HomeMy WebLinkAbout10-068 - Resolutions RESOLUTION NO. 10-068
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
RANCHO CUCAMONGA ADOPTING ENVIRONMENTAL
FINDINGS PURSUANT TO THE CALIFORNIA
ENVIRONMENTAL QUALITY ACT, CERTIFYING THE FINAL
PROGRAM ENVIRONMENTAL IMPACT REPORT FOR THE
2010 GENERAL PLAN UPDATE (SCH 2000061027),
ADOPTING A STATEMENT OF OVERRIDING
CONSIDERATIONS, AND ADOPTING A MITIGATION
MONITORING AND REPORTING PROGRAM.
A. RECITALS
WHEREAS, the 2010 General Plan Update DRC2007-00869 (the "Project") would
consist of a comprehensive update to the City of Rancho Cucamonga (the "City') General Plan
in accordance with the City's vision for the future and by reinforcing established land uses
attained in the City over the last 10 to 15 years by emphasizing protection of existing residential
neighborhoods and targeting new residential, office and commercial growth along major
corridors (such as Foothill Boulevard) and other areas south of Foothill Boulevard (such as
Haven Avenue) where development opportunities exist on vacant and underutilized properties;
and
WHEREAS, the 2010 General Plan Update would augment the City's economic base by
providing incentive for tax-generating uses to remain in or relocate to the City due to ample
opportunities for development and redevelopment in a well-planned community; and
WHEREAS, pursuant to the California Environmental Quality Act ("CEQA") (Public Res.
Code, § 21000 et seq.) and the State CEQA Guidelines (14 CCR § 15000 et seq.), the City
Council of the City of Rancho Cucamonga ("Council") is the lead agency for the Project, as the
public agency with general governmental powers; and
WHEREAS, the City of Rancho Cucamonga, as lead agency, determined that a
Program Environmental Impact Report ("PEIR") should be prepared pursuant to CEQA in order
to analyze all adverse environmental impacts of the Project; and
WHEREAS, a Notice of Preparation ("NOP") identifying the scope of environmental
issues was distributed to numerous State, federal, and local agencies and organizations on
November 12, 2009, with comments requested by December 11, 2009 pursuant to State CEQA
Guidelines sections 15082(a), 15103 and 15375. A total of eight comment letters were received
and are included in Appendix A of the Draft PEIR ("Draft PEIR"). Relevant comments received
in response to the NOP were incorporated into the Draft PEIR; and
WHEREAS, a public scoping meeting was held at the City of Rancho Cucamonga on
November 23, 2009 and input from the public providing direction and scope of the PEIR was
received; and
WHEREAS, a Draft PEIR was prepared for the Project in accordance with CEQA and
the State CEQA Guidelines, where the City analyzed the Project's environmental impacts; and
WHEREAS, the Draft PEIR was distributed for a 45-day public review period on
February 16, 2010, with the comment period expiring on April 1, 2010. Twelve comment letters
were received during the public comment period. The City prepared written responses to all
comment received on the PEIR, and those responses to comments are incorporated into the
Final PEIR.
The responses to comments were distributed to all public agencies and all individuals that
provided comments during the comment period at least 10 days prior to certification as required
by CEQA; and
WHEREAS, the Final PEIR is comprised of the Draft PEIR, and all appendices thereto,
the comments and responses to comments, and the mitigation monitoring and reporting
program; and
WHEREAS, a Notice of Completion ("NOC") was sent with the Draft PEIR to the State
Clearinghouse on February 16, 2010; and
WHEREAS, the Planning Commission of the City of Rancho Cucamonga held a public
hearing to consider the 2010 General Plan Update, the Final PEIR, and staff recommendations,
on April 28, 2010. Notice of this Planning Commission hearing was provided through
publication on April 5, 2010; and
WHEREAS, the Planning Commission of the City of Rancho Cucamonga after a duly
noticed public hearing, recommended that the City Council certify the Final PEIR and adopt the
findings, statement of overriding considerations, and mitigation monitoring and reporting
program; and
WHEREAS, the City Council of the City of Rancho Cucamonga held a public hearing to
consider the 2010 General Plan Update, the Final PEIR, all comment letters received on the
PEIR, any oral testimony provided, and staff recommendations, on May 19, 2010. Notice of this
City Council hearing was provided through publication on May 3, 2010; and
WHEREAS, as contained herein, the City has endeavored in good faith to set forth the
basis for its decision on the Project; and
WHEREAS, all the requirements of CEQA, the State CEQA Guidelines and the City's
Local CEQA Guidelines have been satisfied in the PEIR, which is sufficiently detailed so that all
of the significant environmental effects of the Project have been adequately evaluated; and
WHEREAS, the findings made in this Resolution are based upon the information and
evidence set forth in the Final PEIR and upon other substantial evidence that has been
presented at the hearings and in the record of the proceedings. The documents, staff reports,
technical studies, appendices, plans, specifications, and other materials that constitute the
record of the proceedings on which this Resolution is based are on file for public examination
during normal business hours at the Planning Department located at City of Rancho
Cucamonga City Hall, 10500 Civic Center Drive, Rancho Cucamonga; and
WHEREAS, the City Council finds that agencies and interested members of the public
have been afforded ample notice and opportunity to comment on the EIR and the Project; and
WHEREAS, Section 15091 of the State CEQA Guidelines requires that the City, before
approving the Project, make one or more of the following written findings for each significant
effect identified in the Final PEIR accompanied by a brief explanation of the rationale for each
finding: (1) Changes or alterations have been required in, or incorporated into, the project which
avoid or substantially lessen the significant environmental effects as identified in the Final EIR;
or, (2) Such changes or alterations are within the responsibility and jurisdiction of another public
agency and not the agency making the finding.
Resolution No. 10-068 - Page 2 of 5
Such changes have been adopted by such other agency or can and should be adopted by such
other agency; or, (3) Specific economic, legal, social, technological, or other considerations,
including provision of employment opportunities for highly trained workers, make infeasible the
mitigation measures or project alternatives identified in the final EIR; and
WHEREAS, Section 15093 of the State CEQA Guidelines requires that if the Project will
cause significant unavoidable adverse impacts, the City must adopt a Statement of Overriding
Considerations prior to approving the project. A Statement of Overriding Considerations states
that any significant adverse project effects are acceptable if expected project benefits outweigh
unavoidable adverse environmental impacts, and
WHEREAS, environmental impacts identified in the Final PEIR as less than significant
and not requiring mitigation are described in Section 3 of Exhibit A, attached hereto and
incorporated herein by this reference; and
WHEREAS, environmental impacts identified in the Final PEIR as significant but which
the City finds can be mitigated to a level of less than significant, through the imposition of
feasible mitigation measures identified in the Final PEIR and set forth herein, are described in
Section 4 of Exhibit A, attached hereto and incorporated herein by this reference; and
WHEREAS, environmental impacts identified in the Final PEIR as significant but which the
City finds cannot be fully mitigated to a level of less than significant, despite the imposition of all
feasible mitigation measures identified in the Final PEIR and set forth herein, are described in
Section 5 of Exhibit A, attached hereto and incorporated herein by this reference; and
WHEREAS, alternatives to the 2010 General Plan Update that might eliminate or reduce
significant environmental impacts are described in Section 6 of Exhibit A, attached hereto and
incorporated herein by this reference; and
WHEREAS, a discussion of the project benefits and a Statement of Overriding
Considerations for the environmental impacts that cannot be fully mitigated to a less than
significant level are set forth in Exhibit B, attached hereto and incorporated herein by this
reference; and
WHEREAS, Public Resources Code Section 21081.6 requires the City to prepare and
adopt a mitigation monitoring and reporting program for any project for which mitigation
measures have been imposed to assure compliance with the adopted mitigation measures. The
Mitigation Monitoring and Reporting Program is attached hereto as Exhibit C, and is hereby
incorporated herein by reference; and
WHEREAS, prior to taking action, the City Council reviewed, considered and has exercised
its independent judgment on the Final PEIR and all of the information and data in the administrative
record, and all oral and written testimony presented to it during meetings and hearings and finds that
the Final PEIR is adequate and was prepared in full compliance with CEQA. No comments or any
additional information submitted to the City have produced any substantial new information requiring
recirculation or additional environmental review of the Project under CEQA; and
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO CUCAMONGA
DOES HEREBY RESOLVE AS FOLLOWS:
B. RESOLUTION
1. The City Council hereby finds that all of the facts set forth in the Recitals, Part A,
of this Resolution are true and correct.
Resolution No. 10-068 - Page 3 of 5
2. The City Council of the City of Rancho Cucamonga hereby certifies the Final
PEIR, adopts findings pursuant to the California Environmental Quality Act, as set forth in
Exhibit A incorporated herein by reference; adopts the Statement of Overriding Considerations
set forth in Exhibit B incorporated herein by reference; adopts the Mitigation Monitoring and
Reporting Program as Exhibit C and incorporated herein by reference, and imposes each
mitigation measure as a condition of Project approval. City staff shall implement and monitor
the mitigation measures as described in Exhibit C. Exhibits A, B, and C are available for review
in the City Clerk's office located at 10500 Civic Center Drive, Rancho Cucamonga, CA 91730.
The Secretary to the City Council shall certify to the adoption of this Resolution.
Please see the following page
for formal adoption,certification and signatures
Resolution No. 10-068 - Page 4 of 5
PASSED, APPROVED, AND ADOPTED this 19th day of May 2010.
AYES: Gutierrez, Kurth, Michael, Spagnolo,Williams
NOES: None
ABSENT: None
ABSTAINED: None
Donald J. Kurth, M.D., Mayor
ATTEST:
nice C. Reynolds, City Cle <
I, JANICE C. REYNOLDS, CITY CLERK of the City of Rancho Cucamonga,
California, do hereby certify that the foregoing Resolution was duly passed, approved and
adopted by the City Council of the City of Rancho Cucamonga, California, at a Regular Meeting
of said City Council held on the 19th day of May 2010.
Executed this 201h day of May 2010, at Rancho Cucamonga, California.
vt�-rte l
nice C. Reynolds, City Merk
Resolution No. 10-068- Page 5 of 5