HomeMy WebLinkAbout2001/02/20 - Agenda Packet• DESIGN REVIEW COMMITTEE MEETING
ACTION AGENDA AND MINUTES
TUESDAY FEBRUARY 20, 2001 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
•
Committee Members: Larry McNiel Pam Stewart
Alternates: Peter Tolstoy Rich Macias
CONSENT CALENDAR
Larry Henderson
John Mannerino
The following items are expected to be routine and non-controversial. Typically they are items such
as plan revisions prepared in response to discussions at a previous meeting.
7:00 p.m.
(Rudy)
7:10 p.m.
(Brent)
A request to modify a previously approved design review for the construction of a
640,300 square foot industrial building to iwo individual buildings totaling
632,000 square feet on 27.75 acres of land in the General Industrial District (Subarea
5) of the Industrial Area Specific Plan, located at the southeast corner of Hermosa
Avenue and 6th Street-APN: 210-072-14, 25, 30, and 37 and 210 371-08.
DEVELOPMENT REVIEW 99-72 MODIFICATION-AMERICAN PACIFIC HOMES-
The modification of home Plans 3 and 4 for previously approved design review of
building elevations and detailed site plan for 78 homes within Tentative Tracts 15911
and 15912 in the Low-Medium Residential District (4-8 dwelling units per acre) of the
Etiwanda Specific Plan, located on the southwest and northeast corner of East
Avenue and the Southern Pacific Railroad right-of-way-APN: 227-131-05 and 227-
141-11 and 12. Related Files: Tentative Tract 15911 and Tentative Tract 15912,
Development Review 99-72, and Variance 99-11.
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant
regarding their development application. The following items do not legally require any public
testimony, although the Committee may open the meeting for public input.
7:20 p.m
(Sal) PRELIMINARY REVIEW 01-02 -COUNTY OF SAN BERNARDINO - A courtesy
review of expansion of the existing Juvenile Housing Facility located in the General
Industrial Designation (Subarea 14), generally located north of 4th Street on the west
side of Etiwanda Avenue -APN: 229-283-70.
7:40 p.m.
(Rudy) ENVIRONMENTAL ASSESSMENTAND DEVELOPMENT REVIEW 00-40-ARROW
& UTICA PARTNERS, LLC -The development of a 27,018 square foot industrial
building on 1.72 acres of vacant land in the General Industrial District (Subarea 8),
located at the southeast corner of Arrow Route and Utica Avenue -APN: 209-491-79.
• DRC AGENDA
February 20, 2001
Page 2
PUBLIC COMMENTS
This is the time and place for the general public to address the Committee. State law prohibits the
Committee from addressing any issue not previously included on the Agenda. The Committee may
receive testimony and set the matter for a subsequent meeting. Comments are limited to five
minutes per individual.
ADJOURNMENT
•
•
CONSENT CALENDAR COMMENTS
7:00 p.m. Rudy Zeledon February 20, 2001
DEVELOPMENT REVIEW 99-77 MODIFICATION-CABOT INDUSTRIALTRUST-A requestto
modify a previously approved design review for the construction of a 640,300 square foot industrial
building to two individual buildings totaling 632,000 square feet on 27.75 acres of land in the
General Industrial District (Subarea 5) of the Industrial Area Specific Plan, located at the southeast
corner of Hermosa Avenue and 6th Street - APN: 210-072-14, 25, 30, and 37 and 210-371-08.
Design Review Committee Action:
Members Present: Larry McNiel, Nancy Fong
Staff Planner Rudy Zeledon
The Committee reviewed the project as a consent item and recommended approval subject to the
following change:
Provide landscaping along the east boundary of Building 2, consistent with Building 1.
r1
LJ
CONSENT CALENDAR COMMENTS
•
7:10 p.m. Brent Le Count February 20, 2001
DEVELOPMENT REVIEW 99-72 MODIFICATION- AMERICAN PACIFIC HOMES -The
modification of home Plans 3 and 4 for previously approved design review of building elevations and
detailed site plan for 78 homes within Tentative Tracts 15911 and 15912 in the Low-Medium
Residential District (4-8 dwelling units per acre) of the Etiwanda Specific Plan, located on the
southwest and northeast corners of East Avenue and the Southern Pacific Railroad right-of-way-
APN: 227-131-05 and 227-141-11 and 12. Related Files: Tentative Tract 15911 and Tentative
Tract 15912, Development Review 99-72, and Variance 99-11.
Design Parameters: The design review was approved by the Planning Commission on April 12,
2000. This approval was appealed to the City Council due to very high walls required for freeway
noise mitigation. The appeal was resolved and the City Council upheld the Commission's decision
on July 19, 2000. The site has been purchased from the previous developer by American Pacific
Homes.
The modification before the Committee involves architectural enhancements to the previously
approved home Plans 3 and 4. American Pacific wishes to modify the interior floor plans and these
changes affect the exterior of the homes. The exterior revisions primarily affect rooflines (though
still hipped), window location and treatment, subtle material application changes, and massing.
Please refer to the exhibits that indicate previously approved elevations and proposed new
elevations for direct comparison. It is staff's opinion that the overall affect of the changes adds
further enhancement to already well-designed homes. The changes do not appear to be related in
any way to cost cutting measures but instead to developing superior home design.
• Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Staff is in full support of the proposed modification.
Recommendation: Staff recommends approval.
Design Review Committee Action:
Members Present: Larry McNiel, Nancy Fong
Staff Planner: Brent Le Count
The Committee recommends approval of the subject architectural revisions.
n
U
DESIGN REVIEW COMMENTS
7:20 p.m. Sal Salazar February 20, 2001
•
PRELIMINARY REVIEW 01-02 -COUNTY OF SAN BERNARDINO - A courtesy review of
expansion of the existing Juvenile Housing Facility located in the General Industrial Designation
(Subarea 14), generally located north of 4th street on the west side of Etiwanda Avenue -
APN: 229-283-70.
Background/Analysis: A small detention facility within the West Valley Detention Center currently
exists on-site and it houses 22 juveniles. The detention facility was constructed in 1996. Since
construction of this facility, the demand forjuvenile detention services in the County has increased.
To meet this demand, the County proposes to expand the existing facility. The proposed facility
expansion consists of five single-story buildings, totaling 65,139 square feet and will accommodate
an additional 160 juveniles. The buildings will be located in the northeast quadrant of the existing
facility, and within the existing perimeter screen wall.
The Design Review Committee and Planning Commission reviewed and commented on the existing
facility in March and April 1996, respectively. The comments generated by the Committee and
Commission were incorporated into the architecture and design of the building.
Staff Comments: The following comments are intended to provide an outline for Committee
discussion:
The architect for the project and the County representative will provide a description of the project
• during the meeting. The description will explain the following:
1. How would the design of the proposed buildings (building materials and colors) compliment
or enhance the existing building?
2. How the facilities (existing and proposed) are screened from Etiwanda Avenue.
Staff Recommendations: Because the application is part of a County owned facility, the City of
Rancho Cucamonga has no jurisdiction of the site and buildings (other than within the public right-
of-way). The applicant has provided some plans as a courtesy review.
Design Review Committee Action:
Members Present: Larry McNiel, Nancy Fong
Staff Planner: Sal Salazar
The County agreed to provide landscaping along Etiwanda Avenue adjacent to the juvenile facility.
The County will coordinate with the City (Engineering Division) for the installment of landscaping
within the City's right-of-way.
r 1
LJ
DESIGN REVIEW COMMENTS
7:40 p.m. Rudy Zeledon February 20, 2001
•
ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-40 -ARROW & UTICA
PARTNERS. LLC -The development of a 27,018 square foot industrial building on 1.72 acres of
vacant land in the General Industrial District (Subarea 8), located at the southeast corner of Arrow
Route and Utica Avenue - APN: 209-491-79.
Background: The Planning Commission approved this project on December 13, 2000. The
applicant would like to present to the Design Review Committee possible building elevation changes
to the approved plans.
Staff will present comments at the meeting.
Design Review Committee Action:
Members Present: Larry McNiel, Nancy Fong
Staff Planner: Rudy Zeledon
The Committee reviewed the proposed changes to the approved elevations for Development
Review 00-40. The Committee provided comments and directed the applicant to work with staff in
resolving design issues discussed at the meeting. The Committee recommended the item be
brought back to the Design Review Committee as a consent item for review and approval.
•
•
DESIGN REVIEW COMMENTS
• FEBRUARY 20, 2001
PUBLIC COMMENTS
There were no public comments at this time.
ADJOURNMENT
The meeting adjourned at 8:00 p.m.
Respectfully submitted,
Brad Buller
Secretary
n
lJ
•
w~
DESIGN REVIEW COMMITTEE MEETING
REVISED AGENDA
TUESDAY FEBRUARY 20, 2001 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
Committee Members: Larry McNiel Pam Stewart
Alternates: Peter Tolstoy Rich Macias
CONSENT CALENDAR
Larry Henderson
John Mannerino
The following items are expected to be routine and non-controversial. Typically they are items such
as plan revisions prepared in response to discussions at a previous meeting.
7:00 p.m.
(Rudy) DEVELOPMENT REVIEW 99-77 MODIFICATION-CABOTINDUSTRIALTRUST-
A request to modify a previously approved design review for the construction of a
640,300 square foot industrial building to two individual buildings totaling
632,000 square feet on 27.75 acres of land in the General Industrial District (Subarea
5) of the Industrial Area Specific Plan, located at the southeast corner of Hermosa
• Avenue and 6th Street-APN: 210-072-14, 25, 30, and 37 and 210 371-08.
7:10 p.m.
(Brent) DEVELOPMENT REVIEW 99-72 MODIFICATION-AMERICAN PACIFIC HOMES-
The modification of home Plans 3 and 4 for previously approved design review of
building elevations and detailed site plan for 78 homes within Tentative Tracts 15911
and 15912 in the Low-Medium Residential District (4-8 dwelling units per acre) of the
Etiwanda Specific Plan, located on the southwest and northeast corner of East
Avenue and the Southern Pacific Railroad right-of-way-APN: 227-131-05 and 227-
141-11 and 12. Related Files: Tentative Tract 15911 and Tentative Tract 15912,
Development Review 99-72, and Variance 99-11.
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant
regarding their development application. The following items do not legally require any public
testimony, although the Committee may open the meeting for public input.
7:20 p.m
(Sal) PRELIMINARY REVIEW 01-02 -COUNTY OF SAN BERNARDINO - A courtesy
review of expansion of the existing Juvenile Housing Facility located in the General
Industrial Designation (Subarea 14), generally located north of 4th Street on the west
side of Etiwanda Avenue -APN: 229-283-70.
7:40 p.m.
• (Rudy) ENVIRONMENTALASSESSMENT AND DEVELOPMENT REVIEW 00-40-ARROW
& UTICA PARTNERS, LLC -The development of a 27,018 square foot industrial
building on 1.72 acres of vacant land in the General Industrial District (Subarea 8),
located at the southeast corner of Arrow Route and Utica Avenue -APN: 209-491-79.
• DRC AGENDA
February 20, 2001
Page 2
PUBLIC COMMENTS
This is the time and place for the general public to address the Committee. State law prohibits the
Committee from addressing any issue not previously included on the Agenda. The Committee may
receive testimony and set the matter for a subsequent meeting. Comments are limited to five
minutes per individual.
ADJOURNMENT
1, Mary Lou Gragg, Office Specialist 11 for the City of Rancho Cucamonga, hereby certify that a true,
accurate copy of the foregoing agenda was posted on February 15, 2001, at least 72 hours prior to
the meeting per Government Code Section 54954.2 at 10500 Civic Center Drive, Rancho
Cucamonga.
•
CONSENT CALENDAR COMMENTS
•
C~
7:00 p.m. Rudy Zeledon February 20, 2001
DEVELOPMENT REVIEW 99-77 MODIFICATION-CABOT INDUSTRIALTRUST-A requestto
modify a previously approved design review for the construction of a 640,300 square foot industrial
building to two individual buildings totaling 632,000 square feet on 27.75 acres of land in the
General Industrial District (Subarea 5) of the Industrial Area Specific Plan, located at the southeast
corner of Hermosa Avenue and 6th Street - APN: 210-072-14, 25, 30, and 37 and 210-371-08.
Design Review Committee Action:
Members Present:
Staff Planner Rudy Zeledon
•
CONSENT CALENDAR COMMENTS
7:10 p.m. Brent Le Count February 20, 2001
•
DEVELOPMENT REVIEW 99-72 MODIFICATION- AMERICAN PACIFIC HOMES -The
modification of home Plans 3 and 4 for previously approved design review of building elevations and
detailed site plan for 78 homes within Tentative Tracts 15911 and 15912 in the Low-Medium
Residential District (4-8 dwelling units per acre) of the Etiwanda Specific Plan, located on the
southwest and northeast corners of East Avenue and the Southern Pacific Railroad right-of-way-
APN: 227-131-05 and 227-141-11 and 12. Related Files: Tentative Tract 15911 and Tentative
Tract 15912, Development Review 99-72, and Variance 99-11.
Design Parameters: The design review was approved by the Planning Commission on April 12,
2000. This approval was appealed to the City Council due to very high walls required for freeway
noise mitigation. The appeal was resolved and the City Council upheld the Commission's decision
on July 19, 2000. The site has been purchased from the previous developer by American Pacific
Homes.
The modification before the Committee involves architectural enhancements to the previously
approved home Plans 3 and 4. American Pacific wishes to modify the interior floor plans and these
changes affect the exterior of the homes. The exterior revisions primarily affect rooflines (though
still hipped), window location and treatment, subtle material application changes, and massing.
Please refer to the exhibits that indicate previously approved elevations and proposed new
elevations for direct comparison. It is staff's opinion that the overall affect of the changes adds
further enhancement to already well-designed homes. The changes do not appear to be related in
any way to cost cutting measures but instead to developing superior home design.
• Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Staff is in full support of the proposed modification.
Recommendation: Staff recommends approval.
Design Review Committee Action:
Members Present:
Staff Planner: Brent Le Count
r1
U
DESIGN REVIEW COMMENTS
7:20 p.m. Sal Salazar February 20, 2001
•
PRELIMINARY REVIEW 01-02 -COUNTY OF SAN BERNARDINO - A courtesy review of
expansion of the existing Juvenile Housing Facility located in the General Industrial Designation
(Subarea 14), generally located north of 4th street on the west side of Etiwanda Avenue -
APN: 229-283-70.
Background/Analysis: A small detention facility within the West Valley Detention Center currently
exists on-site and it houses 22 juveniles. The detention facility was constructed in 1996. Since
construction of this facility, the demand forjuvenile detention services in the County has increased.
To meet this demand, the County proposes to expand the existing facility. The proposed facility
expansion consists of five single-story buildings, totaling 65,139 square feet and will accommodate
an additional 160 juveniles. The buildings will be located in the northeast quadrant of the existing
facility, and within the existing perimeter screen wall.
The Design Review Committee and Planning Commission reviewed and commented on the existing
facility in March and April 1996, respectively. The comments generated by the Committee and
Commission were incorporated into the architecture and design of the building.
Staff Comments: The following comments are intended to provide an outline for Committee
discussion:
The architect for the project and the County representative will provide a description of the project
• during the meeting. The description will explain the following:
1. How would the design of the proposed buildings (building materials and colors) compliment
or enhance the existing building?
How the facilities (existing and proposed) are screened from Etiwanda Avenue.
Staff Recommendations: Because the application is part of a County owned facility, the City of
Rancho Cucamonga has no jurisdiction of the site and buildings (other than within the public right-
of-way). The applicant has provided some plans as a courtesy review.
Design Review Committee Action:
Members Present:
Staff Planner: Sal Salazar
•
DESIGN REVIEW COMMENTS
•
•
7:40 p.m. Rudy Zeledon February 20, 2001
ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-40 -ARROW & UTICA
PARTNERS, LLC -The development of a 27,018 square foot industrial building on 1.72 acres of
vacant land in the General Industrial District (Subarea 8), located at the southeast corner of Arrow
Route and Utica Avenue - APN: 209-491-79.
Background: The Planning Commission approved this project on December 13, 2000. The
applicant would like to present to the Design Review Committee possible building elevation changes
to the approved plans.
Staff will present comments at the meeting.
Design Review Committee Action:
Members Present:
Staff Planner: Rudy Zeledon
DESIGN REVIEW COMMITTEE MEETING
ACTION AGENDA AND MINUTES
TUESDAY FEBRUARY 6, 2001 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
t• J
Committee Members: Larry McNiel Pam Stewart
Alternates: Peter Tolstoy Rich Macias
CONSENT CALENDAR
Larry Henderson
John Mannerino
The following items are expected to be routine and non-controversial. Typically they are items such
as plan revisions prepared in response to discussions at a previous meeting.
7:00 p.m.
(Brent) ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-38 -
CHIPOTLE GRILL - A request to construct a 2,508 square foot restaurant with
495 square feet of outdoor patio area and master plan for a future 2,800 square foot
fast food restaurant with drive-thru on 1.3 acres of land in Subarea 7 (Industrial Park)
of the Industrial Area Specific Plan, located on the south side of Foothill Boulevard
between Aspen Street and Spruce Avenue -APN: 208-352-90. Related File:
Development Review 99-04 (RC Hotel Master Plan).
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant
regarding their development application. The following items do not legally require any public
testimony, although the Committee may open the meeting for public input.
7:10 p.m
(Tom) ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-45 -
ALBERTSON'S EXPRESS - A request to construct a 2,029 a square foot fuel service
and convenience store on 0.71 acres of land in the Community Commercial District
(Foothill Boulevard, Subarea 2), located at the northwest corner of Foothill Boulevard
and Vineyard Avenue -APN: 207-102-49. Related File: Conditional Use
Permit 97-19.
7:30 p.m.
(Doug) ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-65-HOGLE-
IRELAND - A request to construct a 456,274 square foot industrial building on
19.25 acres of land in the General Industrial District (Subarea 5), located west of
Hermosa Avenue and north of 6th Street -APN: 209-211-30 and 31.
7:50 p.m.
(Rudy) ENVIRONMENTAL ASSESSMENT FOR DEVELOPMENT REVIEW 00-76 -
RIVERSIDECOMMERCIAL INVESTORS-A request to construct a 175,291 square
foot multi-tenant industrial building on 9.07 acres of land in the General Industrial
District (Subarea 11) of the Industrial Area Specific Plan, located on the north side of
Sixth Street approximately 300 feet west of Cleveland Avenue -APN: 209-411-12.
DRC AGENDA
February 6, 2001
Page 2
•
PUBLIC COMMENTS
This is the time and place for the general public to address the Committee. State law prohibits the
Committee from addressing any issue not previously included on the Agenda. The Committee may
receive testimony and set the matter for a subsequent meeting. Comments are limited to five
minutes per individual.
ADJOURNMENT
•
LJ
CONSENT CALENDAR COMMENTS
• 7:00 p.m. Brent Le Count February 6, 2001
ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-38-CHIPOTLE GRILL
- A request to construct a 2,508 square foot restaurant with 495 square feet of outdoor patio area
and master plan for a future 2,800 square foot fast food restaurant with drive-thru on 1.3 acres of
land in Subarea 7 (Industrial Park) of the Industrial Area Specific Plan, located on the south side of
Foothill Boulevard between Aspen Street and Spruce Avenue - APN: 208-352-90. Related
File: Development Review 99-04 (RC Hotel Master Plan).
Design Review Committee Action
Members Present: Larry McNiel, Pam Stewart, Larry Henderson
Staff Planner: Brent Le Count
The Committee reviewed and approved the applicant's revised plans
C~
C~
DESIGN REVIEW COMMENTS
. 7:10 p.m. Tom Grahn February 6, 2001
ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-45 - ALBERTSON'S
EXPRESS - A request to construct a 2,029 a square foot fuel service and convenience store on
0.71 acres of land in the Community Commercial District (Foothill Boulevard, Subarea 2), located at
the northwest corner of Foothill Boulevard and Vineyard Avenue - APN: 207-102-49. Related
File: Conditional Use Permit 97-19.
Desion Parameters: The proposed project will occupy one of the drive-thru pads approved with the
application to develop the 10-acre site at the northwest corner of Foothill Boulevard and Vineyard
Avenue. The shopping center was approved under Conditional Use Permit 97-19 that created a
Master Plan for the development of this site. The Master Plan included a 68,355 square foot
supermarket, two satellite pads totaling 5,000 square feet each, and two drive-thru pads totaling
2,500 and 3,500 square feet. The Master Plan addressed conceptual building locations, overall
circulation, access points, parking layout, landscaping, and provided conceptual elevations to
establish an architectural style, and the form, bulk, and height of certain architectural elements. The
master Conditional Use Permit was approved in 1997, and the supermarket-shopping center is
currently under construction. The development of a Jack In the Box restaurant was approved on
one of the drive-thru pads, but construction has not yet begun (Development Review 99-12).
Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Maior Issues: The following broad design issues will be the focus of Committee discussion
• regarding this project:
1. The elevations appear very rigid and should be revised to provide greater variation in
building design. This can be accomplished by providing variation in the building plane,
roofline, and building mass. For example, consider the elevations for Jack In The Box,
which has similar proportions yet creates a building with substantially greater visual interest
(see attached exhibits).
2. Expand the use of architectural elements for greater consistency with the shopping center
design. This could include additional use of native stone, wood trellises, tower elements,
and decorative columns.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
Special decorative paving should be used for the entire pedestrian sidewalk system,
consistent with the approved Master Plan. Including both the enhanced paving adjacent to
the
2. The landscaped area to the' east and west of the building should be revised to include
undulated berming.
3. Increase the size of the canopy columns to a minimum width dimension of 24 inches
4. Increase the size of the cornice element on the canopy for consistency with the primary
building.
C1
DRC COMMENTS
CUP 00-45 - ALBERTSON'S EXPRESS
February 6, 2001
• Page 2
Policv Issues: The following items are a matter of Planning Commission policy and should be
incorporated into the project design without discussion:
The trash enclosure shall be designed for compatibility with the City Standard Drawing.
2. All signs shall be designed to comply with the centers Uniform Sign Program.
Staff Recommendation: Staff recommends the project be designed to comply with the preceding
comments and return to the Committee for further review and consideration.
Design Review Committee Action:
Members Present: Larry McNiel, Pam Stewart, Larry Henderson
Staff Planner: Tom Grahn
The Committee reviewed the project and did not recommend approval. The Committee directed the
applicant to work with staff in resolving the design issues presented at the meeting.
•
~~
DESIGN REVIEW COMMENTS
• 7:30 p.m. Doug Fenn February 6, 2001
ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-65- HOGLE-IRELAND-A
request to construct a 456,274 square foot industrial building on 19.25 acres of land in the General
Industrial District (Subarea 5), located west of Hermosa Avenue and north of 6th Street - APN:
209-211-30 and 31.
Design Parameters: The site contains two vacant and adjacent rectangular shaped parcels that
total 19.25 acres. A stand of mature Eucalyptus trees along Hermosa Avenue were removed as a
result of the City's Capital Improvement program to install a underground storm drain system along
Hermosa Avenue. There is no significant vegetation on the site. The site is currently cultivated as a
vineyard. The site slopes from north to south at an approximately 2 percent. The vacant industrially
designated land surrounds the entire site.
The proposed building is designed to house a single industrial warehouse tenant. The primary
building design and 20,000 square foot office portion of the building will front Hermosa Avenue. The
loading area face is oriented towards the south and does face Hermosa Avenue and staff will
condition that the loading area be screened with an 8-foot high solid screen wall.
The buildings incorporate two primary building materials, however, more sandblasted concrete could
be used (northeast corner of the building). The office portion of the building is well articulated with
strong vertical and horizontals changes and recess to the building plane that are carried throughout
and on all sides of the buildings. Additionally, the public patio areas are designed to be accessible
to the office entryways of the facilities without conflicting with on-site traffic maneuvering areas. The
• color variation of the building is blackthorn and iron house grey, white shadow and cavlier blue
accent squares, color scheme on a primarily concrete tilt-up fapade. There is also vertical sandblast
concrete element along with blue reflective colored glazing accents to help create contrast.
Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Maior Issues: The following broad issues will be on the focus of Committee discussion regarding
this project:
Provide sandblasted concrete at the northeast corner of the building, and design some
movement along the fapade to mimic the office portion of the building at the southeast
corner.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
Provide pedestrian plaza screen wall minimum 3 feet high, around outdoor employee eating
areas.
2. Decorative paving should be installed at the primary entrance (southerly entrance).
3. An 8-foot high solid screen wall must be installed along the south property line to screen the
loading area, and should be architecturally compatible with the building.
Policy Issues: The following items are a matter of Planning Commission policy and should be
• incorporated into the project design without discussion.
No exterior downspouts shall be visible from the adjacent right-of-ways.
DRC COMMENTS
DR 00-65 - HOGLE-IRELAND
February 6, 2001
• Page 2
Staff Recommendation: Staff recommends that the Design Review Committee approve the project
subject to the modifications as recommend above.
Design Review Committee Action:
Members Present: Larry McNiel, Pam Stewart, Larry Henderson
Staff Planner: Doug Fenn
Project approved subject to direction of the Design Review Committee.
•
•
DESIGN REVIEW COMMENTS
• 7:50 p.m. Rudy Zeledon February 6, 2001
ovvinvivrvi~ivin~ r~oo~oomuvi rvn v~vcwrmovi n~viwv w-iv - niv~n~iv~
COMMERCIAL INVESTORS -A request to construct a 175,291 square foot multi-tenant industrial
building on 9.07 acres of land in the General Industrial District (Subarea 11) of the Industrial Area
Specific Plan, located on the north side of Sixth Street approximately 300 feet west of Cleveland
Avenue - APN: 209-411-12.
Design Parameters: The site contains one vacant parcel that is 2.17 acres. The site slopes from
north to south about at approximately 2 to 4 percent and is currently cultivated as a vineyard. There
are no mature trees on the site nor is there any significant vegetation on the site. The site is located
within an area identified as potential habitat for the Delhi Sands Flower Loving Fly. The applicant
has submitted a biological Survey for the site. The street frontages along Sixth Street are
unimproved with no curb and gutter, sidewalk or street side landscaping. There is an existing drive
approach at the southwest corner of the site that will be shared with the industrial property to the
west. The project site is bordered to the north, south (across 6th street), and east by existing
industrial development. To the west is an existing industrial complex and vacant land north of the
complex.
The proposed multi-tenant industrial building will be oriented on a north and south axis. The
building incorporates primary building materials: painted and sandblasted concrete. Secondary
design material accents such colored panel reveal bands, and blue reflective glazed glass is also
• proposed. The building design is consistent with the architectural style of industrial park district in
which it is located. The office portions of the multi-tenant building will be along the southeast corner,
northeast corner, and east areas of the building. The office elevations feature a well articulated
building surface, with vertical and horizontal changes to the building plane, color variation and use of
sandblasted concrete with blue reflective colored glass accents. The building plane along the north
and west elevations will feature horizontal panel reveal bands (painted gray) and an arched scored
reveal design theme between each building panel. The loading area of the building is proposed
along the west area of the building.
Staff Comments: The following comments are intended to provide ant outline for Committee
discussion:
Maior Issues: The following broad issues will be on the focus of Committee discussion regarding this
project:
Staff has no major issues with this project the applicant has worked with staff in addressing
earlier issues and staff is pleased with the outcome.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
The proposed 8-foot wrought iron fence, along the west property line, should be replaced
with a solid 8-foot wall to ensure proper screening of the truck loading area.
2. The 5-foot landscaped planter, adjacent to the building at northeast corner, should be
• continued along the entire north elevation and length of the parking row. In addition, a
landscaped planter (a minimum 5-foot inside dimension) should be provided at the end of
the parking row to provide a buffer between truck and vehicle traffic.
DRC COMMENTS
DR 00-76 -RIVERSIDE COMMERCIAL INVESTORS
February 6, 2001
• Page 2
3. A Landscaped planter (a minimum 5-foot inside dimension) should be provided at the end
of the parking row at the northwest corner of the site to provide a buffer between truck and
vehicle parking.
4. To maintain a required setback of 5 feet from property line, all proposed trash enclosure
locations should be setback 5 feet from property line. In addition a landscape strip (a
minimum 5-foot inside dimension), on both sides of the trash enclosures shall be provided
as a buffer.
Staff Recommendations: Staff recommends that the Design Review Committee approve the
project subject to the conditions as recommended above.
Design Review Committee Action:
Members Present: Peter Tolstoy, Pam Stewart, Larry Henderson
Staff Planner: Rudy Zeledon
The Committee reviewed the project and recommended approval subject to staff's comments with
the following change:
• 1. The proposed 8-foot wrought iron fence, along the west property line, will provide adequate
screening and therefore is approved as shown on the proposal.
•
DESIGN REVIEW COMMENTS
•
February 6, 2001
PUBLIC COMMENTS
There were no public comments at this time.
ADJOURNMENT
The meeting adjourned at 8:00 p.m.
Respectfully submitted,
Br d Buller
Secretary
•
•
DESIGN REVIEW COMMITTEE MEETING
TUESDAY FEBRUARY 6, 2001 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
u
•
Committee Members: Larry McNiel Pam Stewart
Alternates: Peter Tolstoy Rich Macias
CONSENT CALENDAR
Larry Henderson
John Mannerino
The following items are expected to be routine and non-controversial. Typically they are items such
as plan revisions prepared in response to discussions at a previous meeting.
7:00 p.m.
(Brent) ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-38 -
CHIPOTLE GRILL - A request to construct a 2,508 square foot restaurant with
495 square feet of outdoor patio area and master plan for a future 2,800 square foot
fast food restaurant with drive-thru on 1.3 acres of land in Subarea 7 (Industrial Park)
of the Industrial Area Specific Plan, located on the south side of Foothill Boulevard
between Aspen Street and Spruce Avenue -APN: 208-352-90. Related File:
Development Review 99-04 (RC Hotel Master Plan).
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant
regarding their development application. The following items do not legally require any public
testimony, although the Committee may open the meeting for public input.
7:10 p.m
(Tom) ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-45 -
ALBERTSON'S EXPRESS -A request to construct a 2,029 a square foot fuel service
and convenience store on 0.71 acres of land in the Community Commercial District
(Foothill Boulevard, Subarea 2), located at the northwest corner of Foothill Boulevard
and Vineyard Avenue -APN: 207-102-49. Related File: Conditional Use
Permit 97-19.
7:30 p.m.
(Doug) ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-65-HOGLE-
IRELAND - A request to construct a 456,274 square foot industrial building on
19.25 acres of land in the General Industrial District (Subarea 5) of the Industrial Area
Specific Plan, located west of Hermosa Avenue and north of 6th Street -
APN: 209-211-30 and 31.
7:50 p.m.
(Rudy) ENVIRONMENTAL ASSESSMENT FOR DEVELOPMENT REVIEW 00-76-CABOT
INDUSTRIAL TRUST - A request to construct a 175,291 square foot multi-tenant
industrial building on 9.07 acres of land in the General Industrial District (Subarea 11)
of the Industrial Area Specific Plan, located on the north side of Sixth Street
approximately 300 feet west of Cleveland Avenue -APN: 209-411-12.
• DRC AGENDA
February 6, 2001
Page 2
PUBLIC COMMENTS
This is the time and place for the general public to address the Committee. State law prohibits the
Committee from addressing any issue not previously included on the Agenda. The Committee may
receive testimony and set the matter for a subsequent meeting. Comments are limited to five
minutes per individual.
ADJOURNMENT
1, Mary Lou Gragg, Office Specialist 11 for the City of Rancho Cucamonga, hereby certify that a true,
accurate copy of the foregoing agenda was posted on February 1, 2001, at least 72 hours prior to
the meeting per Government Code Section 54954.2 at 10500 Civic Center Drive, Rancho
Cucamonga. n
•
U
CONSENT CALENDAR COMMENTS
• 7:00 p.m. Brent Le Count February 6, 2001
ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-38-CHIPOTLE GRILL
- A request to construct a 2,508 square foot restaurant with 495 square feet of outdoor patio area
and master plan for a future 2,800 square foot fast food restaurant with drive-thru on 1.3 acres of
land in Subarea 7 (Industrial Park) of the Industrial Area Specific Plan, located on the south side of
Foothill Boulevard between Aspen Street and Spruce Avenue - APN: 208-352-90. Related
File: Development Review 99-04 (RC Hotel Master Plan).
Design Review Committee Action
Members Present:
Staff Planner: Brent Le Count
r1
LJ
r
LJ
DESIGN REVIEW COMMENTS
• 7:10 p.m. Tom Grahn February 6, 2001
ENVIRONMENTAL ASSESSMENT AND CONDITIONAL USE PERMIT 00-45 - ALBERTSON'S
EXPRESS - A request to construct a 2,029 a square foot fuel service and convenience store on
0.71 acres of land in the Community Commercial District (Foothill Boulevard, Subarea 2), located at
the northwest corner of Foothill Boulevard and Vineyard Avenue - APN: 207-102-49. Related
File: Conditional Use Permit 97-19.
Design Parameters: The proposed project will occupy one of the drive-thru pads approved with the
application to develop the 10-acre site at the northwest corner of Foothill Boulevard and Vineyard
Avenue. The shopping center was approved under Conditional Use Permit 97-19 that created a
Master Plan for the development of this site. The Master Plan included a 68,355 square foot
supermarket, two satellite pads totaling 5,000 square feet each, and two drive-thru pads totaling
2,500 and 3,500 square feet. The Master Plan addressed conceptual building locations, overall
circulation, access points, parking layout, landscaping, and provided conceptual elevations to
establish an architectural style, and the form, bulk, and height of certain architectural elements. The
master Conditional Use Permit was approved in 1997, and the supermarket-shopping center is
currently under construction. The development of a Jack In the Box restaurant was approved on
one of the drive-thru pads, but construction has not yet begun (Development Review 99-12).
Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Maior Issues: The following broad design issues will be the focus of Committee discussion
• regarding this project:
1. The elevations appear very rigid and should be revised to provide greater variation in
building design. This can be accomplished by providing variation in the building plane,
roofline, and building mass. For example, consider the elevations for Jack In The Box,
which has similar proportions yet creates a building with substantially greatervisual interest
(see attached exhibits).
Expand the use of architectural elements for greater consistency with the shopping center
design. This could include additional use of native stone, wood trellises, tower elements,
and decorative columns.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
1. Special decorative paving should be used for the entire pedestrian sidewalk system,
consistent with the approved Master Plan. Including both the enhanced paving adjacent to
the
2. The landscaped area to the east and west of the building should be revised to include
undulated berming.
3. Increase the size of the canopy columns to a minimum width dimension of 24 inches
4. Increase the size of the cornice element on the canopy for consistency with the primary
building.
•
DRC COMMENTS
CUP 00-45 - ALBERTSON'S EXPRESS
February 6, 2001
• Page 2
Policv Issues: The following items are a matter of Planning Commission policy and should be
incorporated into the project design without discussion:
The trash enclosure shall be designed for compatibility with the City Standard Drawing.
2. All signs shall be designed to comply with the centers Uniform Sign Program.
Staff Recommendation: Staff recommends the project be designed to comply with the preceding
comments and return to the Committee for further review and consideration.
Design Review Committee Action:
Members Present:
Staff Planner: Tom Grahn
•
•
DESIGN REVIEW COMMENTS
• 7:30 p.m. Doug Fenn February 6, 2001
ENVIRONMENTAL ASSESSMENT AND DEVELOPMENT REVIEW 00-65 - HOGLE-IRELAND -A
request to construct a 456,274 square foot industrial building on 19.25 acres of land in the General
Industrial District (Subarea 5) of the Industrial Area Specific Plan, located west of Hermosa Avenue
and north of 6th Street - APN: 209-211-30 and 31.
Design Parameters: The site contains two vacant and adjacent rectangular shaped parcels that
total 19.25 acres. A stand of mature Eucalyptus trees along Hermosa Avenue were removed as a
result of the City's Capital Improvement program to install a underground storm drain system along
Hermosa Avenue. There is no significant vegetation on the site. The site is currently cultivated as a
vineyard. The site slopes from north to south at an approximately 2 percent. The vacant industrially
designated land surrounds the entire site.
The proposed building is designed to house a single industrial warehouse tenant. The primary
building design and 20,000 square foot office portion of the building will front Hermosa Avenue. The
loading area face is oriented towards the south and does face Hermosa Avenue and staff will
condition that the loading area be screened with an 8-foot high solid screen wall.
The buildings incorporate two primary building materials, however, more sandblasted concrete could
be used (northeast corner of the building). The office portion of the building is well articulated with
strong vertical and horizontals changes and recess to the building plane that are carried throughout
and on all sides of the buildings. Additionally, the public patio areas are designed to be accessible
to the office entryways of the facilities without conflicting with on-site traffic maneuvering areas. The
• color variation of the building is blackthorn and iron house grey, white shadow and cavlier blue
accent squares, color scheme on a primarily concrete tilt-up facade. There is also vertical sandblast
concrete element along with blue reflective colored glazing accents to help create contrast.
Staff Comments: The following comments are intended to provide an outline for Committee
discussion.
Maior Issues: The following broad issues will be on the focus of Committee discussion regarding
this project:
Provide sandblasted concrete at the northeast corner of the building, and design some
movement along the facade to mimic the office portion of the building at the southeast
corner.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
Provide pedestrian plaza screen wall minimum 3 feet high, around outdooremployee eating
areas.
Decorative paving should be installed at the primary entrance (southerly entrance).
An 8-foot high solid screen wall must be installed along the south property line to screen the
loading area, and should be architecturally compatible with the building.
• Policy Issues: The following items are a matter of Planning Commission policy and should be
incorporated into the project design without discussion.
No exterior downspouts shall be visible from the adjacent right-of-ways.
DRC COMMENTS
DR 00-65 - HOGLE-IRELAND
February 6, 2001
• Page 2
Staff Recommendation: Staff recommends that the Design Review Committee approve the project
subject to the modifications as recommend above.
Design Review Committee Action:
Members Present:
Staff Planner: Doug Fenn
n
U
U
DESIGN REVIEW COMMENTS
• 7:50 p.m. Rudy Zeledon February 6, 2001
ENVIRONMENTAL ASSESSMENT FOR DEVELOPMENT REVIEW 00-76-CABOT INDUSTRIAL
TRUST-A request to construct a 175,291 square foot multi-tenant industrial building on 9.07 acres
of land in the General Industrial District (Subarea 1 1) of the Industrial Area Specific Plan, located on
the north side of Sixth Street approximately 300 feet west of Cleveland Avenue - APN: 209-411-12.
Desiqn Parameters: The site contains one vacant parcel that is 2.17 acres. The site slopes from
north to south about at approximately 2 to 4 percent and is currently cultivated as a vineyard. There
are no mature trees on the site nor is there any significant vegetation on the site. The site is located
within an area identified as potential habitat for the Delhi Sands Flower Loving Fly. The applicant
has submitted a biological Survey for the site. The street frontages along Sixth Street are
unimproved with no curb and gutter, sidewalk or street side landscaping. There is an existing drive
approach at the southwest corner of the site that will be shared with the industrial property to the
west. The project site is bordered to the north, south (across 6th street), and east by existing
industrial development. To the west is an existing industrial complex and vacant land north of the
complex.
The proposed multi-tenant industrial building will be oriented on a north and south axis. The
building incorporates primary building materials: painted and sandblasted concrete. Secondary
design material accents such colored panel reveal bands, and blue reflective glazed glass is also
proposed. The building design is consistent with the architectural style of industrial park district in
• which it is located. The office portions of the multi-tenant building will be along the southeast corner,
northeast corner, and east areas of the building. The office elevations feature a well articulated
building surface, with vertical and horizontal changes to the building plane, color variation and use of
sandblasted concrete with blue reflective colored glass accents. The building plane along the north
and west elevations will feature horizontal panel reveal bands (painted gray) and an arched scored
reveal design theme between each building panel. The loading area of the building is proposed
along the west area of the building.
Staff Comments: The following comments are intended to provide ant outline for Committee
discussion:
Maior Issues: The following broad issues will be on the focus of Committee discussion regarding this
project:
Staff has no major issues with this project the applicant has worked with staff in addressing
earlier issues and staff is pleased with the outcome.
Secondary Issues: Once all of the major issues have been addressed, and time permitting, the
Committee will discuss the following secondary design issues:
The proposed 8-foot wrought iron fence, along the west property line, should be replaced
with a solid 8-foot wall to ensure proper screening of the truck loading area.
2. The 5-foot landscaped planter, adjacent to the building at northeast corner, should be
continued along the entire north elevation and length of the parking row. In addition, a
• landscaped planter (a minimum 5-foot inside dimension) should be provided at the end of
the parking row to provide a buffer between truck and vehicle traffic.
DRC COMMENTS
DR 00-76 -CABOT INDUSTRIAL TRUST
February 6, 2001
• Page 2
3. A Landscaped planter (a minimum 5-foot inside dimension) should be provided at the end
of the parking row at the northwest corner of the site to provide a buffer between truck and
vehicle parking.
4. To maintain a required setback of 5 feet from property line, all proposed trash enclosure
locations should be setback 5 feet from property line. In addition a landscape strip (a
minimum 5-foot inside dimension), on both sides of the trash enclosures shall be provided
as a buffer.
Staff Recommendations: Staff recommends that the Design Review Committee approve the
project subject to the conditions as recommended above.
Design Review Committee Action:
Members Present:
Staff Planner: Rudy Zeledon
\J
•