HomeMy WebLinkAbout2025-11-12 - SupplementalsPanattoni 9 th and Vineyard Project
Primary Case File No: DRC2019 -00742
November 12, 2025
PROJECT BACKGROUND
DRC2019-00742 2
•Who : C P Lo g i s ti c s Vi n e y a r d , LLC ;
•What : A request for entitlements to
subdivide parcels and construct three new
industrial buildings totaling approx.
982,096 square feet and rehab historic
Baker House;
•Where : 45.96 acres bounded by 9 th Street,
Vineyard Avenue, BNSF/ Metrolink, and
Baker Avenue;
•When :
•Accepted on September 23, 2019;
•Deemed Complete on June 16, 2021.
Project Site and Background
9267 Haven Avenue
(To be renovated)
9227 Haven Avenue
(To be demolished)
North from 6th StreetView of 9th Street facing EastView of 8th and Baker looking Northeast
Panorama facing East from Baker Avenue
PROJECT SITE
Northwest from 6th Street and Utica Avenue
View of Baker House Facing East
9267 Haven Avenue
(To be renovated)
9227 Haven Avenue
(To be demolished)
North from 6th StreetView of 9th Street facing East
Proposed Project
Project:
•Proposal to construct
DRC2023-00067 11
PROPOSED PROJECT
Project:
•Proposal to construct
DRC2023-00067 11
PROPOSED PROJECT
DRC2023-00067 11
ARCHITECTURE
DRC2023-00067 8
Looking northeast from 6th and Utica
Looking northeast from 6th Street
Looking northeast from 6th and Utica
DRC2023-00067
Design Review
•Required to allow construction of
proposed project;
Tentative Parcel Map
•To consolidate project site into 4 lots;
Conditional Use Permit
•To permit requested uses
•Wholesale Distribution -Medium;
•Distribution/ Fulfillment Center, Large;
•E-Commerce Distribution
•Storage Warehouse
•Manufacturing, Light-La r g e
ENTITLEMENTS REQUIRED
Development Agreement
•To establish certainty in development
process for developer and benefits to
the City;
Certificate of Appropriateness
•To allow rehabilitation of Baker House
Important note
The Project application previously included additional
entitlements, including a Uniform Sign Program. Prior to the
public hearing, staff and the applicant agreed that the USP was
not necessary at this time and will rather be a condition of
approval. This action has no impact to overall project scope,
design or operational characteristics.
DEVELOPMENT AGREEMENT
•Term Length: eight years, with an option for an additional two years
upon payment by developer of $1 million;
•A requirement for future tenants to designate Rancho Cucamonga as the
“point of sale” for material handling equipment in project operation;
•A requirement for developer to pay $5 million Community Benefit Fee;
•Rehabilitate the Baker House and improve to tenant “shell.” Baker House
property to be dedicated to the City for future use in exchange for relief
on public art requirement.
Baker House
•Designated Historic Landmark (2014),
Certificate of Appropriateness required to allow
rehabilitation
•Developer proposes to rehabilitate structure,
subdivide and improve property after which
property to be dedicated to the City;
Drc2023-00067
DEVELOPMENT STANDARDS
•The Fire, Engineering and Building
Departments have also reviewed the
project and have provided conditions
of approval included with this staff
report;
•Various traffic improvements required.
INTERDEPARTMENTAL REVIEW
Neighborhood Meetings
•Two neighborhood meeting held on April 22, 2022 and August 8, 2024;
•Concerns included traffic, truck circulation, privacy walls, fiber optic
•Applicant revised plans to prohibit truck access on Baker Ave and limit
truck access on 9 th Street;
Design Review Committee (DRC)
•DRC held meeting on December 17, 2024.
•Comments included thoughts on truck circulation;
•A condition of approval added to require additional on-site queueing.
Previous Meetings
•Per State CEQA Guidelines, An EIR was prepared
for this project (SCH2019110456);
•EIR published in 2022, recirculated in 2024.
Environmental documentation included with this staff
report for reference (Exhibit C);
•Project results in significant and unavoidable impac
for noise and proximity to other uses;
•Statement of Overriding Considerations has been
prepared for Commission and Council
consideration.
ENVIRONMENTAL REVIEW
As required, this item was advertised as follows:
•Published in the Inland Valley Daily Bulletin on
October 29, 2025;
•Notices mailed to property owners and interested
parties on October 28, 2025;
•The project site was also posted with physical
notices on October 30, 2025;
•To date, staff has received three responses.
NOTICING
NEXT STEPS
NEXT STEPS
•Planning Commission is a recommending
body for this Project, including EIR
Certification;
•Separate noticed public hearing before the
City Council (date to be determined);
•City Council is the final authority on both EIR
and project.
RECOMMENDATION
RECOMMENDATION
Staff recommends that the Commission
approve Resolution 2025 -039 as amended,
recommending that the City Council approve
the project, subject to the Conditions of
Approval.
General Plan & Code Amendments
DRC2025 -00255 & 256
November 12, 2025]
BACKGROUND
BACKGROUND
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 3
•General Plan adopted in December 2021
•Need for technical updates
•Land Use and Community Character
•Mobility
•Municipal Code amendments needed to
support/implement proposed changes to the
General Plan
PROPOSED LAND USE CHANGES
Floor Area Ratio
•Clarify “Target Non -Residential Intensity”
•Eliminate FAR as a parcel-based requirement
Ground Floor Non-Residential
•Adding a minimum height requirement
•Clarifying where it is required
•Permit some amenity space on the ground floor
•Collapse types of non-residential uses allowed
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 5
PROPOSED AMENDMENTS
New Policy LC-2.12
•Block Length Max. 600 feet, perimeter 1,800
feet
•Allows for exceptions of up to 10%
•Goal of aligning with existing streets
Amended Policy LC-2.10
•Auto dependent uses (gas station, drive thru, car
wash)
•Clarifying prohibition on pedestrian priority
streets
•Creating safe and active public realm
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 6
PROPOSED AMENDMENTS
8 th Street Trail
•Deemed unfeasible
•Reallocate resources to existing infrastructure
•Remove references to the 8th Street trail
•Focus Area 1(Downtown Cucamonga)
•Focus Area 3 (HART District)
•Focus Area 5 (Cucamonga Town Center)
•Focus Area 8 (SE Industrial Area)
•Remove task from implementation workplan
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 7
PROPOSED AMENDMENTS
PROPOSED MOBILTY CHANGES
Boulevard Configurations for Foothill & Haven
•Foothill Boulevard east of Haven
•Haven Avenue South of Foothill to 7th Street
•Adding dimensional drawings
Roadway Typologies
•Adding a dimensions by roadway type
•Maximum ROW width
•Standards for lanes, medians and sidewalks
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 9
PROPOSED AMENDMENTS
AB 98 Truck Route Evaluation
•Reviewed existing truck routes for proximity to
sensitive receptors
•Vineyard/Carnelian had sensitive receptors along
73% of the route
•Updated the truck routes map
Other Amendments
•Incorporated Connect RC map
•Updated grade crossings in Focus Area 8
•Update goals and policies to prioritize safety
projects
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 10
PROPOSED AMENDMENTS
•An addendum to the General Plan EIR was
prepared
•EIR addresses all environmental issues
•No new significant impacts from this project
•Tribal notification initiated on August 29,
2024
•Notice published in the Inland Valley Daily
Bulletin on October 8th
•Individual noticing not required
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 11
ENVIRONMENTAL REVIEW & NOTICE
RECOMMENDATION
RECOMMENDATION
Staff recommends approval of Resolutions
2025 -040 and 2025 -041
City Council will consider these amendments
at a future hearing for final approval
GENERAL PLAN AND DEVELOPMENT CODE AMENDMENTS 13