and operation of five buildings totaling 1,775,098 square feet within
approximately 3,513,101 gross square feet in lot size on certain property bounded by Arrow
Route to the north, BNSF/Metrolink Railway to the south, Yellow Wood Road/Juneberry Drive
and industrial land use to the east and west; APNs: 0229-121-35, 0229-131-19, 0229-121-33,
0229-121-34. Primary Case File No. DRC2021-00485.
Staff presented the item to the Design Review Committee. The Committee liked the project
design overall and asked for clarification on a few items. Committee member Daniels asked
for clarification on the number of "new" streets proposed for the project. He expressed that he
liked the design and the layout of the project, and that the architecture would be complimentary
to the surrounding area. He asked about the proposed screen wall heights and
locations. Committee member Boling asked for clarification on truck access, drive approaches,
street dedications, and overall connections to adjacent public streets. He too expressed favor
for the proposed architecture and like the street circulation, layout, and design of the overall
project.
The Design Review Committee voted to move the project forward to the Planning Commission
with a recommendation of approval.
Recommended approval to PC. 2-0 Unanimous Vote.
E. Adjournment
Planning Director Nakamura adjourned the meeting at 6:36 p.m.
Respectfully submitted,
___________________________
Elizabeth Thornhill, Executive Assistant
DESIGN REVIEW COMMENTS
July 1, 2025
6:00 p.m.
Kirt Coury, Contract Planner
ZONING MAP AMENDMENT, MASTER PLAN, DEVELOPMENT AGREEMENT, TENTATIVE
MAP, DESIGN REVIEW AND CONDITIONAL USE PERMIT - To allow for the development
and operation of three buildings totaling 985,329 square feet within approximately 2,805,809
gross square feet in lot size on certain property (and two remaining parcels) bounded by the
BNSF/Metrolink Railway to the north, Etiwanda Avenue to the east, and industrial land uses to
the south and west; APNs: 0229-283-79. Primary Case File No. DRC2021-00484.
Site Characteristics: The project site totals approximately 64.41 acres and will be comprised of
five parcels after processing a new tentative parcel map (SUBTPM20487). Three parcels front
along the northern boundary of the project site accommodating the proposed buildings at this
location, as well as two parcels noted along Etiwanda Avenue, towards the southeasterly
portion of the project site. The site is generally located between Interstate 15 to the west,
Etiwanda Avenue to the east, and Arrow Route and the BNSF/Metrolink Railway to the north.
The Southern California Edison (SCE) “Etiwanda Sub-Station” is located adjacent to the south
and west property line of the project site and the Inland Empire Utilities Agency (IEUA) owns
property improved with utility infrastructure to the south/southwest of the project site.
The subject property was developed as agricultural use from approximately 1938 through 1951.
Following this, the site was redeveloped with an electric power generating facility, which has
since been decommissioned and demolished.
The existing land use, General Plan, and Zoning designations for the project site and adjacent
properties are as follows:
Land Use General Plan Zoning
Site Vacant Industrial Employment
District Industrial Employment (IE)
North Vacant/Industrial
Warehouse
Industrial Employment
District Industrial Employment (IE)
South Utility/Industrial Industrial Employment
District Industrial Employment (IE)
West Utility/Industrial Industrial Employment
District
Industrial Employment (IE)
East
Utility/Industrial Industrial Employment
District
Industrial Employment
(IE)/Unincorporated San
Bernardino County
Project Overview: The applicant is proposing to redevelop the project site that was previously
operated as a heavy industrial power generating station into a modern Class A warehouse
development. The proposed project would include the site clearing and grading of the project
site and the construction, use, and maintenance of three (3) new buildings for general
warehouse space, office space, loading docks for truck trailers, and include 569 automobile
parking spaces and 170 truck trailer parking spaces. The proposed project would also include a
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 2
new electrical substation, water quality basins, utility infrastructure, exterior lighting and signage,
and approximately 14 percent landscape coverage. Vehicle access to the project site would be
provided by public roadway connections from Etiwanda Avenue and Napa Street and by a
vehicular circulation system to be constructed as part of the proposed project. A new public
“Street A” will be constructed south of Building 1 and Building 2 and will connect to Napa Street.
New public “Street B” will run parallel to Buildings 1 and 2 in a North-to-South alignment, “Street
C” will run parallel to Building 3 and connect new streets “A” and “D”. Lastly, new public “Street
D" will be constructed along the northern property line as well as the most southern property line
and connect to Etiwanda Avenue. Truck circulation would travel North/South along Etiwanda
and access the site via the newly constructed streets.
Truck courts for each of the three buildings will be secured through manual gate access.
Electrical conduit will be installed to accommodate future tenant requests for electric gates and
site security guard shacks. Screening between neighboring parcels will be installed through
eight (8) foot screen walls painted to match the building architecture, and all utility structures will
be screened by landscape.
Project Site Plan
The Project is proposing an optional alternative for Parcel 3, which is proposed to be located
within the far northwestern corner of the project area, to be developed as one of the following
uses indicated below. This alternative would eliminate Building 3 (249,245 square feet).
• 11.5-acre Battery Energy Storage Facility (“BESS Facility”).
o Eliminate 180 auto parking spaces, and 33 truck trailer parking spaces.
• 11.5-acre Truck parking lot.
o Add 340 truck trailer parking spaces.
o Eliminate 180 auto parking spaces.
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 3
Alternate Site Plan with BESS Facility
Alternate Site Plan with Truck Parking Lot
The table below provides a breakdown of the maximum number of buildings proposed by
square footage for warehouse area, office area and mezzanine area:
Project Proposed Use Warehouse Office Area Mezz Area* G.F.A.
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 4
Data Area
Parcel 1 Industrial
Warehouse
578,741 SF 25,000 SF 20,000 SF 603,741 SF
Parcel 2 Industrial
Warehouse
122,343 SF 10,000 SF 5,000 SF 132,343 SF
Parcel 3 Industrial
Warehouse or
BES Facility or
Truck Parking
Lot
239,245 SF or
None
10,000 SF
or None
5,000 SF or
None
249,245 SF
or None
Parcel 4 Substation N/A N/A N/A N/A
Parcel 5 Substation N/A N/A N/A N/A
*Mezzanine areas may be used for office space. To consider a conservative worst-case scenario, the
project has included parking based on the mezzanine area as usable office space.
The proposed industrial warehouse buildings meet the City’s architectural design standards.
The buildings would be constructed of concrete tilt-up panels with reveal lines (that create an
aesthetic reveal between two panels), with multiple gray paint tones, vision glass, and spandrel
glass to provide a modern aesthetic. Offices will be located at one or more corners of the buildings
that will feature more extensive glass work, tiles, metal canopies, and aluminum storefront framing
with tempered glazing at all doors. Buildings will range in height from 45 feet for Buildings 2-3, and
53 feet for Building 1. The project also provides an attractive and varied color pallet to break up
the expanse of the façade which includes “Zircon Gray” (Sherwin Williams SW 7667), “Gray
Shingle” (SW 7670), “Peppercorn Gray” (SW 7674), and “Distance Gray” (SW 6243).
Aerial Image of Buildings From Etiwanda Avenue
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 5
Building Rendering
As noted in the title of this report, the applicant has also applied for a Master Plan. Pursuant to
Development Code Section 17.22.020, an applicant may establish site-specific development
standards upon the approval of a Master Plan (a full discussion of the Master Plan request will
be included in the Planning Commission staff report at a later date). The table below outlines
that the project complies with some of the applicable development standards for the Industrial
Employment zone, while others are not compliant and will need to be approved through the
Master Plan. Those site-specific development standards relative to architecture and site
planning for which the applicant requests to establish via the approval of the Master Plan are
indicated accordingly:
Development
Standard Required Proposed Complies?
Building Height
Maximum 35 feet (at front
setback) and
75 feet (1-foot increment
from the front setback line)
Building 1: 53 feet
Building 2: 45 feet
Building 3: 45 feet
YES
Floor Area Ratio
(FAR) 50-60%
Building 1: 47.81%
Building 2: 40.47%
Building 3: 49,40%
YES
Front Building
Setback
45 feet (Etiwanda);
25 feet (Local Streets) Building: 83 feet YES
Street Side
Setback 25 Feet (Street B) Building: 25 feet YES
Average Depth of
Landscape
45 feet (Etiwanda Avenue);
15 feet (Local Streets)
26 feet (Etiwanda Avenue);
15 feet (Street D)
MP
Request*
Parking Setback 25 feet (Etiwanda Avenue);
15 feet (Local Streets)
10 feet (Etiwanda Avenue);
15 feet (Street D)
MP
Request*
Interior Side Yard
Setback Min. 5 feet Buildings: 60 feet plus YES
Rear Yard Setback Min. 0 feet Building: 25 feet plus YES
Open 10% 14.13% YES
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 6
*The project applicant has requested to establish site specific development standards through the request
of approval of a Master Plan.
Pursuant to Development Code Section 17.64.050, 17.64.090 and Table 17.64.050-1, auto
parking for warehouse/storage uses is based on a tiered ratio as illustrated in the table below. In
addition, office areas require parking at 1 stall per 250 square feet. Further, the development
code requires 1 trailer loading stall for each dock door proposed. As such, the proposed project
is required to provide 475 auto parking stalls and 164 trailer loading. The table below
demonstrates the project’s compliance with all parking standards:
Parking Ratio Required
Parking
Provided
Parking Complies?
Warehouse/storage
and office
1 per 1,000 sf for the first
20,000 sf; 1 per 2,000 sf for
the next 20,000 sf, and 1 per
40,000 sf for remaining sf
Office requires 1 per 250 sf
Buildings:
475 stalls
Buildings:
569 stalls YES
Trailer Loading
Stalls 1 per loading dock Building:
164
Building:
170 YES
Landscaping would be provided in accordance with the RCMC Chapter 17.56, Landscaping
Standards. In total the project site would be developed with approximately seven acres of
landscape or other pervious surface area. The entire project site would be maintained with an
automatic irrigation system.
Staff Comments
Major/Secondary Issues: The following broad design issues will be the focus of Committee
discussion regarding the project:
None.
Policy Issues: The following items are a matter of Planning Commission policy or development
code requirements and should be incorporated into the project design without discussion:
1. Decorative paving shall be provided at each vehicle entrance to each of the new
sites/properties, behind the public right-of-way. New public intersections are not to be
considered “entrances to the site” for the purposes of this policy issue. These decoratively
paved areas shall extend from the front property line to the building setback line and have a
width equal to that of the driveway.
2. Downspouts shall not be visible from the exterior on any elevations of the building. All
downspouts shall be routed through the interior of the building walls.
3. Pursuant to 17.64.100.C, the applicant shall confirm prior to public hearing that the entrance
gate to all industrial properties shall be a minimum of 135 feet from the public-right-of-way.
Space/Landscape
Standards
DRC COMMENTS
DRC2021-00484 – BTC III ETIWANDA COMMERCE CENTER LP
Page 7
Staff Recommendation: Staff requests that the Design Review Committee consider the
design (building architecture, site planning, etc.) of the proposed project and recommend the
selected action below:
☐Recommend Moving the Item Forward to the Full Planning Commission as proposed by
the applicant.
☐Recommend Moving Forward with Modifications to the design of the project by
incorporating revisions requested by the Committee. Follow-up review by the Committee is not
required. The revisions shall be verified by staff prior to review and action by the Planning
Director / Planning Commission.
☐Recommend Conditional Support: of the design of the project by incorporating revisions
requested by the Committee. Follow-up review by the Committee is not required. The revisions
shall be Conditions of Approval and verified by staff during plan check after review and action by
the Planning Director / Planning Commission.
☐Recommend Further Consultation with Staff of the design of the project as proposed by
the applicant.
Staff Planner: Kirt Coury, Contract Planner
Staff Coordinator: Sean McPherson, Principal Planner
Attachment: Exhibit A: Link_Project Plans
EXHIBIT A
Due to file size, this attachment can be accessed through the following link:
Project Plans