HomeMy WebLinkAbout03-129 - Resolutions RESOLUTION NO. 03-129
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
RANCHO CUCAMONGA, CALIFORNIA,APPROVING THE MODIFICATION
OF CONDITIONAL USE PERMIT DRC2002-00653, FOR THE
MODIFICATION TO CHANGE A CARPORT INTO AN ENCLOSED
1,200 SQUARE FOOT STORAGE BUILDING INCLUDING HAZARDOUS
MATERIALS, FOR AN APPROVED FIRE STATION NO. 173 ON
2.46 ACRES OF LAND IN THE LOW-MEDIUM RESIDENTIAL DISTRICT
(4-8 DWELLING UNITS PER ACRE) OF THE VICTORIA COMMUNITY
PLAN, LOCATED AT THE SOUTHWEST CORNER OF DAY CREEK
BOULEVARD AND THE SOUTHERN PACIFIC RAILROAD RIGHT-OF-WAY,
AND MAKING FINDINGS IN SUPPORT THEREOF -APN: 1089-031-18.
A. Recitals.
1. The Rancho Cucamonga Fire Protection District filed an application for approval of a
Modification of Conditional Use Permit DRC2002-00653, as described in the title of this Resolution.
Hereinafter in this Resolution, the subject Conditional Use Permit request is referred to as "the
application."
2. On the 10th day of September 2003, the Planning Commission of the City of Rancho
Cucamonga conducted a duly noticed public hearing on the application and concluded said hearing
on that date.
3. All legal prerequisites prior to the adoption of this Resolution have occurred.
B. Resolution.
NOW, THEREFORE, it is hereby found, determined, and resolved bythe Planning Commission
of the City of Rancho Cucamonga as follows:
1. This Commission hereby specifically finds that all of the facts set forth in the Recitals,
Part A, of this Resolution are true and correct.
2. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing on September 10, 2003, including written and oral staff reports, together
with public testimony, this Commission hereby specifically finds as follows:
a. The application applies to property located on the west side of Day Creek Boulevard
between Base Line Road and the Pacific Electric Railroad right-of-way, with a street frontage of
approximately 250 feet and a lot depth of 320 feet, and is presently vacant; and
b. The property to the north is an existing residential development, the properties to
the south and west are currently vacant and undeveloped, and to the east is Day Creek Boulevard;
and
C. The development of a Fire Station is consistent with the objectives of the General
Plan pertaining to the provision of adequate levels of service.
3. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing and upon the specific findings of facts set forth in paragraphs 1 and 2
above, this Commission hereby finds and concludes as follows:
PLANNING COMMISSION RESOLUTION NO. 03-129
DRC2002-00653— RC FIRE PROTECTION DISTRICT
September 10, 2003
Page 2
a. The Conditional Use Permit is consistent with the General Plan, Development
Code; and the Victoria Community Plan; and
b. The design or improvements of the project is consistent with the General Plan,
Development Code, and the Victoria Community Plan; and
C. The site is physically suitable for the type of development proposed; and
d. The design of the proposed project will not cause substantial environmental
damage and avoidable injury to humans and wildlife or their habitat; and
e. The proposed project is not likely to cause serious public health problems.
4. Based upon the facts and information contained in the proposed Negative Declaration,
together with all written and oral reports included for the environmental assessment for the
application, the Planning Commission finds that there is no substantial evidence that the project will
have a significant effect upon the environment and adopts a Negative Declaration, based upon the
findings as follows:
a. That the Negative Declaration has been prepared in compliance with the California
Environmental Quality Act of 1970, as amended, and the State CEQA guidelines promulgated
thereunder; that said Negative Declaration and the Initial Study prepared therefore reflect the
independent judgment of the Planning Commission; and,further, this Commission has reviewed and
considered the information contained in said Negative Declaration with regard to the application.
b. That, based upon the changes and alterations which have been incorporated into the
proposed project, no significant adverse environmental effects will occur.
c. Pursuant to the provisions of Section 753.5(c) of Title 14 of the California Code of
Regulations, the Planning Commission finds as follows: In considering the record as a whole, the
Initial Study and Negative Declaration for the project, there is no evidence that the proposed project
will have potential for an adverse impact upon wildlife resources or the habitat upon which wildlife
depends. Further, based upon the substantial evidence contained in the Negative Declaration, the
staff reports and exhibits, and the information provided to the Planning Commission during the public
hearing, the Planning Commission hereby rebuts the presumption of adverse effect as set forth in
Section 753.5(c-1-d) of Title 14 of the California Code of Regulations.
d. The applicant is already required to implement all mitigation measures contained in
the Mitigated Negative Declaration adopted by Planning Commission Resolution No. 02-109.
5. Based upon the findings and conclusions set forth in paragraphs 1, 2, 3, and 4 above,
this Commission hereby approves the application subject to each and every condition set forth
below:
Planning Division
1) All conditions of approval as adopted by Planning Commission
Resolution No. 02-109, including the Standard Conditions attached
thereto, shall apply.
PLANNING COMMISSION RESOLUTION NO. 03-129
DRC2002-00653— RC FIRE PROTECTION DISTRICT
September 10, 2003
Page 3
2) Walls shall be decorative and shall comply with setback and design
requirements of the Victoria Community Plan and Day Creek Boulevard.
3) Where rock cobble is used, it shall be real river rock.
Engineering Division
1) Provide a Parcel Map or Lot Line Adjustment with a separate
instrument for dedication of Oak Creek Court, Day Creek Boulevard,
and Base Line Road.
2) Day Creek Boulevard frontage shall be improved in accordance with
City"Major Divided Arterial' standards and are required, including but
not limited to, protect existing curb and gutter or repair as required,
sidewalk, streetlights, street trees, signs, and striping.
3) Provide a traffic signal at the intersection of Day Creek Boulevard and
Oak Creek Court, and direct the City Engineer to evaluate safe
movements of intersection traffic flow.
4) Oak Creek Court shall be improved in accordance with City"Collector"
standards as required, including but not limited to, curb and gutter,
sidewalk, pavement, driveway approaches, streetlights, and street
trees, signs, and striping.
5) Install the storm drain per the approved City drawings to the satisfaction
of the City Engineer from Oak Creek Court southerly to the existing
storm drain in Base Line Road. Provide a storm drain easement or
acceptance letter for the drainage from Oak Creek Court.
6) The proposed project may be subject to pay its fair share
reimbursement costs for street improvements along Day Creek
Boulevard and storm drain improvements pending the submittal of a
reimbursement agreement from adjacent developers.
7) The Pacific Electric Inland Empire Trail shall loop down along Day
Creek Boulevard to Oak Creek Court within a 25-foot wide parkway for
trail purposes.
8) As a public facility, the site will be required to generally follow
Landscape Maintenance District design requirements on-site as well as
off site. The landscape architect should contact City staff.
6. The Secretary to this Commission shall certify to the adoption of this Resolution.
APPROVED AND ADOPTED THIS 10TH DAY OF SEPTEMBER 2003.
PLANNING COMMISSION OF THE CITY OF RANCHO CUCAMONGA
PLANNING COMMISSION RESOLUTION NO. 03-129
DRC2002-00653— RC FIRE PROTECTION DISTRICT
September 10, 2003
Page 4
BY '
Larry T. cN el, Vice Chairman
ATTEST:
rad B H r cretary
1, Brad Buller, Secretary of the Planning Commission of the City of Rancho Cucamonga, do hereby
certify that the foregoing Resolution was duly and regularly introduced, passed, and adopted by the
Planning Commission of the City of Rancho Cucamonga, at a regular meeting of the Planning
Commission held on the 10th day of September 2003, by the following vote-to-wit:
AYES: COMMISSIONERS: McNIEL, McPHAIL, STEWART
NOES: COMMISSIONERS: NONE
ABSENT: COMMISSIONERS: FLETCHER, MACIAS
COMMUNITY DEVELOPMENT
DEPARTMENT
STANDARD CONDITIONS
PROJECT#: DRC2002-00653
SUBJECT: FIRE STATION NO. 173
APPLICANT: RANCHO CUCAMONGA FIRE PROTECTION DISTRICT
WEST SIDE OF DAY CREEK BOULEVARD BETWEEN BASE LINE ROAD AND THE PACIFIC
LOCATION: ELECTRIC RAILROAD RIGHT-OF-WAY
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
APPLICANT SHALL CONTACT THE PLANNING DIVISION,(909)477-2750, FOR COMPLIANCE
WITH THE FOLLOWING CONDITIONS:
A. General Requirements Completion Date
1. The applicant shall agree to defend at his sole expense any action brought against the City, its —j—j_
agents,officers,or employees,because of the issuance of such approval,or in the alternative,to
relinquish such approval. The applicant shall reimburse the City, its agents, officers, or
employees, for any Court costs and attorneys fees which the City, its agents, officers, or
employees may be required by a court to pay as a result of such action. The City may,at its sole
discretion,participate at its own expense in the defense of any such action but such participation
shall not relieve applicant of his obligations under this condition.
2. Copies of the signed Planning Commission Resolution of Approval No. 03-129, Standard —J--L—
Conditions, and all environmental mitigations shall be included on the plans (full size). The
sheet(s) are for information only to all parties involved in the construction/grading activities and
are not required to be wet sealed/stamped by a licensed Engineer/Architect.
B. Time Limits
1. Conditional Use Permit, Variance, or DevelopmenVDesign Review approval shall expire if
building permits are not issued or approved use has not commenced within 5 years from the date
of approval. No extensions are allowed.
C. Site Development
1. The site shall be developed and maintained in accordance with the approved plans,which include
site plans,architectural elevations,exterior materials and colors,landscaping,sign program,and
grading on file in the Planning Division, the conditions contained herein, Development Code
regulations, and the Victoria Community Plan.
SC-07-03 1
Project No.DRC2002-00653
Completion Date
2. Prior to any use of the project site or business activity being commenced thereon,all Conditions
of Approval shall be completed to the satisfaction of the City Planner.
3. Occupancy of the facilities shall not commence until such time as all Uniform Building Code and
State Fire Marshal regulations have been complied with. Prior to occupancy, plans shall be
submitted to the Rancho Cucamonga Fire Protection District and the Building and Safety Division
to show compliance. The buildings shall be inspected for compliance prior to occupancy.
4. Revised site plans and building elevations incorporating all Conditions of Approval shall be
submitted for City Planner review and approval prior to the issuance of building permits.
5. All site, grading, landscape, irrigation, and street improvement plans shall be coordinated for
consistency prior to issuance of any permits (such as grading, tree removal, encroachment,
building, etc.) or prior to final map approval in the case of a custom lot subdivision,or approved
use has commenced, whichever comes first.
6. Approval of this request shall not waive compliance with all sections of the Development Code,all
other applicable City Ordinances, and applicable Community or Specific Plans in effect at the
time of building permit issuance.
7. A detailed on-site lighting plan,including a photometric diagram,shall be reviewed and approved
by the City Planner and Police Department(477-2800) prior to the issuance of building permits.
Such plan shall indicate style,illumination, location, height,and method of shielding so as not to
adversely affect adjacent properties.
8. Trash receptacle(s)are required and shall meet City standards. The final design,locations,and
the number of trash receptacles shall be subject to City Planner review and approval prior to the
issuance of building permits.
9. All ground-mounted utility appurtenances such as transformers, AC condensers, etc., shall be
located out of public view and adequately screened through the use of a combination of concrete
or masonry walls,berm ing,and/or landscaping to the satisfaction of the City Planner. For single-
family residential developments, transformers shall be placed in underground vaults.
10. All building numbers and individual units shall be identified in a clear and concise manner,
including proper illumination.
11. Six-foot decorative block walls shall be constructed along the project perimeter. If a double wall
condition would result, the developer shall make a good faith effort to work with the adjoining
property owners to provide a single wall. Developer shall notify, by mail,all contiguous property
owner at least 30 days prior to the removal of any existing walls/fences along the project's
perimeter.
12. Where rock cobble is used, it shall be real river rock. Other stone veneers may be manufactured
products.
D. Building Design
1. All roof appurtenances, including air conditioners and other roof mounted equipment and/or
projections, shall be shielded from view and the sound buffered from adjacent properties and
streets as required by the Planning Division. Such screening shall be architecturally integrated
with the building design and constructed to the satisfaction of the City Planner. Details shall be
included in building plans.
E. Parking and Vehicular Access (indicate details on building plans)
1. All parking spaces shall be 9 feet wide by 18 feet long. When a side of any parking space abuts _/_J_
a building, wall, support column, or other obstruction, the space shall be a minimum of 11 feet
wide.
SC-07-03 2
Project No.DRC2002-00653
Completion Date
2. All parking lot landscape islands shall have a minimum outside dimension of 6 feet and shall
contain a 12-inch walk adjacent to the parking stall (including curb).
3. All parking spaces shall be double striped per City standards and all driveway aisles,entrances,
and exits shall be striped per City standards.
F. Trip Reduction
1. Bicycle storage spaces shall be provided in all commercial, office, industrial, and multifamily
residential projects of more than 10 units. Minimum spaces equal to five percent of the required
automobile parking spaces or three bicycle storage spaces,whichever is greater. After the first
50 bicycle storage spaces are provided,additional storage spaces required are 2.5 percent of the
required automobile parking spaces. Warehouse distribution uses shall provide bicycle storage
spaces at a rate of 2.5 percent of the required automobile parking spaces with a minimum of a
3-bike rack. In no case shall the total number of bicycle parking spaces required exceed 100.
Where this results in a fraction of 0.5 or greater, the number shall be rounded off to the higher
whole number.
G. Landscaping
1. A detailed landscape and irrigation plan, including slope planting and model home landscaping in
the case of residential development, shall be prepared by a licensed landscape architect and
submitted for City Planner review and approval prior to the issuance of building permits or prior
final map approval in the case of a custom lot subdivision.
2. Within parking lots,trees shall be planted at a rate of one 15-gallon tree for every three parking
stalls.
3. Trees shall be planted in areas of public view adjacent to and along structures at a rate of one
tree per 30 linear feet of building.
4. All private slopes of 5 feet or more in vertical height and of 5:1 or greater slope,but less than 2:1
slope,shall be,at minimum,irrigated and landscaped with appropriate ground cover for erosion
control. Slope planting required by this section shall include a permanent irrigation system to be
installed by the developer prior to occupancy.
5. All private slopes in excess of 5 feet, but less than 8 feet in vertical height and of 2:1 or greater
slope shall be landscaped and irrigated for erosion control and to soften their appearance as
follows: one 15-gallon or larger size tree per each 150 sq.ft.of slope area 1-gallon or larger size
shrub per each 100 sq.ft.of slope area,and appropriate ground cover. In addition,slope banks
in excess of 8 feet in vertical height and 2:1 or greater slope shall also include one 5-gallon or
larger size tree per each 250 sq. ft. of slope area. Trees and shrubs shall be planted in
staggered clusters to soften and vary slope plane. Slope planting required by this section shall
include a permanent irrigation system to be installed by the developer prior to occupancy.
6. The final design of the perimeter parkways,walls,landscaping,and sidewalks shall be included in
the required landscape plans and shall be subject to City Planner review and approval and
coordinated for consistency with any parkway landscaping plan which may be required by the
Engineering Division.
7. Special landscape features such as mounding, alluvial rock, specimen size trees, meandering
sidewalks (with horizontal change), and intensified landscaping, is required along along Day
Creek Boulevard.
8. Landscaping and irrigation systems required to be installed within the public right-of-way on the
perimeter of this project area shall be continuously maintained by the developer.
9. All walls shall be provided with decorative treatment. If located in public maintenance areas,the
design shall be coordinated with the Engineering Division.
SC-07-03 3
Project No.DRC2002-00653
completion Date
10. Landscaping and irrigation shall be designed to conserve water through the principles of
Xeriscape as defined in Chapter 19.16 of the Rancho Cucamonga Municipal Code.
H. Signs
1. The signs indicated on the submitted plans are conceptual only and not a part of this approval.
Any signs proposed for this development shall comply with the Sign Ordinance and shall require
separate application and approval by the Planning Division prior to installation of any signs.
I. Environmental
1. Mitigation measures are required for the project. The applicant is responsible for the cost of
implementing said measures, including monitoring and reporting. Applicant shall be required to
post cash, letter of credit, or other forms of guarantee acceptable to the City Planner in the
amount of $719.00 prior to the issuance of building permits, guaranteeing satisfactory
performance and completion of all mitigation measures. These funds maybe used bythe Cityto
retain consultants and/or pay for City staff time to monitor and report on the mitigation measures.
Failure to complete all actions required by the approved environmental documents shall be
considered grounds for forfeit.
J. Other Agencies
1. The applicant shall contact the U.S. Postal Service to determine the appropriate type and location
of mailboxes. Multi-family residential developments shall provide a solid overhead structure for
mailboxes with adequate lighting. The final location of the mailboxes and the design of the
overhead structure shall be subject to City Planner review and approval prior to the issuance of
building permits.
APPLICANT SHALL CONTACTTHE BUILDING AND SAFETY DIVISION,(909)477-2710, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
NOTE: ANY REVISIONS MAY VOID THESE REQUIREMENTS AND NECESSITATE ADDITIONAL REVIEW(S)
K. General Requirements
1. Submit five complete sets of plans including the following: —/�—
a. Site/Plot Plan;
b. Foundation Plan;
C. Floor Plan;
d. Ceiling and Roof Framing Plan;
e. Electrical Plans(2 sets, detached) including the size of the main switch, number and size
of service entrance conductors, panel schedules, and single line diagrams;
f. Plumbing and Sewer Plans,including isometrics, underground diagrams,water and waste
diagram, sewer or septic system location, fixture units, gas piping, and heating and air
conditioning; and
g. Planning Division Project Number(i.e., TT#, CUP#, DR #, etc.) clearly identified on the
outside of all plans.
2. Submit two sets of structural calculations, energy conservation calculations, and a soils report.
Architect's/Engineer's stamp and "wet' signature are required prior to plan check submittal.
SC-07-03 4
Project No.DRC2002-00653
Completion Date
3. Contractors must show proof of State and City licenses and Workers'Compensation coverage to
the City prior to permit issuance.
4. Separate permits are required for fencing and/or walls.
5. Business shall not open for operation prior to posting the Certificate of Occupancy issued by the
Building and Safety Division.
L. Site Development
1. Plans shall be submitted for plan check and approved prior to construction. All plans shall be
marked with the project file number(i.e., DRC2002-00653). The applicant shall comply with the
latest adopted California Codes, and all other applicable codes, ordinances, and regulations in
effect at the time of permit application. Contact the Building and Safety Division for availability of
the Code Adoption Ordinance and applicable handouts.
2. Prior to issuance of building permits for a new commercial or industrial development project or
major addition,the applicant shall pay development fees at the established rate. Such fees may
include but are not limited to: City Beautification Fee, Park Fee, Drainage Fee, Transportation
Development Fee, Permit and Plan Check Fees, and School Fees. Applicant shall provide a
copy of the school fees receipt to the Building and Safety Division prior to permits issuance.
3. Street addresses shall be provided by the Building and Safety Official after tract/parcel map
recordation and prior to issuance of building permits.
4. Construction activity shall not occur between the hours of 8:00 p.m. and 6:30 a.m. Monday
through Saturday, with no construction on Sunday or holidays.
5. Construct trash enclosure(s) per City Standard (available at the Planning Division's public
counter).
M. New Structures
1. Provide compliance with the California Building Code (CBC) for property line clearances
considering use, area, and fire-resistiveness.
2. Provide compliance with the California Building Code for required occupancy separations.
3. Provide draft stops in attic areas, not to exceed 3,000 square feet, in accordance with CBC __J__J
Section 1505.
4. Exterior walls shall be constructed of the required fire rating in accordance with CBC Table 5-A
5. Openings in exterior walls shall be protected in accordance with CBC Table 5-A.
6. Provide smoke and heat venting in accordance with CBC Section 906. Jam_
7. Upon tenant improvement plan check submittal, additional requirements may be needed.
N. Grading
1. Grading of the subject property shall be in accordance with California Building Code,City Grading
Standards, and accepted grading practices. The final grading plan shall be in substantial
conformance with the approved grading plan.
2. A soils report shall be prepared by a qualified engineer licensed by the State of California to
perform such work.
3. A geological report shall be prepared by a qualified engineer or geologist and submitted at the
time of application for grading plan check.
SC-07-03 5
Project No.DRC2002-00653
Completion Date
4. The final grading, appropriate certifications and compaction reports shall be completed,
submitted, and approved by the Building and Safety Official prior to the issuance of building
permits.
5. A separate grading plan check submittal is required for all new construction projects and for
existing buildings where improvements being proposed will generate 50 cubic yards or more of
combined cut and fill. The grading plan shall be prepared,stamped,and signed by a California
registered Civil Engineer.
O. Additional Requirements/Comments
APPLICANT SHALL CONTACT THE ENGINEERING DIVISION, (909) 477-2740, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
P. Dedication and Vehicular Access
1. Rights-of-way and easements shall be dedicated to the City for all interior public streets,
community trails,public paseos,public landscape areas,street trees,traffic signal encroachment
and maintenance, and public drainage facilities as shown on the plans and/or tentative map.
Private easements for non-public facilities (cross-lot drainage, local feeder trails, etc.) shall be
reserved as shown on the plans and/or tentative map.
2. Dedication shall be made of the following rights-of-way on the perimeter streets(measured from
street centerline):
Varies total feet on Day Creek Boulevard
Varies total feet on Base Line Road
3. Corner property line cutoffs shall be dedicated per City Standards.
4. All existing easements lying within future rights-of-way shall be quit-claimed or delineated on the.
final map.
5. Easements for public sidewalks and/or street trees placed outside the public right-of-way shall be
dedicated to the City.
6. Additional street right-of-way shall be dedicated along right turn lanes,to provide a minimum of 7
feet measured from the face of curbs. If curb adjacent sidewalk is used along the right turn lane,
a parallel street tree maintenance easement shall be provided.
Q. Street Improvements
1. All public improvements(interior streets,drainage facilities,community trails,paseos,landscaped
areas, etc.) shown on the plans and/or tentative map shall be constructed to City Standards.
Interior street improvements shall include, but are not limited to,curb and gutter,AC pavement,
drive approaches, sidewalks, street lights, and street trees.
2. Construct the following perimeter street improvements including, but not limited to:
Curb& AC. Side- Drive Street Street ComMedian Bike
ees
Street Name Gutter Pvmt walk Appr. Lights TrTall
Island Trail Other
Day Creek Boulevard X X X X X Rails X
to
Trails
SC-07-03 6
Project No.DRC2002-00653
Completion Date
3. Improvement Plans and Construction:
a. Street improvement plans, including street trees,street lights,and intersection safety lights
on future signal poles, and traffic signal plans shall be prepared by a registered Civil
Engineer and shall be submitted to and approved by the City Engineer. Security shall be
posted and an agreement executed to the satisfaction of the City Engineer and the City
Attorney guaranteeing completion of the public and/or private street improvements,priorto
final map approval or the issuance of building permits, whichever occurs first.
b. Prior to any work being performed in public right-of-way, fees shall be paid and a
construction permit shall be obtained from the City Engineer's Office in addition to any
other permits required.
C. Pavement striping,marking,traffic signing,street name signing,traffic signal conduit,and
interconnect conduit shall be installed to the satisfaction of the City Engineer.
d. Signal conduit with pull boxes shall be installed with any new construction or reconstruction
project along major or secondary streets and at intersections for future traffic signals and
interconnect wiring. Pull boxes shall be placed on both sides of the street at 3 feet outside
of BCR, ECR, or any other locations approved by the City Engineer
Notes:
1) Pull boxes shall be No.6 at intersections and No.5 along streets,a maximum of 200
feet apart, unless otherwise specified by the City Engineer.
2) Conduit shall be 3-inch (at intersections) or 2-inch (along streets) galvanized steel
with pull rope or as specified.
e. Handicapped access ramps shall be installed on all corners of intersections per City
Standards or as directed by the City Engineer.
f. Existing City roads requiring construction shall remain open to traffic at all times with
adequate detours during construction. Street or lane closure permits are required. A cash
deposit shall be provided to cover the cost of grading and paving,which shall be refunded
upon completion of the construction to the satisfaction of the City Engineer.
g. Concentrated drainage flows shall not cross sidewalks. Under sidewalk drains shall be
installed to City Standards, except for single family residential lots.
h. Street names shall be approved by the City Planner prior to submittal for first plan check.
4. Street trees, a minimum of 15-gallon size or larger, shall be installed per City Standards in
accordance with the City s street tree program.
5. Intersection line of sight designs shall be reviewed by the City Engineer for conformance with
adopted policy. On collector or larger streets, lines of sight shall be plotted for all project
intersections, including driveways. Local residential street intersections and commercial or
industrial driveways may have lines of sight plotted as required.
R. Public Maintenance Areas
1. Public landscape areas are required to incorporate substantial areas(40%)of mortared cobble or
other acceptable non-irrigated surfaces.
2. All required public landscaping and irrigation systems shall be continuously maintained by the
developer until accepted by the City.
3. Parkway landscaping on the following street(s) shall conform to the results of the respective
Beautification Master Plan Day Creek Master Plan.
SC-07-03 7
Project No.DRC2002-00653
Completion Date
S. Drainage and Flood Control
1. A final drainage study shall be submitted to and approved by the City Engineer prior to final map
approval or the issuance of building permits,whichever occurs first. All drainage facilities shall
be installed as required by the City Engineer.
2. Adequate provisions shall be made for acceptance and disposal of surface drainage entering the
property from adjacent areas.
3. Trees are prohibited within 5 feet of the outside diameter of any public storm drain pipe measured
from the outer edge of a mature tree trunk.
4. Public storm drain easements shall be graded to convey overflows in the event of a blockage in a J_
sump catch basin on the public street.
T. Utilities
1. Provide separate utility services to each parcel including sanitary sewerage system,water,gas,
electric power, telephone, and cable TV (all underground) in accordance with the Utility
Standards. Easements shall be provided as required.
2. The developer shall be responsible for the relocation of existing utilities as necessary.
3. Water and sewer plans shall be designed and constructed to meet the requirements of the
Cucamonga County Water District(CCW D), Rancho Cucamonga Fire Protection District,and the
Environmental Health Department of the County of San Bernardino. A letter of compliance from
the CCW D is required prior to final map approval or issuance of permits,whichever occurs first.
Such letter must have been issued by the water district within 90 days prior to final map approval
in the case of subdivision or prior to the issuance of permits in the case of all other residential
projects.
4. Approvals have not been secured from all utilities and other interested agencies involved.
Approval of the final parcel map will be subject to any requirements that may be received from
them.
U. General Requirements and Approvals
1. A non-refundable deposit shall be paid to the City,covering the estimated operating costs for all
new streetlights for the first six months of operation,prior to final map approval or priorto building
permit issuance if no map is involved.
APPLICANT SHALL CONTACT THE POLICE DEPARTMENT, (909) 477-2800, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
V. Security Lighting
1. All parking, common, and storage areas shall have minimum maintained 1-foot candle power.
These areas should be lighted from sunset to sunrise and on photo sensored cell.
2. All buildings shall have minimal security lighting to eliminate dark areas around the buildings,with
direct lighting to be provided by all entryways. Lighting shall be consistent around the entire
development.
3. Lighting in exterior areas shall be in vandal-resistant fixtures.
SC-07-03 8
Project No.DRC2002-00653
Completion Date
W. Security Hardware
1. One-inch single cylinder dead bolts shall be installed on all entrance doors. If windows are within
40 inches of any locking device, tempered glass or a double cylinder dead bolt shall be used.
2. All garage or rolling doors shall have slide bolts or some type of secondary locking devices.
X. Security Fencing
1. All businesses or residential communities with security fencing and gates will provide the police
with a keypad access and a unique code.The initial code is to be submitted to the Police Crime
Prevention Unit along with plans. If this code is changed due to a change in personnel or for any
other reason, the new code must be supplied to the Police via the 24-hour dispatch center at
(909)941-1488 or by contacting the Crime Prevention Unit at(909)477-2800 extension 2474 or
extension 2475.
Y. Building Numbering
1. Numbers and the backgrounds shall be of contrasting color and shall be reflective for nighttime
visibility.
SC-07-03 9