HomeMy WebLinkAbout05-41 - Resolutions RESOLUTION NO. 05-41
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
RANCHO CUCAMONGA, CALIFORNIA,APPROVING TENTATIVE PARCEL
MAP SUBTPM17156,A REQUEST TO SUBDIVIDE 12.8 GROSS ACRES OF
LAND INTO THREE PARCELS WITHIN THE GENERAL COMMERCIAL AND
GENERAL INDUSTRIAL (SUBAREA 1) DISTRICTS, LOCATED AT THE
NORTHEAST CORNER OF 9TH STREET AND MADRONE AVENUE; AND
MAKING FINDINGS IN SUPPORT THEREOF-APN: 0207-262-18 AND 27.
A. Recitals.
1. Rancho Cucamonga Housing Partners, LP filed an application for the approval of
Tentative Parcel Map SUBTPM17156, as described in the title of this Resolution. Hereinafter in this
Resolution, the subject Tentative Parcel Map request is referred to as "the application."
2. On the 25th day of May 2005, the Planning Commission of the City of Rancho
Cucamonga conducted a duly noticed public hearing on the application and concluded said hearing
on that date.
3. All legal prerequisites prior to the adoption of this Resolution have occurred.
B. Resolution.
NOW, THEREFORE, it is hereby found, determined, and resolved by the Planning Commission
of the City of Rancho Cucamonga as follows:
1. This Commission hereby specifically finds that all of the facts set forth in the Recitals,
Part A, of this Resolution are true and correct.
2. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing on May 25, 2005, including written and oral staff reports, together with
public testimony, this Commission hereby specifically finds as follows:
a. The application applies to partially developed property located on the northeast
comer of 9th Street and Madrone Avenue, with a street frontage of approximately 788 feet on 9th
Street and approximately 550 feet on Madrone Avenue; and
b. The property to the north of the subject site is developed with apartments, and
townhome and single-family development exist on the west side of Madrone Avenue. Further east is
non-conforming industrial development and to the south will be new light industrial development;and
C. The proposed use, together with the conditions applicable thereto, will not be
detrimental to the public health, safety, or welfare or materially injurious to properties or
improvements in the vicinity; and
d. The applicant conducted a neighborhood meeting on May 12, 2005, to inform the
surrounding neighborhood residents of the proposed project and to obtain feedback; and
e. The application contemplates the retention of the original Cask-N-Cleaver
restaurant buildings, the development of a private gated community of 64 condominium units, and
reservation of land area for a future public park.
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 2
f. The parcel map associated with this project is appropriate in that the proposed
parcels are of sufficient size to meet minimum Code requirements to accommodate anticipated
future development.
g. New street improvements associated with the approval of the parcel map will
enhance the appearance of the 9th Street streetscape, and improve pedestrian access/movement in
the area.
3. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing and upon the specific findings of facts set forth in paragraphs 1 and 2
above, this Commission hereby finds and concludes as follows:
a. That the tentative parcel map is consistent with the General Plan, Development
Code, and any applicable specific plans; and
b. The design or improvements of the tentative parcel map is consistent with the
General Plan, Development Code, and any applicable specific plans; and
C. The site is physically suitable for the type of development proposed; and
d. The design of the subdivision is not likely to cause substantial environmental
damage and avoidable injury to humans and wildlife or their habitat; and
e. The tentative parcel map is not likely to cause serious public health problems; and
f. The design of the tentative parcel map will not conflict with any easement acquired
by the public at large, now of record, for access through or use of the property within the proposed
subdivision.
4. Based upon the facts and information contained in the proposed Mitigated Negative
Declaration, together with all written and oral reports included for the environmental assessment for
the application, the Planning Commission finds that there is no substantial evidence that the project
will have a significant effect upon the environment and adopts a Mitigated Negative Declaration and
Monitoring Program attached hereto, and incorporated herein by this reference, based upon the
findings as follows:
a. That the Mitigated Negative Declaration has been prepared in compliance with the
California Environmental Quality Act of 1970, as amended, and the State CEQA guidelines
promulgated thereunder; that said Mitigated Negative Declaration and the Initial Study prepared
therefore reflect the independent judgment of the Planning Commission; and, further, this
Commission has reviewed and considered the information contained in said Mitigated Negative
Declaration with regard to the application.
b. Although the Mitigated Negative Declaration identifies certain significant
environmental effects that will result if the project is approved, all significant effects have been
reduced to an acceptable level by imposition of mitigation measures on the project,which are listed
below as conditions of approval.
C. Pursuant to the provisions of Section 753.5(c) of Title 14 of the California Code of
Regulations, the Planning Commission finds as follows: In considering the record as a whole, the
Initial Study and Mitigated Negative Declaration for the project, there is no evidence that the
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 3
proposed project will have potential for an adverse impact upon wildlife resources orthe habitat upon
which wildlife depends. Further, based upon the substantial evidence contained in the Mitigated
Negative Declaration, the staff reports and exhibits, and the information provided to the Planning
Commission during the public hearing, the Planning Commission hereby rebuts the presumption of
adverse effect as set forth in Section 753.5(c-1-d) of Title 14 of the California Code of Regulations.
5. Based upon the findings and conclusions set forth in paragraphs 1, 2, 3, and 4 above,
this Commission hereby approves the application subject to each and every condition set forth below
and in the Standard Conditions, attached hereto and incorporated herein by this reference.
Planning Department
1) The approval of this application is contingent upon City Council
approval of General Plan Amendment DRC2005-00106 and
Development District Amendment DRC2005-00107.
Engineering Department
2) Submit a Water Quality Management Plan (WQMP)that follows current
WQMP templates/guidance and regulations set forth by the Santa Ana
Regional Water Quality Control Board(RWQCB). Access the following
website for an updated San Bernardino County WQMP for New
Development and Redevelopment Projects:
hftp://www.swrcb.ca.gov/rwgcb8/html/sb_wgmp.html. This site
provides Guidance and Templates that can be filled out electronically
and printed. Adhere to these guidelines and use the templates
provided.
3) Along Parcel 3, 9th Street frontage improvements shall be designed
and installed to the satisfaction of the City Engineer.
4) All on-site and off-site utilities on 9th Street frontage along Parcel 3
shall be handled according to the underground utility policy. Utilities on
the opposite sides of the street fronting the project shall have fees paid
in accordance with the policy. Utilities on the project side of the street
fronting the project shall be undergrounded in accordance with the
policy.
5) File with the City Engineer a signed consent and waiver form to join
and/or form the appropriate Landscape and Lighting District(s) for
Parcels 1, 2 and 3 of the proposed map. The developer shall be
responsible for paying the costs related to the formation of the
abovementioned Landscape and Lighting District(s).
6) Pay a non-refundable deposit to the City of Rancho Cucamonga,
covering the estimated cost of operating all streetlights for Parcel 3
along the 9th Street frontage for the first 6 months of operation.
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 4
Environmental Mitigation
Air Quality
1) All construction equipment shall be maintained in good operating
condition so as to reduce operational emissions. The contractor shall
ensure that all construction equipment is being properly serviced and
maintained as per manufacturers'specifications. Maintenance records
shall be available at the construction site for City verification.
2) Prior to the issuance of any grading permits, the developer shall submit
Construction Plans to the City denoting the proposed schedule and
projected equipment use. Construction contractors shall provide
evidence that low-emission mobile construction equipment will be
utilized, or that their use was investigated and found to be infeasible for
the project. Contractors shall also conform to any construction
measures imposed by the South Coast Air Quality Management District
(SCAQMD) as well as City Planning staff.
3) All paints and coatings shall meet or exceed performance standards
noted in SCAQMD Rule 1113. Paints and coatings shall be applied
either by hand or high-volume, low-pressure spray.
4) All asphalt shall meet or exceed performance standards noted in
SCAQMD Rule 1108.
5) All construction equipment shall comply with SCAQMD Rules 402 and
403. Additionally, contractors shall include the following provisions:
• Reestablish ground cover on the construction site through
seeding and watering.
• Pave or apply gravel to any on-site haul roads.
• Phase grading to prevent the susceptibility of large areas to
erosion over extended periods of time.
• Schedule activities to minimize the amounts of exposed
excavated soil during and after the end of work periods.
• Dispose of surplus excavated material in accordance with local
ordinances and use sound engineering practices.
• Sweep streets according to a schedule established by the City if
silt is carried over to adjacent public thoroughfares or occurs as a
result of hauling. Timing may vary depending upon the time of
year of construction.
• Suspend grading operations during high winds(i.e.,wind speeds
exceeding 25 mph) in accordance with Rule 403 requirements.
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 5
• Maintain a minimum 24-inch freeboard ratio on soils haul trucks or
cover payloads using tarps or other suitable means.
6) The site shall be treated with water or other soil-stabilizing agent
(approved by SCAQMD and Regional Water Quality Control Board
[RWQCB]) daily to reduce PM10 emissions, in accordance with
SCAQMD Rule 403.
7) Chemical soil-stabilizers(approved by SCAQMD and RWQCB)shall be
applied to all inactive construction areas that remain inactive for 96
hours or more to reduce PM10 emissions.
8) The construction contractor shall utilize electric or dean alternative fuel-
powered equipment where feasible.
9) The construction contractor shall ensure that Construction Grading
Plans include a statement that work crews will shut off equipment when
not in use.
10) All residential and commercial structures shall be required to
incorporate high-efficiency/low-polluting heating, air conditioning,
appliances, and water heaters.
11) All residential and commercial structures shall be required to
incorporate thermal pane windows and weather-stripping.
Cultural Resources
1) If any prehistoric archaeological resources are encountered before or
during grading, the developer will retain a qualified archaeologist to
monitor construction activities, to take appropriate measures to protect
or preserve them for study. With the assistance of the archaeologist,
the City of Rancho Cucamonga will:
• Enact interim measures to protect undesignated sites from
demolition or significant modification without an opportunity for
the City to establish its archaeological value.
• Consider establishing provisions to require incorporation of
archaeological sites within new developments, using their special
qualities as a theme or focal point.
• Pursue educating the public about the area's archaeological
heritage.
• Propose mitigation measures and recommend conditions of
approval to eliminate adverse project effects on significant,
important, and unique prehistoric resources,following appropriate
CEQA guidelines.
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 6
• Prepare a technical resources management report, documenting
the inventory, evaluation, and proposed mitigation of resources
within the project area. Submit one copy of the completed report
with original illustrations, to the San Bernardino County
Archaeological Information Center for permanent archiving.
2) A qualified paleontologist shall conduct a pre-construction field survey
of the project site. The paleontologist shall submit a report of findings
that will also provide specific recommendations regarding further
mitigation measures (i.e., paleontological monitoring) that may be
appropriate. Where mitigation monitoring is appropriate, the program
must include, but not be limited to, the following measures:
• Assign a paleontological monitor, trained and equipped to allow
the rapid removal of fossils with minimal construction delay,to the
site full-time during the interval of earth-disturbing activities.
• Should fossils be found within an area being cleared or graded,
divert earth-disturbing activities elsewhere until the monitor has
completed salvage. If construction personnel make the
discovery, the grading contractor should immediately divert
construction and notify the monitor of the find.
3) Submit a summary report to the City of Rancho Cucamonga. Transfer
collected specimens with a copy of the report to San Bernardino County
Museum.
Geologic and Soils
1) The site shall be treated with water or other soil-stabilizing agent
(approved by SCAQMD and RWQCB) daily to reduce PM10 emissions,
in accordance with SCAQMD Rule 403 or re-planted with drought
resistant landscaping as soon as possible.
2) Frontage public streets shall be swept according to a schedule
established by the City to reduce PM10 emissions associated with
vehicle tracking of soil off-site. Timing may vary depending upon the
time of year of construction.
3) Grading operations shall be suspended when wind speeds exceed
25 mph to minimize PM10 emissions from the site during such episodes.
4) Chemical soil-stabilizers(approved by SCAQMD and RWQCB)shall be
applied to all inactive construction areas that remain inactive for 96
hours or more to reduce PM10 emissions.
Hydrology and Water Quality
1) Prior to issuance of grading permits, the permit applicant shall submit to
Building Official for approval a Storm Water Pollution Prevention Plan
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 7
(SWPPP) specifically identifying Best Management Practices (BMPs)
that shall be used on-site to reduce pollutants during construction
activities entering the storm drain system to the maximum extent
practical.
2) An Erosion Control Plan shall be prepared, included in the Grading
Plan, and implemented for the proposed project that identifies specific
measures to control on-site and off-site erosion from the time of ground
disturbing activities are initiated through completion of grading. This
Erosion Control Plan shall include the following measures at a
minimum: a)Specify the timing of grading and construction to minimize
soil exposure to rainy periods experienced in southern California,and b)
An inspection and maintenance program shall be included to ensure
that any erosion which does occur either on-site or off-site as a result of
this project will be corrected through a remediation or restoration
program within a specified time frame.
3) During construction, temporary berms such as sandbags or gravel
dikes must be used to prevent discharge of debris or sediment from the
site when there is rainfall or other runoff.
4) During construction, to remove pollutants, street cleaning will be
performed prior to storm events and after the use of water trucks to
control dust in order to prevent discharge of debris or sediment from
the site.
5) The developer shall implement the BMPs identified in the Water Quality
Management Plan prepared by MDS Consulting(March 2005)to reduce
pollutants after construction entering the storm drain system to the
maximum extent practical.
6) Landscaping plans shall include provisions for controlling and
minimizing the use of fertilizers/pesticides/herbicides. Landscaped
areas shall be monitored and maintained for at least two years to
ensure adequate coverage and stable growth. Plans for these areas,
including monitoring provisions for a minimum of two years, shall be
submitted to the City for review and approval prior to the issuance of
grading permits.
7) Prior to issuance of building permits, the applicant shall submit to the
City Engineer for approval of a WQMP, including a project description
and identifying BMPs that will be used on-site to reduce pollutants into
the storm drain system to the maximum extent practicable. The WQMP
shall identify the structural and non-structural measures consistent with
the Guidelines for New Development and Redevelopment adopted by
the City of Rancho Cucamonga in June 2004.
8) Prior to issuance of grading or paving permits,the applicant shall obtain
a Notice of Intent (NO]) to comply with obtaining coverage under the
National Pollutant Discharge Elimination System (NPDES) General
Construction Storm Water Permit from the State Water Resources
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 8
Control Board. Evidence that this has been obtained (i.e., a copy of the
Waste Discharger's Identification Number) shall be submitted to the
City Building Official for coverage under the NPDES General
Construction Permit.
Noise
1) Construction or grading shall not take place between the hours of 8:00
p.m. and 6:30 a.m. on weekdays, including Saturday, or at any time on
Sunday or a national holiday.
2) Construction or grading noise levels shall not exceed the standards
specified in Development Code Section 17.02.120-D, as measured at
the property line. The developer shall hire a consultant to perform
weekly noise level monitoring as specified in Development Code
Section 17.02.120. Monitoring at other times may be required by the
Building Official. Said consultant shall report their findings to the
Building Official within 24 hours; however, if noise levels exceed the
above standards, then the consultant shall immediately notify the
Building Official. If noise levels exceed the above standards, then
construction activities shall be reduced in intensity to a level of
compliance with above noise standards or halted.
3) The perimeter block wall shall be constructed as early as possible in
first phase.
4) Haul truck deliveries shall not take place between the hours of 8:00
p.m. and 6:30 a.m. on weekdays, including Saturday, or at any time on
Sunday or a national holiday. Additionally, if heavy trucks used for
hauling would exceed 100 daily trips (counting both to and from the
construction site), then the developer shall prepare a Noise Mitigation
Plan denoting any construction traffic haul routes. To the extent
feasible, the plan shall denote haul routes that do not pass sensitive
land uses or residential dwellings.
6. The Secretary to this Commission shall certify to the adoption of this Resolution.
APPROVED AND ADOPTED THIS 25TH DAY OF MAY 2005.
PLANNING COMMISSION OF THE CITY OF RANCHO CUCAMONGA
BY: 12-Z
ich Macs, Chai
ATTEST
—B�n`Colem , Acting Secretary
PLANNING COMMISSION RESOLUTION NO. 05-41
SUBTPM17156— RANCHO CUCAMONGA HOUSING PARTNERS, LP
May 25, 2005
Page 9
I, Dan Coleman,Acting Secretary of the Planning Commission of the City of Rancho Cucamonga,do
hereby certify that the foregoing Resolution was duly and regularly introduced, passed, and adopted
by the Planning Commission of the City of Rancho Cucamonga, at a regular meeting of the Planning
Commission held on the 25th day of May 2005, by the following vote-to-wit:
AYES: COMMISSIONERS: MACIAS, McNIEL, McPHAIL, STEWART
NOES: COMMISSIONERS: NONE
ABSENT: COMMISSIONERS: FLETCHER
City of Rancho Cucamonga
MITIGATION MONITORING
PROGRAM
Project File No.: General Plan Amendment DRC2005-00106, Development District Amendment
DRC2005-00107, Tentative Parcel Map SUBTPM17156, and Development Review
DRC2005-00220
This Mitigation Monitoring Program (MMP)has been prepared for use in implementing the mitigation
measures identified in the Mitigated Negative Declaration for the above-listed project. This program
has been prepared in compliance with State law to ensure that adopted mitigation measures are
implemented (Section 21081.6 of the Public Resources Code).
Program Components -This MMP contains the following elements:
1. Conditions of approval that act as impact mitigation measures are recorded with the action and
the procedure necessary to ensure compliance. The mitigation measure conditions of approval
are contained in the adopted Resolution of Approval for the project.
2. A procedure of compliance and verification has been outlined for each action necessary. This
procedure designates who will take action, what action will be taken and when, and to whom
and when compliance will be reported.
3. The MMP has been designed to provide focused, yet flexible guidelines. As monitoring
progresses, changes to compliance procedures may be necessary based upon
recommendations by those responsible for the program.
Program Management-The MMP will be in place through all phases of the project. The project
planner, assigned by the City Planner, shall coordinate enforcement of the MMP. The project
planner oversees the MMP and reviews the Reporting Forms to ensure they are filled out correctly
and proper action is taken on each mitigation. Each City department shall ensure compliance of the
conditions (mitigation) that relate to that department.
Procedures - The following steps will be followed by the City of Rancho Cucamonga.
1. A fee covering all costs and expenses, including any consultants'fees, incurred by the City in
performing monitoring or reporting programs shall be charged to the applicant.
2. A MMP Reporting Form will be prepared for each potentially significant impact and its
corresponding mitigation measure identified in the Mitigation Monitoring Checklist, attached
hereto. This procedure designates who will take action,what action will be taken and when,and
to whom and when compliance will be reported. All monitoring and reporting documentation will
be kept in the project file with the department having the original authority for processing the
project. Reports will be available from the City upon request at the following address:
City of Rancho Cucamonga - Lead Agency
Planning Department
10500 Civic Center Drive
Rancho Cucamonga, CA 91730
Mitigation Monitoring Program
GPA DRC2005-00106, DDA DRC2005-00107, SUBTPM17156, and DR DRC2005-00220
Page 2
3. Appropriate specialists will be retained if technical expertise beyond the City staffs is needed,as
determined by the project planner or responsible City department,to monitor specific mitigation
activities and provide appropriate written approvals to the project planner.
4. The project planner or responsible City department will approve, by signature and date, the
completion of each action item that was identified on the MMP Reporting Form. After each
measure is verified for compliance, no further action is required for the specific phase of
development.
5. All MMP Reporting Forms for an impact issue requiring no further monitoring will be signed off
as completed by the project planner or responsible City department at the bottom of the MMP
Reporting Form.
6. Unanticipated circumstances may arise requiring the refinement or addition of mitigation
measures.The project planner is responsible for approving any such refinements or additions.
An MMP Reporting Form will be completed by the project planner or responsible City department
and a copy provided to the appropriate design, construction, or operational personnel.
7. The project planner or responsible City department has the authority to stop the work of
construction contractors if compliance with any aspects of the MMP is not occurring after written
notification has been issued. The project planner or responsible City department also has the
authority to hold certificates of occupancies if compliance with a mitigation measure attached
hereto is not occurring.The project planner or responsible City department has the authority to
hold issuance of a business license until all mitigation measures are implemented.
8. Any conditions (mitigation) that require monitoring after project completion shall be the
responsibility of the City of Rancho Cucamonga Planning Division.The Division shall require the
applicant to post any necessary funds (or other forms of guarantee)with the City. These funds
shall be used by the City to retain consultants and/or pay for City staff time to monitor and report
on the mitigation measure for the required period of time.
9. In those instances requiring long-term project monitoring, the applicant shall provide the City
with a plan for monitoring the mitigation activities at the project site and reporting the monitoring
results to the City. Said plan shall identify the reporter as an individual qualified to know whether
the particular mitigation measure has been implemented. The monitoring/reporting plan shall
conform to the City's MMP and shall be approved by the Community Development Director or
City Planner prior to the issuance of building permits.
MITIGATION MONITORING CHECKLIST (INITIAL STUDY PART III)
Project File No.'s: General Plan Amendment DRC2005-00106: Development District Amendment DRC2005-00107; Tentative Parcel
Map SUBTP17156: and Tentative Tract Map SUBTT17455 Applicant: Rancho Cucamonga Housing Partners, LP
Initial Study Prepared by: Michael Diaz Date: April 13, 2005
ResponsibleMitigation Measures No. . . of Verified Sanctions for
Implementing Action for Monitoring Frequency Verification Verification Date/Initials Non-Compliance
Air Quality
All construction equipment shall be maintained in good CP C Review of plans A/C 2/4
operating condition so as to reduce operational
emissions. The contractor shall ensure that all
construction equipment is being properly serviced and
maintained as per manufacturers' specifications.
Maintenance records shall be available at the
construction site for City verification.
Prior to the issuance of any grading permits, the CP/BO C Review of plans C 2
developer shall submit Construction Plans to the City
denoting the proposed schedule and projected
equipment use. Construction contractors shall provide
evidence that low-emission mobile construction
equipment will be utilized, or that their use was
investigated and found to be infeasible for the project.
Contractors shall also conform to any construction
measures imposed by the South Coast Air Quality
Management District (SCAQMD) as well as City
Planning Staff.
All paints and coatings shall meet or exceed CP C Review of plans A/C 2/4
performance standards noted in SCAQMD Rule 1113.
Paints and coatings shall be applied either by hand or
high-volume, low-pressure spray.
All asphalt shall meet or exceed performance standards BO B Review of plans A/C 2
noted in SCAQMD Rule 1108.
All construction equipment shall comply with SCAQMD BO C Review of plans A/C 2/4
Rules 402 and 403. Additionally, contractors shall
include the following provisions:
1 of 8
Mitigation Measures No. Responsible Monitoring Timing of Method of Verified Sanctions for
ImplementingAction for • • • Frequency
• Reestablish ground cover on the construction site BO C Review of plans A/C 2/4
through seeding and watering.
• Pave or apply gravel to any on-site haul roads. BO C Review of plans A/C 2/4
• Phase grading to prevent the susceptibility of large BO C Review of plans A/C 2/4
areas to erosion over extended periods of time.
• Schedule activities to minimize the amounts of BO C Review of plans A/C 2/4
exposed excavated soil during and after the end of
work periods.
• Dispose of surplus excavated material . in BO C Review of plans A 4
accordance with local ordinances and use sound
engineering practices.
• Sweep streets according to a schedule established BO C During A 4
by the City if silt is carried over to adjacent public construction
thoroughfares or occurs as a result of hauling.
Timing may vary depending upon time of year of
construction.
• Suspend grading operations during high winds(i.e., BO C During A 4
wind speeds exceeding 25 mph)in accordance with construction
SCAQMD Rule 403 requirements.
• Maintain a minimum 24-inch freeboard ratio on.soils BO C During A 4
haul trucks or cover payloads using tarps or other Construction
suitable means.
The site shall be treated with water or other soil- BO C During A 4
stabilizing agent (approved by SCAQMD and Regional construction
Water Quality Control Board [RWQCB])daily to reduce
PM,o emissions,in accordance with SCAQMD Rule 403.
Chemical soil-stabilizers (approved by SCAQMD and BO C During A 4
RWQCB) shall be applied to all inactive construction construction
areas that remain inactive for 96 hours or more to
reduce PM,o emissions.
The construction contractor shall utilize electric or clean BO C Review of plans A/C 4
alternative fuel powered equipment where feasible.
2of8
Mitigation • ResponsibleMonitoring
ImplementingAction
The construction contractor shall ensure that BO C Review of plans A/C 2/4
Construction Grading Plans include a statement that
work crews will shut off equipment when not in use.
All residential and commercial structures shall be BO CID Review of plans C 2/4
required to incorporate high-efficiency/low-polluting
heating,air conditioning,appliances,and water heaters.
All residential and commercial structures shall be BO CID Review of plans C 2/4
required to incorporate thermal pane windows and
weather-stripping.
Cultural Resources
If any prehistoric archaeological resources are
encountered before or during grading,the developer will
retain a qualified archaeologist to monitor construction
activities, to take appropriate measures to protector
preserve them for study. With the assistance of the
archaeologist, the City of Rancho Cucamonga will:
• Enact interim measures to protect undesignated CP/BO C Review of report A/D 3/4
sites from demolition or significant modification
without an opportunity for the City to establish its
archaeological value.
• Consider establishing provisions to require CP/BO C Review of report A/D 3/4
incorporation of archaeological sites within new
developments, using their special qualities as a
theme or focal point.
• Pursue educating the public about the area's CP/BO C Review of report A/D 3/4
archaeological heritage.
• Propose mitigation measures and recommend CP/BO C Review of report A/D 3/4
conditions of approval to eliminate adverse project
effects on significant, important, and unique
prehistoric resources, following appropriate CEQA
guidelines.
3of8
Mitigation . . g of Method .
Implementing Action for Monitoring Frequency Verification Verification Date/initials Non-Compliance
• Prepare a technical resources management report, CP C Review of report A/D 3/4
documenting the inventory, evaluation, and
proposed mitigation of resources within the project
area. Submit one copy of the completed report,with
original illustrations, to the San Bernardino County
Archaeological Information Center for permanent
archiving.
A qualified paleontologist shall conduct a preconstruction CP B Review of report A/D 4
field survey of the project site. The paleontologist shall
submit a report of findings that will also provide specific
recommendations regarding further mitigation measures
(i.e., paleontological monitoring) that may be
appropriate.Where mitigation monitoring is appropriate,
the program must include, but not be limited to, the
following measures:
• Assign a paleontological monitor, trained and CP B Review of report A/D 4
equipped to allow the rapid removal of fossils with
minimal construction delay, to the site full-time
during the interval of earth-disturbing activities.
• Should fossils be found within an area being cleared BO B/C Review of report A/D 4
or graded, divert earth-disturbing activities
elsewhere until the monitor has completed salvage.
If construction personnel make the discovery, the
grading contractor should immediately divert
construction and notify the monitor of the find.
• Submit a summary report to the City of Rancho CP D Review of report D 3
Cucamonga. Transfer collected specimens with a
copy of the report to the San Bernardino County
Museum.
Geology and Soils
The site shall be treated with water or other soil- BO C During A 4
stabilizing agent(approved by SCAQMD and RWQCB) construction
daily to reduce PM,o emissions, in accordance with
SCAQMD Rule 403 or re-planted with drought resistant
landscaping as soon as possible.
4 of 8
Mitigation Measures No.
Responsible of Verified Sanctions for
Implementing Action for Monitoring Frequency Verification Verification Date/initials Non-Compliance
Frontage public streets shall be swept according to a BO C During A 4
schedule established by the City to reduce PM10 construction
emissions associated with vehicle tracking of soil off-
site. Timing may vary depending upon the time of year
of construction.
Grading operations shall be suspended when wind BO C During A 4
speeds exceed 25 mph to minimize PM10 emissions construction
from the site during such episodes.
Chemical soil-stabilizers (approved by SCAQMD and BO C During A 4
RWQCB) shall be applied to all inactive construction construction
areas that remain inactive for 96 hours or more to
reduce PM10 emissions.
Hydrology and Water Quality
Prior to issuance of grading permits,the permit applicant BO B/C/D Review of plans A/C 2/4
shall submit to Building Official for approval, Storm
Water Pollution Prevention Plan (SWPPP) specifically
identifying Best Management Practices (BMPs) that
shall be used on-site to reduce pollutants during
construction activities entering the storm drain system to
the maximum extent practical.
An Erosion Control Plan shall be prepared, included in BO B/C/D Review of plans A/C 2/4
the Grading Plan, and implemented for the proposed
project that identifies specific measures to control on-
site and off-site erosion from the time of ground
disturbing activities are initiated through completion of
grading. This Erosion Control Plan shall include the
following measures at a minimum: a)Specify the timing
of grading and construction to minimize soil exposure to
rainy periods experienced in southern California,and b)
An inspection and maintenance program shall be
included to ensure that any erosion which does occur
either on-site or off-site as a result of this project will be
corrected through a remediation or restoration program
within a specified time frame.
5of8
Mitigation Measures No.I Responsible Monitoring Timing of Method of Verified Sanctions for
Implementing Action for Monitoring Frequency Verification Verification
Date/initials Non-Compliance
During construction, temporary berms such as BO B/C/D Review of plans A/C 2/4
sandbags or gravel dikes must be used to prevent
discharge of debris or sediment from the site when there
is rainfall or other runoff.
During construction, to remove pollutants, street BO B/C/D Review of plans A/C 2/4
cleaning will be performed prior to storm events and
after the use of water trucks to control dust in order to
prevent discharge of debris or sediment from the site.
The developer shall implement the BMPs identified in CE B/C/D Review of plans A/C 2/4
the Water Quality Management Plan (WQMP)prepared
by MDS Consulting (March 2005). to reduce pollutants
after construction entering the storm drain system to the
maximum extent practical.
Landscaping plans shall include provisions for BO B/C/D Review of plans A/C 2/4
controlling and minimizing the use of
fertilizers/pesticides/herbicides. Landscaped areas shall
be monitored and maintained for at least two years to
ensure adequate coverage and stable growth. Plans for
these areas, including monitoring provisions for a
minimum of two years,shall be submitted to the City for
review and approval prior to the issuance of grading
permits.
Prior to issuance of building permits,the applicant shall CE B/C/D Review of plans A/C 2/4
submit to the City Engineer for approval of a WQMP,
including a project description and identifying BMPs that
will be used on-site to reduce pollutants into the storm
drain system to the maximum extent practicable. The
WQMP shall identify the structural and non-structural
measures consistent with the Guidelines for New
Development and Redevelopment adopted by the City of
Rancho Cucamonga in June 2004.
6of8
Mitigation Measures No.I
Responsible g of Method .
ImplementingDate/initials Non-Compliance
Prior to issuance of grading or paving permits,applicant BO B/C/D Review of plans A/C 2/4
shall obtain a Notice of Intent (NOI) to comply with
obtaining coverage under the National Pollutant
Discharge Elimination System (NPDES) General
Construction Storm Water Permit from the State Water
Resources Control Board. Evidence that this has been
obtained (i.e., a copy of the Waste Discharger's
Identification Number) shall be submitted to the City
Building Official for coverage under the NPDES General
Construction Permit.
Noise
Construction or grading shall not take place between the BO C During A 4
hours of 8:00 p.m. and 6:30 a.m. on weekdays, construction
including Saturday, or at any time on Sunday or a
national holiday.
Construction or grading noise levels shall not exceed the BO C During A 4
standards specified in Development Code Section construction
17.02.120-D, as measured at the property line. The
developer shall hire a consultant to perform weekly
noise level monitoring as specified in Development
Code Section 17.02.120. Monitoring at other times may
be required by the Building Official. Said consultant
shall report their findings to the Building Official within 24
hours; however, if noise levels exceed the above
standards, then the consultant shall immediately notify
the Planning Department. If noise levels exceed the
above standards, then construction activities shall be
reduced in intensity to a level of compliance with above
noise standards or halted.
The perimeter block wall shall be constructed as early CP C During A A
as possible in the first phase. construction
7 of 8
Mitigation Measures No.
Responsible
Implementing Action for Monitoring Frequency Verification Verification
Date/initials Non-Compliance
Haul truck deliveries shall not take place between the POW C During A 4/7
hours of 8:00 p.m. and 6:30 a.m. on weekdays, construction
including Saturday, or at any time on Sunday or a
national holiday. Additionally, if heavy trucks used for
hauling would exceed 100 daily trips (counting both to
and from the construction site),then the developer shall
prepare a Noise Mitigation Plan denoting any
construction traffic haul routes. To the extent feasible,
the plan shall denote haul routes that do not pass
sensitive land uses or residential dwellings.
Key to Checklist Abbreviations
Responsible Person Monitoring Frequency Method of Verification Sanctions
CDD-Community Development Director or designee A-With Each New Development A-On-site Inspection 1 -Withhold Recordation of Final Map
CP-City Planner or designee B-Prior To Construction B-Other Agency Permit/Approval 2-Withhold Grading or Building Permit
CE-City Engineer or designee C-Throughout Construction C-Plan Check 3-Withhold Certificate of Occupancy
BO-Building Official or designee D-On Completion D-Separate Submittal(Reports/Studies/Plans) 4-Stop Work Order
PO-Police Captain or designee E-Operating 5-Retain Deposit or Bonds
FC-Fire Chief or designee 6-Revoke CUP
7-Citation
8of8
COMMUNITY DEVELOPMENT
DEPARTMENT
STANDARD CONDITIONS
PROJECT#: TENTATIVE PARCEL MAP SUBTPM17156
SUBJECT: SUBDIVISION OF 12.8 ACRES OF LAND
APPLICANT: RANCHO CUCAMONGA HOUSING PARTNERS, LP
LOCATION: NORTHEAST CORNER OF 9TH STREET AND MADRONE AVENUE
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
APPLICANT SHALL CONTACT THE PLANNING DEPARTMENT, (909) 477-2750, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
A. General Requirements Completion Date
1. The applicant shall agree to defend at his sole expense any action brought against the City, its
agents,officers,or employees,because of the issuance of such approval,or in the alternative,to
relinquish such approval. The applicant shall reimburse the City, its agents, officers, or
employees, for any Court costs and attorney's fees which the City, its agents, officers, or
employees may be required by a court to pay as a result of such action. The City may,at its sole
discretion,participate at its own expense in the defense of any such action but such participation
shall not relieve applicant of his obligations under this condition.
2. Copies of the signed Planning Commission Resolution of Approval No. 05-41, Standard
Conditions, and all environmental mitigations shall be included on the plans (full size). The
sheet(s)are for information only to all parties involved in the construction/grading activities and
are not required to be wet sealed/stamped by a licensed Engineer/Architect.
B. Time Limits
1. This tentative tract map or tentative parcel map shall expire, unless extended by the Planning
Commission, unless a complete final map is filed with the City Engineer within 3 years from the
date of the approval.
C. Site Development
1. Prior to any use of the project site or business activity being commenced thereon,all Conditions
of Approval shall be completed to the satisfaction of the City Planner.
2. All site, grading, landscape, irrigation, and street improvement plans shall be coordinated for
consistency prior to issuance of any permits (such as grading, tree removal, encroachment,
building, etc.)or prior to final map approval in the case of a custom lot subdivision,or approved
use has commenced, whichever comes first.
1
Project No.SUBTPM17156
Completion Date
3. Approval of this request shall not waive compliance with all sections of the Development Code,all
other applicable City Ordinances, and applicable Community or Specific Plans in effect at the
time of building permit issuance.
4. The developer shall submit a construction access plan and schedule for the development of all
lots for City Planner and City Engineer approval; including, but not limited to, public notice
requirements,special street posting, phone listing for community concems,hours of construction
activity, dust control measures, and security fencing.
APPLICANT SHALL CONTACT THE BUILDING AND SAFETY DEPARTMENT, (909)477-2710,
FOR COMPLIANCE WITH THE FOLLOWING CONDITIONS:
NOTE: ANY REVISIONS MAY VOID THESE REQUIREMENTS AND NECESSITATE ADDITIONAL REVIEW(S)
D. Site Development
1. Plans shall be submitted for plan check and approved prior to construction. All plans shall be
marked with the project file number(i.e., DRC2001-00001). The applicant shall comply with the
latest adopted California Codes, and all other applicable codes, ordinances, and regulations in
effect at the time of permit application. Contact the Building and Safety Department for
availability of the Code Adoption Ordinance and applicable handouts.
2. Construction activity shall not occur between the hours of 8:00 p.m. and 6:30 a.m. Monday
through Saturday, with no construction on Sunday or holidays.
E. Grading
1. Grading of the subject property shall be in accordance with California Building Code,City Grading
Standards, and accepted grading practices. The final grading plan shall be in substantial
conformance with the approved grading plan.
2. A soils report shall be prepared by a qualified engineer licensed by the State of California to
perform such work.
APPLICANT SHALL CONTACT THE ENGINEERING DEPARTMENT, (909) 477-2740, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
F. Dedication and Vehicular Access
1. Corner property line cutoffs shall be dedicated per City Standards.
2. Private drainage easements for cross-lot drainage shall be provided and shall be delineated or
noted on the final map.
G. Street Improvements
1. Improvement Plans and Construction:
a. Street improvement plans, including street trees,street lights,and intersection safety lights
on future signal poles, and traffic signal plans shall be prepared by a registered Civil
Engineer and shall be submitted to and approved by the City Engineer. Security shall be
posted and an agreement executed to the satisfaction of the City Engineer and the City
Attorney guaranteeing completion of the public and/or private street improvements,prior to
final map approval or the issuance of building permits, whichever occurs first.
b. Prior to any work being performed in public right-of-way, fees shall be paid and a
construction permit shall be obtained from the City Engineer's Office in addition to any
other permits required.
2
Project No.SUBTPM17156
Completion Date
C. Pavement striping, marking,traffic signing,street name signing,traffic signal conduit,and
interconnect conduit shall be installed to the satisfaction of the City Engineer.
d. Signal conduit with pull boxes shall be installed with any new construction or reconstruction
project along major or secondary streets and at intersections for future traffic signals and
interconnect wiring. Pull boxes shall be placed on both sides of the street at 3 feet outside
of BCR, ECR, or any other locations approved by the City Engineer
Notes:
1) Pull boxes shall be No.6 at intersections and No.5 along streets,a maximum of 200
feet apart, unless otherwise specified by the City Engineer.
2) Conduit shall be 3-inch galvanized steel with pull rope or as specified.
e. Handicapped access ramps shall be installed on all corners of intersections per City
Standards or as directed by the City Engineer.
f. Existing City roads requiring construction shall remain open to traffic at all times with
adequate detours during construction. Street or lane closure permits are required. A cash
deposit shall be provided to cover the cost of grading and paving,which shall be refunded
upon completion of the construction to the satisfaction of the City Engineer.
g. Concentrated drainage flows shall not cross sidewalks. Under sidewalk drains shall be
installed to City Standards, except for single family residential lots.
h. Street names shall be approved by the City Planner prior to submittal for first plan check.
H. Improvement Completion
1. If the required public improvements are not completed prior to approval of the final parcel map,
an improvement security accompanied by an agreement executed bythe Developer and the City
will be required for: 9th Street frontage improvements along Parcel 3.
2. If the required public improvements are not completed prior to approval of the final parcel map,
an improvement certificate shall be placed upon the final parcel map, stating that they will be
completed upon development for:
a. Parcel 1 development shall be responsible for 9th Street improvements along the frontage
of Parcels 1 and 2, and installation of or provide fair share contribution in lieu of
constriction for the 9th Street storm drain.
b. Parcel 2 development shall be responsible for Madrone Avenue improvements along the
property frontage.
C. Parcel 3 redevelopment shall be responsible for Madrone Avenue improvements along the
property frontage.
I. Utilities
1. Provide separate utility services to each parcel including sanitary sewerage system,water,gas,
electric power, telephone, and cable TV (all underground) in accordance with the Utility
Standards. Easements shall be provided as required.
2. The developer shall be responsible for the relocation of existing utilities as necessary.
3. Water and sewer plans shall be designed and constructed to meet the requirements of the
Cucamonga Valley Water District(CVWD), Rancho Cucamonga Fire Protection District,and the
Environmental Health Department of the County of San Bernardino. A letter of compliance from
the CVWD is required prior to final map approval or issuance of permits,whichever occurs first.
Such letter must have been issued by the water district within 90 days prior to final map approval
in the case of subdivision or prior to the issuance of permits in the case of all other residential
projects.
3
Project No.SUBTPM17156
Completion Date
4. Approvals have not been secured from all utilities and other interested agencies involved.
Approval of the final parcel map will be subject to any requirements that may be received from
them.
J. General Requirements and Approvals
1. A non-refundable deposit shall be paid to the City,covering the estimated operating costs for all
new streetlights for the first six months of operation,prior to final map approval or priorto building
permit issuance if no map is involved.