HomeMy WebLinkAbout1991/07/18 - Agenda PacketDATE:
TO:
July 23, 1991
CITY OF RANCH0 CUCAMONGA
MEMORANDUM
ACTION DOCUMENTS
C~CAM~
1977
Commercial/Industrial
Design Review Committee
Suzanne Chitlea
Wendy Vallette
Otto Kroutil
John Melcher (Alternate
FROM: Scott Murphy, Associate Planner~
SUBJECT: DESIGN REVIEW COMMITTEE MEETING OF JULY 18, 1991
The following is a description of projects which require review and
rating by the Design Review Committee. Please review the attached
plans, visit the project sites, and write down your comments using the
blank space provided under each project on the attached sheets. After
the meeting, the consensus of the Committee's concerns will be typed up
as the formal action/recommendation of the Committee and distributed to
the Commission and Council.
As always, feel free to contact the appropriate project manager (noted
in parentheses along the left margin), prior to the meeting date, if you
have specific questions related to the scheduled projects. Dinner will
be provided between 5:00 5:45 p.m., Consent Calendar items will be
reviewed between 5:45 p.m. - 6:30 p-m-, with the first design review
item being heard at 6:30 p.m. Please notify our department if you will
be unable to attend the meeting, or if you will be late, so that the
dinner can be properly ordered and the necessary arrangements made-
6:30 - 7:00
(Steve H-)
DEVELOPMENT REVIEW 91-04 WELLS FARGO BANK - The
proposed development of a 4,525 square foot bank on
Pad 10 within the previously approved Vineyards
Marketplace Shopping Center, which consists of
11 buildings totaling 121,401 square feet on 12.8 acres
of land in the Village Commercial District of the
Victoria Community Plan, located at the southeast corner
of Highland Avenue and Milliken Avenue - APN: 227-011-
22.
7:30 - 8:30
(Dan)
pLANNING COMMISSION WORKSHOP
PLAN
- TRAILS
IMPLEMENTATION
DRC AGENDA
JULY 18, 1991
Page 2, 1991
8:30 - 9:30
(Nancy)
pLANNING COMMISSION WORKSHOP - AMENDMENT TO TERRA VISTA
TOWN CENTER SIGN PROGRAM
SM:mlg
Attachments
cc: Planning Commission/City Council
COMMERCIAL/INDUSTRIAL
CONSENT CALENDAR rr~S A~DA
July 18, 1991
cur 90--42 - ~G~LES INVESTMENTS
(Steve H. ) Revised tile samples.
Committee Action:
The Design Review Committee (Vallette,
Melcher, Kroutil) recommended that
this item be continued until the
August 8, 1991 Design Review Consent
Calendar to allow the applicant the
opportunity to explore color and
texture alternatives for the proposed
tiles-
DESIGN REVIEW COMMENTS
6:30 - 7:00 Steve H.
July 18, 1991
DEVELOPMENT REVIEW 91-04 - WELLS FARGO BANK - The proposed development
of a 4,525 square foot bank on Pad 10 within the previously approved
Vineyards Marketplace Shopping Center, which consists of 11 buildings
totaling 121,401 square feet on 12.8 acres of land in the Village
Commercial District of the Victoria Community Plan, located at the
southeast corner of Highland Avenue and Milliken Avenue - APN: 227-011-
22.
Background:
The Vineyards Marketplace Shopping Center was approved by the Planning
Commission On November 29, 1989. At that time, the pad in question was
located where Building 11 is plotted, adjacent to the Kenyon Way drive
entrance. However, the Planning Commission approved a switch of
building pads for Buildings 10 and 11 at their meeting of
April 10, 1991, with the specific Design Review approval Of Building 11
in its new location occurring on May 16, 1991.
On June 20, 1991, the Committee (Chitiea, Vallette, Kroutil) reviewed
the proposed bank building but did not recommend approval of the project
as presented. It was recommended that the project return for further
review with the following items incorporated into the project design:
The entire building should be shifted 3 to 4 feet to the north in
order to incorporate a colonade on the south side of the
building. The existing colonade on the north elevation may be
reduced in width accordingly, but not to be less than 4 feet wide.
2. A colonade or articulated Overhang should be provided over the
planter on the west elevation-
3- Solid decorative doors and additional windows should be provided on
the buildings west elevation.
The area framing the automatic teller machines should appear as a
separate finished element by utilizing a tile wainscot or layered
accent element as a backdrop.
A decorative element should be added under the tower arch on the
north elevation.
e
Mexican tile bulkheads, consistent with the tile bulkheads utilized
on other buildings, should be incorporated on the elevations-
Additional trees and shrubs should be included along the north and
east building frontages, beyond the roof overhangs, similar to the
approved landscape concept for the front of other buildings-
DESIGN REVIEW COMMENTS
DR 91-04 - WELLS FARGO BANK
JULY 18, 1991
Page 2
All landscape species should be consistent with approved landscape
palette for the entire shopping center-
Staff COmments:
At the time of comment preparation, the revised plans had not yet been
submitted to staff. Therefore, the Co~nittee should review the revised
plan in light of the previous meetings comments.
Design Review COmmittee Action:
Members Present: Wendy Vallette, John Melcher, Otto Kroutil
Staff Planner: Steve Hayes
The Committee did not recommend approval of the project as presented-
They directed the applicant to incorporate the following changes into
the design and, if staff is satisfied that the changes are addressed,
the project could be reviewed at the next available Design Review
Consent Calendar.
The large pop-out element near the southwest corner of the building
should be redesigned- Suggested methods include:
a)
Bring down a shed roof element that ties into other rooflines
on the building;
b) Provide double columns under this element to appear more
supportive for the apparent mass of this element- If this is
selected, the columns should rise from the inner arch of the
pop-out.
In order to reduce the combined slope/building height as seen from
Kenyon Way, the Con~nittee suggested that the southern elevation of
the building could be reduced in height, while keeping with the
same proportions (example: arches, roof pitch, etc.) with the
balance of the building and other buildings within the center. By
doing this, the Committee would be willing to support a future
Minor Exception for building setback from Kenyon Way from 35 feet
to 33 feet-
A design alternative to the trellis element under the north
elevation tower arch should be explored by the architect.
Suggested options included an ornamental medallion quatrafoil or a
tile wainscot.
4. The tile wainscot should be provided below the ATM structure-
DESIGN REVIEW COMMENTS
DR 91-04 - WELLS FARGO BANK
JULY 18, 1991
Page 3
AS stated at the last meeting, the doors on the west elevation
should be decorative, yet be designed in such a way whereas the
public does not perceive this to be the primary building entrance-
Additional trees and shrubs should be included along the north and
east building frontages, beyond the roof overhangs, similar to the
approved landscape concept for the front of other buildings.