HomeMy WebLinkAbout800 .1
GENERAL NOTES
i 1. All work shall be done in accordance with these plans, the City of
ESTIMA
�� �� QUAA1r1;r1E5
Rancho Cucamonga Standards and the Standard Specifications for Public
Works Construction - current edition. Contractor shall be familiar
I TEM DESCR/PTION with and shall be responsible for adherance to these Standards and
QUANTITY UNIT REMARKS Specifications.
1 CI-EARIA16 AND 5/TE PREPARA ;WAI L. 5 ,[..$. 2. All pipelines or substructures of any kind, telephone or power poles,
Z EXCAVAMIV AND GRAD/NG water meters, valves, fire hydrants, etc. shown or not shown on these
3 6" A• C. pAVE/�ENT LgOO S 1= plans within the right-of-way limits or in adjacent areas where
improvement work-is to be done shall be removed, relocated or protected
In place as required at no cost to the City of Rancho Cucamonga.
P. C.C. CURE & GUTTER �B"CF) 350 L.F STD NO 503
3. Any contractor performing work on this project shall familiarize him-
5 RCC. SIDEWALK 07?T ICk) 2074• 5F, STD. NO -704,3101 41 self with the site and shall be solely responsible for any damage to
Z RCC. COMMERCAL DRIVEWAY (55!W) 1 EA. •STD. NO 306 existing facilities resulting directly or indirectly from his opera-
tions, whether or not such facilities are shown on these plans.
7 11A NO/CA P RA MPS Z EA. 5 M N0, 510
i$ 57RtET"L/dyTS -9300L11MEN ?116. V. FA 4. A permit shall be obtained from the City of Rancho Cucamonga Engineering
9 REDWOOD HEADER /'f L•F. Department prior to.-efy encroachment or construction within City of
Rancho Cucamonga easement or right-of-way.
5. All grade stakes shall be set by the Contractor or Engineer. Paving
stakes shall be set at all hinge points, edge of pavement points
within 0.01 foot of sub-grade elevation and at not more than 50 foot
intervals. Additional paving stakes may be required by City Engineer
as needed at warped or vertical curve areas.
6. All sewer, water, electric, gas, phone or other utility laterals.
mains, or crossings shall be constructed prior to paving.
7. Compaction tests of embankment construction, trench backfill, Com-
pacting original ground and all sub-grades shall be performed at no
cost to the City of Rancho Cucamonga. A written report with these
l compaction tests shall be submitted to the City Engineer for approval
1 prigr to the placement of base materials and/or surfacing.
8. At the completion of paving, a materials report shall be submitted to
the City Engineer. Listing all tests or determinations completed to
verify stability oil content and sieve analysis of asphalt surfacing.
9. Prior to installation of any paving, a materials report shall be
f
submitted to the City Engineer.. Listing all tests or determinations
i completed to verify: R-Value, sieve analysis and sand equivalent of
i aggregate base.
i
10. When improvements are to be placed on native soil which consists of a
rocky material, the sub-grade shall be prepared by removing all rocks
which protrude above the sub-grade and all voids or depressions shall
i be filled with a fine grade material of a quality better than the native
material.
11. If the asphalt concrete is to be placed on sub-grade, a soils sterilant
j registered by the E.P.A. for use under A.C. and P.C.C. shall be uniformiy
applied at the manufacturer's recommended rate for the full pavement
width prior to paving.
1
12. Estimate of quantities is provided by the Engineer only for the con-
ventence of the developer, the contractor shall make his own deter-
i
mination of construction quantities before submitting a bid. Any f:
item of work required by these plans which is not specifically listed
i
in the estimate of quantities shall be considered as included in the
r
other items of work.
13. Street signs per City of Rancho Cucamonga Standard Numbers 401 and 402
i
shall be constructed at each intersection.
14. City approval of plans does not relieve the developer from responsibility
for the correction of error and omission discovered during construction.
Upon request the required plan revisions shall be promptly submitted to
the City Engineer for, approval.
15. Work site and exterior streets shall be in a neat, clean, hazard free,
orderly state, throughout construction. Site shall be cleaned upon
request of the inspector.
16. Contact all Utility Companies as required, 48 hours prior to excavation.
Provided for your convenience are the following:
A. San Gabriel Valley Municipal Water District
Mr. Bob Stallings (213) 969-2718
for Base Line Road construction
B. General Telephone (800) 422-4132
for underground service
C. Southern California Gas Company (714) 529-2889
2191 E. Birch Street (714) 529-7070
Brea, CA 92621
'�� D. Cucamonga County Water District (714) 987-2591
9641 San Bernardino Road
B6ASE UNE AYE
Rancho Cucamonga, CA 91730
E. Metropolitan Water District (714) 593-7474
P.O. Box 54153 t
Los
les, CA
CHURCH F. Pacific Telephone 9
Tele honeCom
5T W
p Company (714) 999-5639
PROJECT
Q 5/T.
ARROW Rr
A.T a -4 FIL
77
CITY OF RANCHO CUCAMONGA
VICINITY MAP
.STREET lMPRO!/EMENT PLAN
HA VEN A VENUE
r1rLe 5Heer
4r A* C UP 62-Z4
APPROVED 6Y pew
CITY ENGINEER R.E. NO. 23889
DES IGH TE/SR4AA;E A• LONE f V8M�IENDED
Construction contractor agrees that in accordance with generally accepted construction R.H YT//MACC- A. LA - •
�AV
practices,construction contractor will be required to assume sole and complete responsibility for —
job site conditions during the course of construction of the project,including safety of all personsC �CoUnCil DRAWN CCARCMONr, CA. SHEET
and property, that this requirement shall be made to apply continuously and not be limited to 1HP (7/4) 024—/90(0
3 normal working hours,and construction contractor further agrees to defend,indemnify and hold OfGAEngIneerl —____ �. 1 OF Z
t; ro
design professional harmless from any and all liability, real or alleged, in connection with the
p g $ SUrVotjou CHECKED R.C.Ee8-*8 DRWG. N 0.
performance of work on this project,excepting liability arising from the sole negligence of design
professional. lc//y DATE_ __ FILE NO.e-'4-1014 600-1
° �► Q N ,... :,....._..:._. :. ...... .. . ..__,._..... } _. .. . ._ . .. . ...... .. ...... . ..... ..... .. .
_.. ... ........ .. ....... . .. ._ . ._._.. ..... ............_. ..._. .._ 3 ._....._._. .__..... _....._......_ _. . .. __..._............_ .. .
o o E o n !n•,pnovemen .
`� j j .. .... .... .... ;....:,. .._ ..... ...........,...,. ...,_....,..,.... >:.>.._.....__._.._._. . ; ........,........,,......_...... ..........
.... .
.... ...:.... _...;_, :_...! __ _ ..__...._:... ...._. __.. ............................._.... .Ilk
..
Cli
ty
1 �.
y,
S �• y 5 j 3 ............................... ._........._. .__..
Atj j � •AA y .
o• O ce c� ...... .. .. _.. �._...,.. ....
tiZCb
pnl mow: � Qi O S�il � •, �. � .._.._ . _. _...... .: .. ........ .. :.. , _... : . ... ._:,.. _, . . ........ _.....,, :. ... : .. _
J ..
J-
West R//y �
At
�•
�� _. �, a,..... ..•
0
n o
� n
�2
Li _.. _... ... •A _ ..
an v
J k
� I
r ,
,..._... _._.._.__..._....... _ ..._.._-....
1I
� _... .. ..... .. ......- .. .......
N a� T
� /2;93.7 o I . ... _-. .. . . .. . .... _ .._.. .. �.. ... -... ......... _-..,. .. ..
Bain to •r I ° ..,.. : . .,..,. .. .: .. ,.._._..,. ..., . .. ... - ... ...... . .. .: .._. w :_..._ _.:..----- ._..._. ,. . .- .., .....
fuluic Or � ..
13,00769
in Curb 8• Guh►en � ��,,
f--
.
53.9 5 TC y
N
per 5to'.No.506
01
QIlkf= o' QRS.. �.. .
4. xt. ' _..... .
47 •�7'
G 7" 67'
^0W13773/8E w�&y A Ct'�.... .... ...... i ''p. .. ._..... ___...
w z . �
•A q
(u n b
. R'1
Vol
119,� I n _... . ..., , _..,._. ._.... .-... -..,... y r. yam. _...._ ... .. .. .,. .. ...-. .
-At- ; ' Cps
_.. .... : _... ..
1. a
ft N
ril
/5+-419 y C.R.. `9 . .„.... , .... _ . .
RROQ5775/' w/Buy r
0,198.
274.aJ R/`V? Gotten eg s�dewo/k ��
.r ,
RP,'�'/93006E w/b'ay o-_____•., � ., � � �` / 8.62 �
T.0 `
J
�y
Fu,�are Curb 4
--�— - T T T
30 A/B9°/7 /Z'!(� + +9�/l En. 0-'0700
Arrow R �.
0 70
ARROW
/ 61' O O � f
On '° G '� 000700Arrow Rf•
—49 —
PICs
_:.....
> C c ,h
_ .
_., :_
mz z Z o a _.,:.: ...__:._ ... _.. ...,.__., ............:.
IV
Z D to _._:..... ..
n
.. ......... _-
O a
Zia
Cl
wn C7 _.__ ..,..,,._.,...... .... _ __... .._. _..._ � o .
NytiC
I r SAN O .. ...............::_......, ,......., . �...._. . . ....__... _..... ._.. _...._.. ..__ . ., .....__._.. 1�
L�,.
o 0 O O C ._......-.,..,_............ ........_......_._... _. _ ........._. ......
_.__,..... - ._,..._... �_ . .._-.. th O 0 .