HomeMy WebLinkAbout04-12 - Resolutions RESOLUTION NO. 04-12
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
RANCHO CUCAMONGA, CALIFORNIA,APPROVING TENTATIVE PARCEL
MAP NO. 16180, A SUBDIVISION OF 4 PARCELS ON APPROXIMATELY
3.37 ACRES OF LAND IN THE VERY LOW RESIDENTIAL DISTRICT(.1-2
DWELLING UNITS PER ACRE) OF THE ETIWANDA SPECIFIC PLAN,
LOCATED AT THE SOUTHEAST CORNER OF BANYAN AVENUE AND
GREENWOOD PLACE,AND MAKING FINDINGS IN SUPPORT THEREOF—
APN: 0225-171-23 AND 26.
A. Recitals.
1. L.D. King, Inc. filed an application for the approval of Tentative Tract Map No.16180, as
described in the title of this Resolution. Hereinafter in this Resolution, the subject Tentative Tract
Map request is referred to as "the application."
2. On the 14th day of January 2004, the Planning Commission of the City of Rancho
Cucamonga conducted a duly noticed public hearing on the application and concluded said hearing
on that date.
3. All legal prerequisites prior to the adoption of this Resolution have occurred.
B. Resolution.
NOW, THEREFORE, it is hereby found, determined, and resolved bythe Planning Commission
of the City of Rancho Cucamonga as follows:
1. This Commission hereby specifically finds that all of the facts set forth in the Recitals,
Part A, of this Resolution are true and correct.
2. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing on January 14, 2004, including written and oral staff reports, togetherwith
public testimony, this Commission hereby specifically finds as follows:
a. The application applies to property located at the southeast comer of Banyan Street
and Greenwood Place; and
b. The property is presently improved with one existing single-family home at the
northwest comer of the site; and
C. The property to the north of the subject site includes-single family development and
vacant land, the property to the east consists of vacant land, and the properties to the south and
west include single-family development; and
d. The application is to subdivide approximately 3.37 acres of land into 4 parcels
consisting of the following square footages; and
Parcel 1 with existing residence 33,625 square feet
Parcel 2 37,992 square feet
Parcel 3 37,791 square feet
Parcel 4 37,489 square feet
36,724 average square feet
PLANNING COMMISSION RESOLUTION NO. 04-12
SUBTPM16180 — L.D. KING, INC.
January 14, 2004
Page 2
e. An existing remnant Eucalyptus windrow consisting of 21 trees runs through the
center of the site; and
f. The applicant has submitted Tree Removal Permit DRC2003-00308 for the removal
of the 21 Eucalyptus trees on-site; and
g. A Community Trail exists on the south side of Banyan Street at the north side of the
project site; and
h. A local equestrian feeder trail is proposed at the rear of Lots 2 through 4; and
i. Access into all four lots will be from Greenwood Place.
3. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing and upon the specific findings of facts set forth in paragraphs 1 and 2
above, this Commission hereby finds and concludes as follows:
a. The tentative parcel map is consistent with the General Plan, Development Code,
and any applicable specific plans; and
b. The design or improvements of the tentative parcel map is consistent with the
General Plan, Development Code, and any applicable specific plans; and
C. The site is physically suitable for the type of development proposed; and
d. The design of the subdivision is not likely to cause substantial environmental
damage and avoidable injury to humans and wildlife or their habitat; and
e. The tentative parcel map is not likely to cause serious public health problems; and
f. The design of the tentative parcel map will not conflict with any easement acquired
by the public at large, now of record, for access through or use of the property within the proposed
subdivision.
4. The Planning Commission concurs with the staff determination that this project is
categorically exempt from the requirements of the California Environmental Quality Act (CEQA)
pursuant to State CEQA Guidelines Section 15315(Class 15 Exemption—Minor Land Divisions).All
requirements for use of that exemption have been satisfied, including but not limited to, zoning,
number of parcels, utility service and access, prior subdivision and average slope.
5. Based upon the findings and conclusions set forth in paragraphs 1, 2, 3, and 4
above, this Commission hereby approves the application subject to each and every condition set
forth below and in the Standard Conditions, attached hereto and incorporated herein by this
reference.
Planning Division
1) All perimeter walls shall be decorative and have uniform design
compatible to those in the area, to the satisfaction of the City
Planner.
PLANNING COMMISSION RESOLUTION NO. 04-12
SUBTPM16180 — L.D. KING, INC.
January 14, 2004
Page 3
2) Tree Removal Permit DRC2003-00308 is hereby approved. All
Eucalyptus windrow trees identified for removal shall be replaced
with 15-gallon Eucalyptus maculata (Spotted Gum) trees, 8 feet
on center, as required by the City's Tree Preservation Ordinance
and Etiwanda Specific Plan. In addition, new windrows shall be
planted at a rate of 50 linear feet per acre per Etiwanda Specific
Plan.
3) Because of Borer beetle infestation, all Eucalyptus tree wood
shall be chipped, removed and buried at a dump site or tarped to
the ground for a minimum of six months, sealing the tarp edges
with soil,to prevent emerging Borer beetles from reinfesting other
trees or wood. The movement of Eucalyptus wood containing live
Borer beetles, or their larvae, in trucks or trailers is prohibited by
State law pursuant to Public Resources Code 4714.5.
4) Improve a Community Trail within the parkway of Banyan Avenue.
5) Relocate the perimeter wall on the north side of the project so it is
on the property line.
6) Provide crossing over 'V' gutter along south tract boundary to
allow access for equines and vehicles into the rear yard of the
lots. The crossing shall be concrete with roughened textured
finish and a minimum 10 feet wide.
7) Install minimum 10-foot wide gates in trail fencing to provide
access to the rear yard at all lots.
Engineering Division
1) Banyan Street frontage improvements to be in accordance with
City"Modified Local Street"standards and the Etiwanda Specific
Plan Figure 5-39, including but not limited to the following:
a) Protect existing curb and gutter, streetlight, R26(s) "No
Stopping"signs and asphalt pavement or repair as required.
b) Install Community Trail improvements per City Standards
Drawing No. 1003 (front-on).
c) The existing driveway for Parcel 1 to be relocated to
Greenwood Place.
2) Greenwood Place frontage improvements to be in accordance
with City"Local Residential"standards, including but not limited to
the following:
a) Protect existing curb and gutter, streetlights, sidewalk, and
asphalt pavement or repair as required.
PLANNING COMMISSION RESOLUTION NO. 04-12
SUBTPM16180— L.D. KING, INC.
January 14, 2004
Page 4
b) Install drive approaches and street trees per City Standards,
to the satisfaction of the City Engineer, upon development.
3) Revise City Drawing Nos. 1587 and 1417 to reflect the above
public improvements to the satisfaction of the City Engineer.
4) Provide a Water Quality Management Plan (WQMP), to the
satisfaction of the City Engineer and identify applicable Best
Management Practices (BMPs) on the grading plans.
5) Prior to the issuance of building permits, a Diversion Deposit and
related administrative fee shall be paid for the Construction and
Demolition Diversion Program. The deposit is fully refundable if
at least 50 percent of all wastes generated during construction
and demolition are diverted from landfills and appropriate
documentation is provided to the City. Form CD-1 shall be
submitted to the Engineering Division when the first Building
permit application is submitted to Building and Safety Division.
Form CD-2 shall be submitted to the Engineering Division within
60 days following the completion of the construction and/or
demolition project.
6. The Secretary to this Commission shall certify to the adoption of this Resolution.
APPROVED AND ADOPTED THIS 14TH DAY OF JANUARY 2004.
PLANNING COMMISSION OF THE CITY OF RANCHO CUCAMONGA
BY:
/. '^^ 4z�- �
Richard Macias, Chairman
ATTEST _
Brad ecreta
I, Brad Buller, Secretary of the Planning Commission of the City of Rancho Cucamonga, do hereby
certify that the foregoing Resolution was duly and regularly introduced, passed, and adopted by the
Planning Commission of the City of Rancho Cucamonga, at a regular meeting of the Planning
Commission held on the 14th day of January 2004, by the following vote-to-wit:
AYES: COMMISSIONERS: FLETCHER, MACIAS, McNIEL, STEWART
NOES: COMMISSIONERS: NONE
ABSENT: COMMISSIONERS: NONE
ABSTAIN: COMMISSIONERS: McPHAIL
COMMUNITY DEVELOPMENT
DEPARTMENT
STANDARD CONDITIONS
PROJECT#: SUBTPM16180
SUBJECT: FOUR-LOT RESIDENTIAL SUBDIVISION
APPLICANT: L.D. KING, INC.
LOCATION: SOUTHWEST CORNER OF BANYAN STREET AND GREENWOOD PLACE
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
APPLICANT SHALL CONTACT THE PLANNING DIVISION,(909)477-2750, FOR COMPLIANCE
WITH THE FOLLOWING CONDITIONS:
Completion Date
A. General Requirements
1. The applicant shall agree to defend at his sole expense any action brought against the City, its
agents,officers,or employees, because of the issuance of such approval,or in the alternative,to
relinquish such approval. The applicant shall reimburse the City, its agents, officers, or
employees, for any Court costs and attorney's fees which the City, its agents, officers, or
employees may be required by a courtto pay as a result of such action. The City may,at its sole
discretion,participate at its own expense in the defense of any such action but such participation
shall not relieve applicant of his obligations under this condition.
B. Time Limits
1. This tentative tract map or tentative parcel map shall expire, unless extended by the Planning
Commission, unless a complete final map is filed with the City Engineer within 3 years from the
date of the approval.
C. Site Development
1. The site shall be developed and maintained in accordance with the approved plans which include
site plans,architectural elevations,exterior materials and colors,landscaping,sign program,and
grading on file in the Planning Division, the conditions contained herein, Development Code
regulations.
2. Prior to any use of the project site or business activity being commenced thereon,all Conditions
of Approval shall be completed to the satisfaction of the City Planner.
3. All site, grading, landscape, irrigation, and street improvement plans shall be coordinated for
consistency prior to issuance of any permits (such as grading, tree removal, encroachment,
building, etc.)or prior to final map approval in the case of a custom lot subdivision, or approved
use has commenced, whichever comes first.
SC-10-03 1
Project No.SUBTPM16180
Completion Date
4. Approval of this request shall not waive compliance with all sections of the Development Code,all
other applicable City Ordinances, and applicable Community or Specific Plans in effect at the
time of building permit issuance.
5. All ground-mounted utility appurtenances such as transformers, AC condensers, etc., shall be
located out of public view and adequately screened through the use of a combination of concrete
or masonry walls,berming,and/or landscaping to the satisfaction of the City Planner. For single-
family residential developments, transformers shall be placed in underground vaults.
6. A detailed plan indicating trail widths, maximum slopes, physical conditions,fencing, and weed
control,in accordance with City Master Trail drawings,shall be submitted for City Planner review
and approval prior to approval and recordation of the Final Tract Map and prior to approval of
street improvement and grading plans. Developer shall upgrade and construct all trails,including
fencing and drainage devices, in conjunction with street improvements.
a. Local Feeder Trails (i.e., private equestrian easements) shall, at a minimum, be fenced
with two-rail,4-inch lodgepole"peeler"logs to define both sides of the easement;however,
developer may upgrade to an alternate fence material.
b. Local Feeder Trail grades shall not exceed 0.5% at the downstream end of a trail for a
distance of 25 feet behind the public right-of-way line to prohibit trail debris from reaching
the street. Drainage devices may be required by the Building Official
C. Provide a 24-foot by 24-foot corral area in the rear yard. Grade access from corral to trail J�—
with a maximum slope of 5:1 and a minimum.width of 10 feet.
d. For single family residential development within the Equestrian/Rural Overlay District, at
least one model home shall be provided with a constructed 24-foot by 24-foot corral with
appropriate fencing.
7. The Covenants, Conditions,and Restrictions(CC&Rs) shall not prohibit the keeping the equine
animals where zoning requirements for the keeping of said animals have been met. Individual lot
owners in subdivisions shall have the option of keeping said animals without the necessity of
appealing to boards of directors of homeowners'associations for amendments to the CC&Rs.
8. The Covenants, Conditions, and Restrictions (CC&Rs) and Articles of Incorporation of the
Homeowners'Association are subject to the approval of the Planning and Engineering Divisions
and the City Attorney. They shall be recorded concurrently with the Final Map or prior to the
issuance of building permits, whichever occurs first. A recorded copy shall be provided to the
City Engineer. The Homeowners' Association shall submit to the Planning Division a list of the
name and address of their officers on or before January 1 of each and every year and whenever
said information changes.
9. All parkways, open areas, and landscaping shall be permanently maintained by the property
owner,homeowners'association,or other means acceptable to the City. Proof of this landscape
maintenance shall be submitted for City Planner and City Engineer review and approved prior to
the issuance of building permits.
D. Parking and Vehicular Access (indicate details on building plans)
1. Multiple car garage driveways shall be tapered down to a standard two-car width at street. _J_/_
E. Landscaping
1. A detailed landscape and irrigation plan, including slope planting and model home landscaping in
the case of residential development, shall be prepared by a licensed landscape architect and
submitted for City Planner review and approval prior to the issuance of building permits or prior
final map approval in the case of a custom lot subdivision.
SC-10-03 2
Project No.SUBTPM16180
Completion Date
2. All private slopes of 5 feet or more in vertical height and of 5:1 or greater slope,but less than 2:1 _/_J_
slope,shall be,at minimum, irrigated and landscaped with appropriate ground cover for erosion
control. Slope planting required bythis section shall include a permanent irrigation system to be
installed by the developer prior to occupancy.
3. All private slopes in excess of 5 feet, but less than 8 feet in vertical height and of 2:1 or greater
slope shall be landscaped and irrigated for erosion control and to soften their appearance as
follows: one 15-gallon or larger size tree per each 150 sq.ft.of slope area, 1-gallon or larger size
shrub per each 100 sq.ft.of slope area,and appropriate ground cover. In addition,slope banks
in excess of 8 feet in vertical height and 2:1 or greater slope shall also include one 5-gallon or
larger size tree per each 250 sq. ft. of slope area. Trees and shrubs shall be planted in
staggered clusters to soften and vary slope plane. Slope planting required by this section shall
include a permanent irrigation system to be installed by the developer prior to occupancy.
4. For single-family residential development, all slope planting and irrigation shall be continuously
maintained in a healthy and thriving condition by the developer until each individual unit is sold
and occupied by the buyer. Prior to releasing occupancy for those units, an inspection shall be
conducted by the Planning Division to determine that they are in satisfactory condition.
5. The final design of the perimeter parkways,walls,landscaping,and sidewalks shall be included in
the required landscape plans and shall be subject to City Planner review and approval and
coordinated for consistency with any parkway landscaping plan which may be required by the
Engineering Division.
6. Landscaping and irrigation systems required to be installed within the public right-of-way on the
perimeter of this project area shall be continuously maintained by the developer.
F. Other Agencies
1. The applicant shall contact the U.S. Postal Service to determine the appropriate type and location
of mailboxes. Multi-family residential developments shall provide a solid overhead structure for
mailboxes with adequate lighting. The final location of the mailboxes and the design of the
overhead structure shall be subject to City Planner review and approval prior to the issuance of
building permits.
APPLICANT SHALL CONTACT THE BUILDING AND SAFETY DIVISION,(909)477-2710, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
NOTE: ANY REVISIONS MAY VOID THESE REQUIREMENTS AND NECESSITATE ADDITIONAL REVIEW(S)
G. General Requirements
1. Submit five complete sets of plans including the following: ��—
a. Site/Plot Plan;
b. Foundation Plan;
C. Floor Plan;
d. Ceiling and Roof Framing Plan;
e. Electrical Plans (2 sets, detached) including the size of the main switch, number and size
of service entrance conductors, panel schedules, and single line diagrams;
f. Plumbing and Sewer Plans, including isometrics, underground diagrams,water and waste
diagram, sewer or septic system location, fixture units, gas piping, and heating and air
conditioning; and
SC-10-03 3
Project No.SUBTPM16180
Completion Date
g. Planning Division Project Number(i.e., TT#, CUP#, DR#, etc.) clearly identified on the
outside of all plans.
2. Submit two sets of structural calculations, energy conservation calculations, and a soils report.
Architect's/Engineer's stamp and "wet"signature are required prior to plan check submittal.
3. Contractors must show proof of State and City licenses and Workers'Compensation coverage to __/_J_
the City prior to permit issuance.
4. Separate permits are required for fencing and/or walls.
5. Developers wishing to participate in the Community Energy Efficiency Program (CEEP) can __J__J_
contact the Building and Safety Division staff for information and submittal requirements.
H. Site Development
1. Plans shall be submitted for plan check and approved prior to construction. All plans shall be
marked with the project file number(i.e., SUBTPM16180). The applicant shall comply with the
latest adopted California Codes,and all other applicable codes, ordinances, and regulations in
effect at the time of permit application. Contact the Building and Safety Division for availability of
the Code Adoption Ordinance and applicable handouts.
2. Prior to issuance of building permits for a new residential project or major addition,the applicant
shall pay development fees at the established rate. Such fees may include,but are not limited to:
City Beautification Fee, Park Fee, Drainage Fee,Transportation Development Fee, Permit and
Plan Check Fees, and School Fees. Applicant shall provide a copy of the school fees receipt to
the Building and Safety Division prior to permit issuance.
3. Street addresses shall be provided by the Building and Safety Official after tract/parcel map
recordation and prior to issuance of building permits.
4. Construction activity shall not occur between the hours of 8:00 p.m. and 6:30 a.m. Monday
through Saturday, with no construction on Sunday or holidays.
I. New Structures
1. Provide compliance with the California Building Code (CBC) for property line clearances
considering use, area, and fire-resistiveness.
2. Provide compliance with the California Building Code for required occupancy separations.
3. Roofing material shall be installed per the manufacturer's "high wind" instructions..
J. Grading
1. Grading of the subject property shall be in accordance with California Building Code,City Grading
Standards, and accepted grading practices. The final grading plan shall be in substantial
conformance with the approved grading plan.
2. A soils report shall be prepared by a qualified engineer licensed by the State of California to _J_/_
perform such work.
3. A geological report shall be prepared by a qualified engineer or geologist and submitted at the
time of application for grading plan check.
4. The final grading, appropriate certifications and compaction reports shall be completed,
submitted, and approved by the Building and Safety Official prior to the issuance of building
permits.
SC-10-03 4
Project No.SUBTPM16180
Completion Date
5. A separate grading plan check submittal is required for all new construction projects and for
existing buildings where improvements being proposed will generate 50 cubic yards or more of
combined cut and fill. The grading plan shall be prepared, stamped,and signed by a California
registered Civil Engineer.
APPLICANT SHALL CONTACT THE ENGINEERING DIVISION, (909) 477-2740, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
K. Dedication and Vehicular Access
1. Rights-of-way and easements shall be dedicated to the City for all interior public streets,
community trails,public paseos,public landscape areas,street trees,traffic signal encroachment
and maintenance, and public drainage facilities as shown on the plans and/or tentative map.
Private easements for non-public facilities (cross-lot drainage, local feeder trails, etc.) shall be
reserved as shown on the plans and/or tentative map.
2. Private drainage easements for cross-lot drainage shall be provided and shall be delineated or
noted on the final map.
L. Street Improvements
1. All public improvements(interior streets,drainage facilities,community trails,paseos,landscaped
areas, etc.) shown on the plans and/or tentative map shall be constructed to City Standards.
Interior street improvements shall include, but are not limited to,curb and gutter,AC pavement,
drive approaches, sidewalks, street lights, and street trees.
2. Pursuant to City Council Resolution No.88-557,no person shall make connections from a source
of energy,fuel or power to any building service equipment which is regulated by technical codes
and for which a permit is required unless, in addition to any and all other codes, regulations and
ordinances,all improvements required by these conditions of development approval have been
completed and accepted by the City Council,except:that in developments containing more than
one building or unit, the development may have energy connections made to a percentage of
those buildings, or units proportionate to the completion of improvements as required by
conditions of approval of development. In no case shall more than 95 percent of the buildings or
units be connected to energy prior to completion and acceptance of all improvements required by
these conditions of approval of development.
3. Construct the following perimeter street improvements including, but not limited to:
Curb& A.C. Side- Drive Street Street Comm Median Bike
Street Name Gutter Pvmt walk Appr. Lights Trees Trail Island Trail Other
Banyan Street x x x x
Greenwood Place x x
Notes: (a) Median island includes landscaping and irrigation on meter. (b) Pavement
reconstruction and overlays will be determined during plan check. (c) If so marked, sidewalk
shall be curvilinear per Standard 114. (d) If so marked, an in-lieu of construction fee shall be
provided for this item.
4. Improvement Plans and Construction:
a. Street improvement plans, including street trees,street lights,and intersection safety lights
on future signal poles, and traffic signal plans shall be prepared by a registered Civil
Engineer and shall be submitted to and approved by the City Engineer. Security shall be
posted and an agreement executed to the satisfaction of the City Engineer and the City
Attorney guaranteeing completion of the public and/or private street improvements,prior to
final map approval or the issuance of building permits, whichever occurs first.
SC-10-03 5
Project No. SUBTPM16180
Completion Date
b. Prior to any work being performed in public right-of-way, fees shall be paid and a
construction permit shall be obtained from the City Engineer's Office in addition to any
other permits required.
C. Pavement striping,marking,traffic signing,street name signing,traffic signal conduit,and
interconnect conduit shall be installed to the satisfaction of the City Engineer.
d. Signal conduit with pull boxes shall be installed with any new construction or reconstruction
project along major or secondary streets and at intersections for future traffic signals and
interconnect wiring. Pull boxes shall be placed on both sides of the street at 3 feet outside
of BCR, ECR, or any other locations approved by the City Engineer
Notes:
1) Pull boxes shall be No.6 at intersections and No.5 along streets,a maximum of 200
feet apart, unless otherwise specified by the City Engineer.
2) Conduit shall be 3-inch (at intersections) or 2-inch (along streets) galvanized steel
with pull rope or as specified.
e. Handicapped access ramps shall be installed on all corners of intersections per City
Standards or as directed by the City Engineer.
f. Existing City roads requiring construction shall remain open to traffic at all times with —J—J_
adequate detours during construction. Street or lane closure permits are required. A cash
deposit shall be provided to cover the cost of grading and paving,which shall be refunded
upon completion of the construction to the satisfaction of the City Engineer.
g. Concentrated drainage flows shall not cross sidewalks. Under sidewalk drains shall be
installed to City Standards, except for single family residential lots.
h. Street names shall be approved by the City Planner prior to submittal for first plan check.
5. Street trees, a minimum of 15-gallon size or larger, shall be installed per City Standards in —J---J—
accordance with the City's street tree program.
6. Install street trees per City street tree design guidelines and standards as follows. The completed ---J—J_
legend and construction notes shall appear on the title page of the street improvement plans.
Where public landscape plans are required,tree installation in those areas shall be per the public
landscape improvement plans.
The City Engineer reserves the right to adjust tree species based upon field conditions and other
variables. For additional information, contact the Project Engineer.
Min.
Grow
Street Name Botanical Name Common Name Space Spacing Size• Gty.
Banyan Street Platanus acerifolia London Plane tree 8' 30'o.c. 15-gal
Greenwood Place Cercis Canadensis Eastern Redbud 5' 25'o.c. 15-gal
'TREES SHALL BE 15-GALLON SIZE UNLESS OTHERWISE APPROVED.
Construction Notes for Street Trees:
1) All street trees are to be planted in accordance with City standard plans.
2) Prior to the commencement of any planting,an agronomic soils report shall be furnished to
the City inspector. Any unusual toxicities or nutrient deficiencies may require backfill soil
amendments, as determined by the City inspector.
3) All street trees are subject to inspection and acceptance by the Engineering Division.
4) Street trees are to be planted per public improvement plans only.
SC-10-03 6
Project No.SUBTPM16180
completion Date
7. Intersection line of sight designs shall be reviewed by the City Engineer for conformance with
adopted policy. On collector or larger streets, lines of sight shall be plotted for all project
intersections, including driveways. Local residential street intersections and commercial or
industrial driveways may have lines of sight plotted as required.
M. Public Maintenance Areas
1. A signed consent and waiver form to join and/or form the appropriate Landscape and Lighting
Districts shall be filed with the City Engineer prior to final map approval or issuance of building
permits whichever occurs first. Formation costs shall be borne by the developer.
N. Drainage and Flood Control
1. Adequate provisions shall be made for acceptance and disposal of surface drainage entering the
property from adjacent areas.
O. Utilities
1. Provide separate utility services to each parcel including sanitary sewerage system,water,gas,
electric power, telephone, and. cable TV (all underground) in accordance with the Utility
Standards. Easements shall be provided as required.
2. The developer shall be responsible for the relocation of existing utilities as necessary.
3. Water and sewer plans shall be designed and constructed to meet the requirements of the _J_J_
Cucamonga County Water District(CCW D),Rancho Cucamonga Fire Protection District,and the
Environmental Health Department of the County of San Bernardino. A letter of compliance from
the CCW D is required prior to final map approval or issuance of permits,whichever occurs first.
Such letter must have been issued by the water district within 90 days prior to final map approval
in the case of subdivision or prior to the issuance of permits in the case of all other residential
projects.
4. Approvals have not been secured from all utilities and other interested agencies involved.
Approval of the final parcel map will be subject to any requirements that may be received from
them.
P. General Requirements and Approvals
1. A non-refundable deposit shall be paid to the City,covering the estimated operating costs for all
new streetlights for the first six months of operation,prior to final map approval or prior to building
permit issuance if no map is involved.
APPLICANT SHALL CONTACT THE FIRE SAFETY DIVISION, FIRE PROTECTION PLANNING
SERVICES AT, (909) 477-2770, FOR COMPLIANCE WITH THE FOLLOWING CONDITIONS:
SEE ATTACHED
SC-10-03 7
L
.nPPY1Lu., �
FIRE PROTECTION DISTRICT
3
FIRE SAFETY DIVISION
STANDARD CONDITIONS
FD PLAN REVIEW#: SUBTPM16180
PROJECT#: SUBTPM16180
PROJECT NAME: TPM16180
DATE: September 8, 2003
PLAN TYPE: 4— SFR Parcel map
APPLICANT NAME: L.D. King, Inc.
OCCUPANCY CLASS: Group R-3
FLOOR AREA(S): Unknown
TYPE CONSTRUCTION: Type V
FIRE PROTECTION
SYSTEM REQUIRED: None
LOCATION: 12715 Banyan
FD REVIEW BY: Moises Eskenazi, Sr. Plans Examiner
PLANNER: Warren Morelion
THE FOLLOWING STANDARD CONDITIONS MAY APPLY TO YOUR PROJECT.
RANCHO CUCAMONGA FIRE DISTRICT- STANDARD CONDITIONS & REQUIREMENTS —
General, Procedural, Technical, must be complete during the plan check process and
construction of the project.
FSC-1 General Requirements for Public and Private Water Supply
1. Minimum Fire Flow: The required fire flow for this project is 1750 gallons per minute at a minimum
residual pressure of 20 pounds per square inch. This requirementis made in accordance with Fire Code
Appendix III-A, as amended. Contact CCW D to request the available fire flow.
2. Hydrants Used to Supply Fire Flow: Public fire hydrants located within a 500-foot radius of the
proposed project may be used to provide the required fire flow subject to Fire District review and approval.
Private fire hydrants on adjacent property shall not be used to provide required fire flow.
3. Show Existing Fire Hydrants and Mains: Existing fire hydrants and mains within 600-feet of the project
shall be shown on the water plan submitted for review and approval. Include main size.
4. Single-family Residential Plans: For single-family residential and accessory structures show all fire
hydrants located within 600-feet of the proposed project site.
PRIOR TO ISSUANCE OF BUILDING PERMITS- Complete the following:
1. Public Fire Hydrants: Prior to issuance of any building permit, the applicant shall submit a plan
showing the locations of all new public fire hydrants for the review and approval by the Fire District
and the Water District. On the plan show all existing fire hydrants within a 600-foot radius of the
project. Contact the Fire Safety Division (909)477-2770
2. Public Installation: All required public fire hydrants shall be installed, flushed, and operable prior to
delivering any combustible building materials on-site (i.e., lumber, roofing materials, etc.). Water
District personnel shall inspect the installation and witness hydrant flushing. The builder/developer
shall submit a copy of the Water District inspection report to the Fire Safety Division. Contact Water
District to schedule testing.
PRIOR TO OCCUPANCY OR FINAL INSPECTION- Complete the following:
1. Hydrant Markers: All fire hydrants shall have a blue reflective pavement marker indicating the fire
hydrant location on the street or driveway in accordance with Rancho Cucamonga Fire Protection
District and City of Rancho Cucamonga Engineering Standard Plan 134, "Installation of Reflective
Hydrant Markers." On private property these markers are to be maintained in good condition by the
property owner. Contact Building and Safety/Fire Construction Services (909) 477-2713.
2. Address Single-family: New single-family dwellings shall post the address with minimum 4-inch
numbers on a contrasting background. The numbers shall be internally or externally illuminated during
periods of darkness. The numbers shall be visible from the street. When building setback from the
public roadway exceeds 100 feet, additional 4-inch numbers shall be displayed at the property entry.
Fire District Forms and Letters
Note: If these conditions are part of the final Standard Conditions issued by the Planning Division referenced
Fire District forms and letters are not included.Contact the Fire Safety Division for copies of forms or letters.The
forms and letter are also found in previously issued Fire District comments.