HomeMy WebLinkAbout90-260 - Resolutions RESOLUTION NO. 90-260
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO
CUCAMONGA, CALIFORNIA, GIVING PRELIMINARY APPROVAL OF
CITY ENGINEER'S REPORT FOR STREET LIGHTING MAINTENANCE
DISTRICT NO. 7
WHEREAS, on May 17, 1989, the City Council of the City of Rancho
Cucamonga directed the City Engineer to make and file with the City Clerk of
said City a report in writing as required by the Landscaping and Lighting Act
of 1972; and
WHEREAS, the City Engineer has made and filed with the City Clerk of
said City a report in writing as called for pursuant to said Act, which report
has been presented to this Council for consideration; and
WHEREAS, said City Council has duly considered said report and each
and every part thereof, and finds that each and every part of said report is
sufficient, and that said report, nor any part thereof, requires or should be
modified in any respect.
NOW, THEREFORE, the City Council of the City of Rancho Cucamonga does
hereby resolve as follws:
SECTION 1: That the Engineer's Estimate of the itemized costs and
expenses of said work and of the incidental expenses in connection therewith,
contained in said report be, and each of them are hereby, preliminarily
approved and confirmed.
SECTION 2: That the diagram showing the Assessment District referred
to and described in said report, the boundaries of the subdivisions of land
within said Assessment District are hereby preliminarily approved and
confirmed.
SECTION 3: That the proposed assessment upon the subdivisions of
land in said Assessment District in proportion to the estimated benefit to be
received by said subdivision, respectively, from said work and of the inciden-
tal expenses thereof, as contained in said report is hereby preliminarily
approved and confirmed.
SECTION 4: That said report shall stand as the City Engineer's
Report for the purposes of all subsequent proceedings, and pursuant to the
proposed district.
PASSED, APPROVED, and ADOPTED this 20th day of June, 1990.
AYES: Alexander, Brown, Buquet, Stout, Wright
NOES: None
ABSENT: None
Resolution No. 90-260
Page 2
ATTEST:
Deb~ra d. Adamj~7~ City Clerk
I, DEBRA J. ADAMS, CITY CLERK of the City of Rancho Cucamonga,
California, do hereby certify that the foregoing Resolution was duly passed,
approved, and adopted by the City Council of the City of Rancho Cucamonga,
California, at a regular meeting of said City Council held on the 20th day of
June, 1990.
Executed this 21st day of June, 1990 at Rancho Cucamonga, California.
City Clerk
Resolution No. 90-260
Page 3
CITY OF RANCHO CUCAMONGA
ENGINEER'S REPORT
FOR
STREET LIGHTING MAINTENANCE DISTRICT NO. 7
TRACT NOS. 13565, -5 THROUGH -9
SECTION 1. AUTHORITY FOR REPORT
This report is prepared in compliance with the requirements of Article 4,
Chapter 1, Division 15, of the Street and Highways Code, of California
(Landscape and Lighting Act of 1972).
SECTION 2. GENERAL DESCRIPTION
This report proposes the establishment of a Street Lighting Maintenance
District for Tract Nos. 13565, -5 through -9 only. This project comprises the
area immediately north and south of 24th Street between Wardman-Bullock Road
and San Sevaine Road. The District will eventually include the majority of
the area referred to as the North Etiwanda Specific Plan, which generally
includes properties from Day Creek to the east City boundary and Highland
Avenue north to the National Forest limits. Areas to be included in the work
program are the street lights within the rights-of-way or designated easements
of streets dedicated to the City and are limited to local streets only as
shown hereon. Street lights within major roadways, such as San Sevaine,
Wardman-Bullock and 24th Street are not included. These areas will be
included in the City-wide lighting district for arterial highways.
SECTION 3. SCOPE OF WORK
The specific areas to be maintained by the District as defined in the preced-
ing section, will become part of the active work program at such time as the
specific areas are annexed into the District. The normal process will be the
dedication of the areas to the City, construction of the street lighting
system, and upon demonstration of satisfactory operation, the acceptance by
the District no later than the following July. The Developer will make a
sufficient deposit with the Southern California Edison Company to provide for
up to twelve (12) months of ordinary and usual maintenance, operation and
servicing costs of the street lights in each development at the time of
initial operation of the lighting system. Upon establishment of assessment
effective July I of each year, any remaining deposit shall be refunded to the
developer. Work to be provided for, with the assessments established by the
District, consists of maintenance, operation and servicing of street lights.
Annual Engineer's Reports will be prepared and approved by the City Council
defining the specific work program for each year and its estimated cost. The
plans and specifications for all street lighting will be prepared by the
developers for the subdivision improvements and will be approved by the City
Engineering Division.
Resolution No. 90-260
Page 4
Detailed maintenance activities on the Street Lighting Maintenance District
include: the furnishing of services and materials for the ordinary and usual
maintenance, operation and servicing of any street light improvement and the
repair, removal, or replacement of all or any part of any improvement,
providing for the illumination of the subject area.
SECTION 4. ESTIMATED COSTS
As development proceeds within North Etiwanda Specific Plan, the area to be
maintained by the District will increase and so will the cost; however, the
number of dwelling units will also increase. It is anticipated that the
number of dwelling units will also increase at approximately the same rate as
the maintenance area will increase, thereby keeping relatively constant the
cost per dwelling unit, excluding cost of living increases. Based on
historical data adjusted for inflation, it is estimated that the quantity of
street lights and the maintenance and energy costs for assessment purposes
will be as follows:
A. Tract Nos. 13565, -5 through -9
The estimated cost (at current dollars) for the District as initially
formed comprising the 216 dwelling units of Tract Nos. 13565, -5 through
-9.
Lamp quantits* Rate** Month/Annual Main. Cost
58 ea. 5800 Lumen x $ 8.93 x 12 : $517.94
6 ea. 9500 Lumen x 10.16 x 12 = 60.96
TOTAL $578.90
NOTE: Arterial lighting shall be annexed into a separate district.
* Assumed to be high pressure sodium vapor, 5800 lumen or 9500 lumen; actual
type and size may vary.
** All night energy service per lamp per month including maintenance costs.
All the costs are based on Southern California Edison Company monthly rates
including maintenance. All costs and areas are based on current estimates and
may or may not be valid for future years. The total cost and unit cost vary
as the monthly rate varies and as additional areas for maintenance are annexed
to the District. The monthly rate is established by the Southern California
Edison Company and is not currently controlled by the size of an area or any
operation of the developer. The size of the areas being annexed to the
District only has an influence on the total cost. The costs shown are
estimates only, and the final assessment will be based on actual cost data.
Resolution No. 90-260
Page 5
SECTION 5. ASSESSMENT DIAGRAM
A copy of the proposed Assessment Diagram for the tracts that will comprise
the original Maintenance District is attached to this report and labeled
Exhibit "A" - "Street Lighting Maintenance District No. 7". Exhibit "B" is a
legal description of the District boundary. These exhibits are hereby
incorporated within the text of this report.
The District will originally comprise Tract Nos. 13565, -5 through -9 only the
remainder of the "Highlands" project, namely Tract Nos. 13565, -5 through -9
will be annexed into the District at the time of recordation and City Council
approval.
SECTION 6. ASSESSMENT
Maintenance costs for the entire District are found to be of specific benefit
to all developed residential, institutional and commercial property within the
District in accordance with the following relationship:
Land Use Assessment Units
Single Family Detached I Assessment Unit
Multi-family/Attached Residential .5 Assessment Unit
Institutional/Commercial I Acre : 2 Assessment Units
Estimated Annual Assessments
Estimated Tract Nos. 13565, -5 through -9
Total annual cost (Section 4) $578.90
Assessment units
Single family 216 DU x I unit : 216 assessment units
Estimated assessment rate : $578.90 _ $2.68 per year
216
Thus, estimated assessments of $2.68 per assessment until will initially
be required for the original District.
Estimated assessments are for comparison only. Actual assessments will be
set by public hearing each year in June and will be based on actual energy
and maintenance expenses and developed land use summaries.
SECTION 7. ORDER OF EVENTS
1. City Council adopts Resolution of Preliminary Approval of City
Engineer's Report.
Resolution No. 90-260
Page 6
2. City Council adopts Resolution of Intention to form a District and
sets public hearings.
3. City Council conducts public hearing, considers all testimony and
determines to for a District or abandon the proceedings.
4. Every year in May, the City Engineer files a report with the City
Council.
5. Every year in June, the City Council conducts a public hearing and
approves or modifies and approves the individual assessments.
EXHIBIT "A"
Resolution No. 90-260
ASSl:Sslymm:'m~mT m)mA(~RAi~ Page 7
n
CITY OF RANCHO CUCAMONGA
COUNTY OF SAN BERNARDINO
STATE OF CALIFORNIA -5
Resolution No. 90-260
Page 8
EXHIBIT "B"
LEGAL DESCRIPTION
STREET LIGHTING MAINTENANCE DISTRICT NO. 7
FOR
TRACT NOS. 13565, -5 THRU -9
THOSE PORTIONS OF THE WEST HALF OF THE EAST HALF AND THE EAST HALF OF
THE WEST HALF OF SECTION 22, TOWNSHIP I NORTH RANGE 6 WEST, SAN
BERNARDINO MERIDIAN IN THE CITY OF RANCHO CUCAMONGA, COUNTY OF SAN
BERNARDINO, STATE OF CALIFORNIA AS SHOWN ON A MAP FILED IN BOOK 73.
PAGES 39 AND 40 OF RECORDS OF SURVEY OF SAID COUNTY DESCRIBED AS
FOLLOWS:
BEGINNING AT THE SOUTHWEST CORNER OF TRACT NO. 13565-6 AS SHOWN ON A
MAP FILED IN BOOK 217, PAGES 37 THROUGH 43 OF MAPS OF SAID COUNTY,
THENCE THE FOLLOWING COURSES:
1. NORTH 0°18'13" WEST 139.23 FEET ALONG THE WEST LINE OF SAID TRACT
BEING ALSO THE CENTERLINE OF RIDGELINE PLACE AS SHOWN ON SAID
MAP OF TRACT 13565-6 TO THE BEGINNING OF A 400.00 FOOT RADIUS CURVE
CONCAVE WESTERLY;
-. NORTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 35°53'28''
AN ARC DISTANCE OF 250.57 FEET;
3. NORTH 36°11'41'' WEST 324.50 FEET TO THE BEGINNING OF A 1900.00 FOOT
RADIUS CURVE CONCAVE NORTHEASTERLY;
4. NORTHWESTERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF
35°01'56" AN ARC DISTANCE OF 1161.71 FEET TO THE BEGINNING OF A 670.00
FOOT COMPOUND CURVE CONCAVE EASTERLY;
5. NORTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 40035'47''
AN ARC DISTANCE OF 474.72 FEET;
6. RADIAL TO SAID CURVE NORTH 49°56'57" WEST 30.00 FEET;
7. NORTH 39°05'15' WEST 494.75 FEET TO THE NORTHWEST CORNER OF TRACT
NO. 13565 AS SHOWN ON A MAP FILED IN BOOK 217, PAGES 59 THROUGH 62
OF MAPS OF SAID COUNTY;
8. ALONG THE NORTH LINE OF SAID TRACT 13565 NORTH 89039'30" EAST 1547.49
FEET TO THE NORTHWEST CORNER OF LOT "Y" OF SAID TRACT 13565;
9. SOUTH 28°40'37" EAST 44.01 FEET TO THE NORTHEAST CORNER OF LOT "Z" OF
SAID TRACT 13565 BEING A POINT ON A 1328.00 FOOT RADIUS CURVE
CONCAVE EASTERLY; A RADIAL THROUGH SAID POINT BEARS NORTH
73°58'51" WEST;
10. SOUTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF ~ ° '"
19 47 32
AN ARC DISTANCE OF 458.74 FEET;
DOC- 173
Resolution Ito. 90-260
Page 9
11. SOUTH 2"01'24" EAST 159.03 FEET TO THE BEGINNING OF A 1172.00 FOOT
RADIUS CURVE CONCAVE WESTERLY;
12. SOUTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 7°I 1'48"
AN ARC DISTANCE OF 147.21 FEET;
13. SOUTH 5"10'24" WEST 114.61 FEET TO THE BEGINNING OF A 1228.00 FOOT
RADIUS CURVE CONCAVE EASTERLY;
14. SOUTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 34~31'00"
AN ARC DISTANCE OF 1228.00 FEET;
15. SOUTH 29~20'36" EAST 377.23 FEET TO THE BEGINNING OF A 872.00 FOOT
RADIUS CURVE CONCAVE WESTERLY;
16. SOUTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 17"37'12"
AN ARC DISTANCE OF 268.16 FEET;
17. SOUTH 11°43'24" EAST 249.94 FEET TO THE BEGINNING OF A 780.00 FOOT
RADIUS CURVE CONCAVE WESTERLY;
18. SOUTHERLY ALONG SAID CURVE THROUGH A CENTRAL ANGLE OF 11~25'10''
AN ARC DISTANCE OF 155.46 FEET;
19. SOUTH 0°18'13" EAST 71.77 FEET TO A POINT ON THE SOUTH LINE OF SAID
TRACT NO. 13565-6;
20. SOUTH 89°41'47" WEST ALONG SAID SOUTH LINE 1146.62 FEET TO THE POINT
OF BEGINNING
DOC- 173