HomeMy WebLinkAbout2009/10/06 - Agenda Packet DESIGN REVIEW COMMITTEE MEETING
TUESDAY OCTOBER 6, 2009 7:00 P.M.
RANCHO CUCAMONGA CIVIC CENTER
RAINS ROOM
10500 CIVIC CENTER DRIVE
RANCHO CUCAMONGA
ACTION AGENDA
•
Committee Members: Lou Munoz Pam Stewart Corkran Nicholson
Alternates: Ray Wimberly Frances Howdyshell Richard Fletcher
CONSENT CALENDAR
NO ITEMS SUBMITTED.
PROJECT REVIEW ITEMS
This is the time and place for the Committee to discuss and provide direction to an applicant regarding
their development application. The following items do not legally require any public testimony, although
the Committee may open the meeting for public input.
7:00 p.m.
(Steve/Willie) DEVELOPMENT REVIEW DRC2009-00413 - STANTEC CONSULTING -
COMERICA BANK - A request to construct a retail bank with a drive-thru at an
existing retail center within the Industrial Park District, Subarea 7, located at
12035 Foothill Boulevard —APN: 0229-023-05.
PUBLIC COMMENTS
There were no public comments.
ADJOURNMENT
The meeting adjourned at 7:10 p.m.
DESIGN REVIEW COMMENTS
October 6, 2009
ADJOURNMENT
The meeting adjourned at 7:10 p.m.
Respe
espe ubmiit ted,
' ' L _1
Corkran W. Nicholson
DESIGN REVIEW COMMENTS
7:00 p.m. Steve Fowler October 6, 2009
DEVELOPMENT REVIEW DRC2009-00413 - STANTEC CONSULTING - COMERICA BANK - A request
to construct a retail bank with a drive-thru at an existing retail center within the Industrial Park District,
Subarea 7, located at 12035 Foothill Boulevard —APN: 0229-023-05.
Design Parameters: The applicant is proposing to construct a 3,982 square foot bank building with a
drive thru ATM located at 12035 Foothill Boulevard. This site is on the south side of Foothill Boulevard in
the Low Residential District.
The design of the site was previously approved under DRC2005-01084. The .74-acre parcel is a vacant
pad at the east end of the previously approved project that sits approximately 8 feet below street level.
The building is a single-story, institutional style structure. Some of the features include a 27-foot tall
tower element on the southwest corner of the building and a drive up ATM on the north side of the
building. The exterior of the building is proposed to use a mixture of mountain rose colored brick veneer
for the wall plans, a frosted almond colored brick veneer band around the lower part of the entire
building, stone veneer for the tower element and columns around the entire building, and a standing
seam metal roof that matches an existing roof within the same center. The building utilizes materials
from the existing buildings to incorporate it into the center but does not duplicate the style.
The proposed landscape around the building will compliment the existing site landscaping. The signage
locations have been indicated on the plans to allow for the review of future placement as it corresponds
with the building. The signage will be submitted under a sign permit package at a later date.
Staff Comments: The following comments are intended to provide an outline for the Committee
discussion regarding this project.
Major Issues: The applicant worked with staff to follow the criteria outlined in the Development Code.
There are no major issues regarding this project at this time.
Staff recommendation: Staff recommends that the Design Review Committee recommend approval of
this Conditional use Permit to the Planning Commission.
Design Review Committee Action:
The Committee members requested that the applicant change the roof material from a metal roof to a tile
roof. The applicant agreed to make the change and turn it back in for review. The Committee agreed to
review it and possibly approve it as a Consent Item at a later meeting.
Members Present: Munoz, Stewart, Nicholson
Staff Planner: Steve Fowler