HomeMy WebLinkAbout94-67 - Resolutions RESOLUTION NO. 94-67
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
RANCHO CUCAMONGA, CALIFORNIA, APPROVING CONDITIONAL USE
PERMIT NO. 93-46, A REQUEST TO CONSTRUCT A GAS STATION
AND MINI-MARKET ON A 0.63 ACRE PARCEL OF LAND IN THE
COMMUNITY COMMERCIAL DESIGNATION (SUBAREA 2) OF THE
FOOTHILL BOULEVARD SPECIFIC PLAN, LOCATED AT THE
SOUTHEAST CORNER OF FOOTHILL BOULEVARD AND VINEYARD
AVENUE, AND MAKING FINDINGS IN SUPPORT THEREOF -
APN: 208-192-06.
A. Recitals.
1. Art and Diane Flores have filed an application for the issuance
of Conditional Use Permit No. 93-46, as described in the title of this
Resolution. Hereinafter in this Resolution, the subject Conditional Use
Permit request is referred to as "the application. "
2. On the 27th day of July 1994, the Planning Commission of the City
of Rancho Cucamonga conducted a duly noticed public hearing on the application
and concluded said hearing on that date.
3. All legal prerequisites prior to the adoption of this Resolution
have occurred.
B. Resolution.
NOW, THEREFORE, it is hereby found, determined, and resolved by the
Planning Commission of the City of Rancho Cucamonga as follows:
1. This Commission hereby specifically finds that all of the facts
set forth in the Recitals, Part A, of this Resolution are true and correct.
2. Based upon substantial evidence presented to this Commission
during the above-referenced public hearing on July 27, 1994, including written
and oral staff reports, together with public testimony, this Commission hereby
specifically finds as follows:
a. The application applies to property located at the southeast
corner of Foothill Boulevard and Vineyard Avenue with a street frontage of 140
feet along Foothill Boulevard and 155 feet along Vineyard Avenue and is
presently vacant; and
b. The property to the north of the subject site is designated
for commercial uses and is developed with a commercial center, the property to
the south is designated for residential uses and is developed with a
condominium project, the property to the east is designated for commercial
uses and is developed with a fast food restaurant, and the property to the
west is designated for commercial uses and is vacant; and
c. The development of a gas station and mini-market is
consistent with the Community Commercial designation of the Foothill Boulevard
Specific Plan and the Commercial designation of the General Plan; and
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 2
d. The application, together with the attached conditions of
approval, will comply with all applicable standards of the Development Code;
and
e. The application maintains the same parking setback along
Foothill Boulevard of 40 feet as approved as part of Variance No. 88-09.
3. Based upon the substantial evidence presented to this Commission
during the above-referenced public hearing and upon the specific findings of
facts set forth in paragraphs 1 and 2 above, this Commission hereby finds and
concludes as follows:
a. That the proposed use is in accord with the General Plan,
the objectives of the Development Code, and the purposes of the district in
which the site is located.
b. That the proposed use, together with the conditions
applicable thereto, will not be detrimental to the public health, safety, or
welfare or materially injurious to properties or improvements in the vicinity.
c. That the proposed use complies with each of the applicable
provisions of the Development Code.
4. Based upon the facts and information contained in the proposed
Negative Declaration, together with all written and oral reports included for
the environmental assessment for the application, the Planning Commission
finds that there is no substantial evidence that the project will have a
significant effect upon the environment and adopts a Negative Declaration
based upon the findings as follows:
a. That the Negative Declaration has been prepared in
compliance with the California Environmental Quality Act of 1970, as amended,
and the State CEQA guidelines promulgated thereunder; that said Negative
Declaration and the Initial Study prepared therefore reflect the independent
judgment of the Planning Commission; and, further, this Commission has
reviewed and considered the information contained in said Negative Declaration
with regard to the application.
b. That, based upon the changes and alterations which have been
incorporated into the proposed project, no significant adverse environmental
effects will occur.
c. Pursuant to the provisions of Section 753.5(c) of Title 14,
of the California Code of Regulations, the Planning Commission finds as
follows: In considering the record as a whole, the Initial Study and Negative
Declaration for the project, there is no evidence that the proposed project
will have potential for an adverse impact upon wildlife resources or the
habitat upon which wildlife depends. Further, based upon substantial evidence
contained in the Negative Declaration, the staff reports and exhibits, and the
information provided to the Planning Commission during the public hearing, the
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 3
Planning Commission hereby rebuts the presumption of adverse effect as set
forth in Section 753.5(c-1-d) of Title 14 of the California Code of
Regulations.
5. Based upon the findings and conclusions set forth in paragraphs
1, 2, 3, and 4 above, this Commission hereby approves the application subject
to each and every condition set forth below and in the Standard Conditions,
attached hereto and incorporated herein by this reference.
Planning Division
1) The street trees along Foothill Boulevard and
Vineyard Avenue shall be planted at 30 feet on
center consistent with the Foothill Boulevard
Specific Plan (FBSP) . The final plans shall be
reviewed and approved by the City Planner prior
to building permit issuance.
2) The sidewalks along Foothill Boulevard and
Vineyard Avenue shall extend to the raised
planters. That portion of sidewalk outside of
the public right-of-way shall be maintained by
the property owner.
3) Decorative light fixtures, benches, potted
plants, and trash receptacles shall be provided
consistent with the FBSP. The final plans shall
be reviewed and approved by the City Planner
prior to building permit issuance.
4) The canopy fascia lighting shall be
eliminated. The final plans shall be reviewed
and approved by the City Planner prior to
building permit issuance.
5) Details of the project shall be worked out with
staff prior to building permit issuance.
6) A comprehensive sign program shall be reviewed
and approved by the City Planner prior to
building permit issuance.
7) The parallel parking stall on the west side of
the site shall be modified to expand the
landscape area on the south end and replace the
landscaping on the north end with a painted
stripe. The final plans shall be reviewed and
approved by the City Planner prior to building
permit issuance.
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 4
8) Extensive landscaping shall be provided along
the south property line. The final plans shall
be reviewed and approved by the City Planner
prior to building permit issuance.
9) Provisions for the following design features in
the trash enclosure, to the satisfaction of the
City Planner:
a) Architecturally integrated into the design
of the project.
b) Separate pedestrian access that does not
require the opening of the main doors.
c) Large enough to accommodate two trash bins.
d) Roll-up doors.
e) Trash bins with counter-weighted lids.
f) Architecturally treated overhead shade
trellis.
g) Chain link screen on top to prevent trash
from blowing out of the enclosure and
designed to be hidden from view.
10) Trash collection shall occur between the hours
of 9 a.m. and 10 p.m. only.
11) Graffiti shall be removed within 72 hours.
12) The entire site shall be kept free from trash
and debris at all times, and in no event shall
trash and debris remain for more than 24 hours.
13) Signs shall be conveniently posted for "no
overnight parking" and for "employee parking
only. "
14) All operations and businesses shall be conducted
to comply with the following standards which
shall be incorporated into the lease agreements
of all tenants:
a) Noise level - All commercial activities
shall not create any noise that would exceed
an exterior noise level of 60 dB during the
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 5
hours of 10 p.m. to 7 a.m. , and 65 dB during
the hours of 7 a.m. to 10 p.m.
b) Loading and Unloading - No person shall
cause the loading, unloading, opening,
closing, or other handling of boxes, crates,
containers, building materials, garbage
cans, or other similar objects between the
hours of 10 p.m. and 7 a.m. , unless
otherwise specified herein, in a manner
which would cause a noise disturbance to a
residential area.
Engineering Division
1) The existing overhead utilities
(telecommunication and electrical, excluding 66
kv lines) shall be undergrounded as follows:
a) Vineyard Avenue from the first pole south of
the south project boundary to the first pole
on the north side of Foothill Boulevard.
b) South project boundary - from the pole at
the west project boundary to the first pole
east of the east project boundary.
The developer may request a reimbursement
agreement to recover one-half of the City
adopted cost for undergrounding from future
development or redevelopment as it occurs on the
adjacent parcel to the south or on the opposite
side of Vineyard Avenue.
2) Foothill Boulevard:
a) An additional 15-foot dedication of right-
of-way shall be required for a total
distance of 75 feet as measured from the
street centerline.
b) Full improvements on the south side from
Vineyard Avenue to the east property line.
Provide necessary improvements easterly
thereof, for transitioning, as approved by
the City Engineer and CalTrans.
3) If CalTrans does not allow the minimal 15-foot
dedication, Foothill Boulevard shall be
constructed as follows:
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 6
a) An additional 17-foot dedication of right-
of-way shall be required for a total
distance of 77 feet as measured from the
street centerline.
b) Full improvements on the south side, per the
Project Study Report (excluding the bus-bay
right turn lane) from Vineyard Avenue to the
east property line. Provide necessary
improvements easterly thereof, for
transitioning as approved by the City
Engineer and CalTrans.
4) Foothill Boulevard (items necessary regardless
of dedication) :
a) Acquire necessary additional right-of-way to
transition public improvements from the
property adjacent to the east.
b) A contribution in lieu of construction for
one-half the cost of the median island
within Foothill Boulevard, including
landscaping and irrigation, shall be paid to
the City prior to the issuance of building
permits. The value of the median island
shall be based on the distance from the
centerline of Vineyard Avenue to the
easterly property line of Assessor's Parcel
No. 208-192-06.
c) The parkway activity center shall be
constructed per the Foothill Boulevard
Specific Plan as approved by the City
Engineer and CalTrans.
5) Vineyard Avenue shall be constructed as follows:
a) Full improvements on the east side from
Foothill Boulevard to the south property
line with necessary transition as determined
by the City Engineer.
b) All improvements shall be constructed with
respect to the new centerline of
construction as it was determined for the
required improvements of Parcel Map 12596.
c) The parkway activity center shall be
constructed per the Foothill Boulevard
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 7
Specific Plan. Sidewalk easements shall be
provided for as necessary.
6) Modification and relocation, as necessary, of
the traffic signal at the Foothill
Boulevard/Vineyard Avenue intersection shall be
the responsibility of the developer. The
relocation and modification shall be to the
satisfaction of the City Engineer and CalTrans.
7) "No Parking/Stopping" signs shall be posted
along the frontages of Foothill Boulevard and
Vineyard Avenue.
8) A contribution in lieu of construction towards
one-fourth the cost of constructing special
pavers within the Foothill Boulevard/Vineyard
Avenue intersection shall be paid to the City
prior to the issuance of building permits and
shall be based on the square footage of the
intersection.
9) The developer shall obtain a right-of-entry for
driveway removal and parking lot reconstruction
from the property owner to the east prior to the
issuance of any permits.
10) The Foothill Boulevard driveway shall serve as a
joint access for Assessor's Parcel Nos.
208-192-06, 07, and 08. A signed and recorded
agreement between the owners of all affected
parcels shall be submitted prior to the issuance
of building permits.
11) The island proposed within the Foothill
Boulevard driveway shall be placed behind the
sidewalk outside of the public right-of-way.
12) On Foothill Boulevard, the sidewalk shall be
extended to the curb within the bus stop area.
The length will be to the satisfaction of the
City Engineer.
13) The band of decorative pavement within the
Vineyard Avenue access shall be located behind
the public sidewalk.
14) A corner cut off for the right-of-way at the
intersection of Foothill Boulevard and Vineyard
Avenue shall be dedicated to the satisfaction of
the City Engineer.
PLANNING COMMISSION RESOLUTION NO. 94-67
CUP 93-46 - FLORES
July 27, 1994
Page 8
6. The Secretary to this Commission shall certify to the adoption of
this Resolution.
APPROVED AND ADOPTED THIS 27TH DAY OF JULY 1994.
PL. . "ti ISSION "F THE Q OF RANCHO CUCAMONGA
1
BYL lialr llira 4
w'W - an
104#4.1.1"
ATTEST: w(ll.
Brad minmer, wry
I, Brad Buller, Secretary of the Planning Commission of the City of Rancho
Cucamonga, do hereby certify that the foregoing Resolution was duly and
regularly introduced, passed, and adopted by the Planning Commission of the
City of Rancho Cucamonga, at a regular meeting of the Planning Commission held
on the 27th day of July 1994, by the following vote-to-wit:
AYES: COMMISSIONERS: BARKER, LUMPP, MCNIEL, MELCHER, TOLSTOY
NOES: COMMISSIONERS: NONE
ABSENT: COMMISSIONERS: NONE
, ,
gtro. • DEPARTMENT OF
RanChoCucatnonga COMMUNITY DEVELOPMENT
STANDARD CONDITIONS
PROJECT#: CQti?1O4CQ/ ° il,
SUBJECT: as cioa //�//!/-Msf
r�
APPLICANT: tZere.5 ! ��
LOCATION: <Tee teefki �'/i1G°�ani
Those items checked are Conditions of Approval.
J
APPLICANT SHALL CONTACT THE PLANNING DIVISION , (909) 989-1861, FOR COMPLIANCE
WITH THE FOLLOWING CONDITIONS:
A. Time Limits Compledcn Date
1. Approval shall expire,unless extended by the Planning Commission, if building permits are ��-
not issued or approved use has not commenced within 24 months from the date of approval.
2. Development/Design Review shall be approved prior to / / ��-
3. Approval of Tentative Tract No. is granted subject to the approval of
4. The developer shall commence,participate in,and consummate or cause to be commenced,
participated in, or consummated, a Mello-Roos Community Facilities District (CFD) for the
Rancho Cucamonga Fire Protection District to finance construction and/or maintenance of
a fire station to serve the development. The station shall be located, designed, and built to
all specifications of the Rancho Cucamonga Fire Protection District, and shall become the
Districts properly upon completion. The equipment shall be selected by the District in
accordance with its needs. In any building of a station, the developer shall comply with all
applicable laws and regulations. The CFD shall be formed by the District and the developer
by the time recordation of the final map occurs.
5. Prior to recordation of the final map or the issuance of building permits, whichever comes !.J
first, the applicant shall consent to, or participate in, the establishment of a Mello-Roos
Community Facilities District for the construction and maintenance of necessary school
• facilities. However, it any school district has previously established such a Community
Facilities District, the applicant shall, in the alternative, consent to the annexation of the
project site into the territory of such existing District prior to the recordation of the final map
or the issuance of building permits, whichever comes first. Further, if the affected school
district has not formed a Mello-Roos Community Facilities District within twelve months from
the date of approval of the project and prior to the recordation of the final map or issuance
of building permits for said project, this condition shall be deemed null and void.
SC - 12/93 1 of 12
Project N' !d
Completion Date:
This condition shall be waived if the City receives notice that the applicant and all affected
school districts have entered into an agreement to privately accommodate any and all school
impacts as a result of this project.
✓ 6. Prior to recordation of the final map or prior to issuance of building permits when no map is / /_
involved,written certification from the affected water district that adequate sewer and water
facilities are or will be available to serve the proposed project shall be submitted to the
Department of Community Development. Such letter must have been issued by the water
district within 90 days prior to final map approval in the case of subdivision or prior to issuance
of permits in the case of all other residential projects.
B. Site Development
1. The site shall be developed and maintained in accordance with the approved plans which ��-
include site plans, architectural elevations, exterior materials and colors, landscaping,sign
program, and grading on file in the Planning Division, the conditions contained herein,
Development Code regulations, and ,,4t f/// ,c 4Y//evird
Specific Plan and
/ Planned Community.
Y 2. Prior to any use of the project site or business activity being commenced thereon, all / /
Conditions of Approval shall be completed to the satisfaction of the City Planner.
3. Occupancy of the facility shall not commence until such time as all Uniform Building Code and ��-
State Fire Marshall's regulations have been complied with. Prior to occupancy, plans shall
be submitted to the Rancho Cucamonga Fire Protection District and the Building and Safety -
Division to show compliance. The building shall be inspected for compliance prior to
occupancy.
4. Revised site plans and building elevations incorporating all Conditions of Approval shall be / /-
submitted for City Planner review and approval prior to issuance of building permits.
17 5. All site,grading,landscape, irrigation,and street improvement plans shall be coordinated for J�
consistency prior to issuance of any permits(such as grading,tree removal,encroachment,
building , etc.), or prior to final map approval in the case of a custom lot subdivision, or
approved use has commenced, whichever comes first.
6. Approval of this request shall not waive compliance with all sections of the Development
Code, all other applicable City Ordinances, and applicable Community Plans or Specific
Plans in effect at the time of Building Permit issuance.
1/ 7. A detailed on-site lighting plan shall be reviewed and approved by the City Planner and
Sheriff's Department (989-6611) prior to the issuance of building permits. Such plan shall
indicate style, illumination, location, height, and method of shielding so as not to adversely
affect adjacent properties.
8. If no centralized trash receptacles are provided,all trash pick-up shall be for individual units / /-
with all receptacles shielded from public view.
f- 9. Trash receptacle(s)are required and shall meet City standards. The final design,locations, —/—l-
and the number of trash receptacles shall be subject to City Planner review and approval
prior to issuance of building permits.
10.All ground-mounted utility appurtenances such as transformers,AC condensers, etc., shall ��-
be located out of public view and adequately screened through the use of a combination of
concrete or masonry walls, berming, and/or landscaping to the satisfaction of the City
Planner.
SC - 12/93 2 of 12
Project \" f f •y
Compieuon D3tc:
11. Street names shall be submitted for City Planner review and approval in accordance with /
the adopted Street Naming Policy prior to approval of the final map.
12.All building numbers and individual units shall be identified in a clear and concise manner, _1_1_
including proper illumination.
13. A detailed plan indicating trail widths, maximum slopes, physical conditions, fencing, and J /
weed control, in accordance with City Master Trail drawings, shall be submitted for City
Planner review and approval priorto approval and recordation of the Final Tract Map and prior
to approval of street improvement and grading plans. Developer shall upgrade and construct
all trails, including fencing and drainage devices, in conjunction with street improvements.
14.The Covenants.Conditions and Restrictions(CC&Rs)shall not prohibit the keeping of equine
animals where zoning requirements for the keeping of said animals have been met.Individual
lot owners in subdivisions shall have the option of keeping said animals without the necessity
of appealing to boards of directors or homeowners' associations for amendments to the
CC&Rs.
15.The Covenants, Conditions, and Restrictions (CC&Rs) and Articles of Incorporation of the _1_1_
Homeowners' Association are subject to the approval of the Planning and Engineering
Divisions and the City Attorney. They shall be recorded concurrently with the Final Map or
prior to the issuance of building permits, whichever occurs first. A recorded copy shall be
provided to the City Engineer.
16. All parkways, open areas,and landscaping shall be permanently maintained by the property J /-
owner, homeowners' association, or other means acceptable to the City. Proof of this -- -
landscape maintenance shall be submitted for City Planner and City Engineer review and
approval prior to issuance of building permits.
17. Solar access easements shall be dedicated for the purpose of assuming that each lot or dwelling unit unit shall have the right to receive sunlight across adjacent lots or units for use of
a solar energy system.The easements may be contained in a Declaration of Restrictions for
the subdivision which shall be recorded concurrently with the recordation of the final map or
issuance of permits, whichever comes first. The easements shall prohibit the casting of
shadows by vegetation, structures, fixtures or any other object, except for utility wires and
similar objects, pursuant to Development Code Section 17.08.060-G-2.
18. The project contains a designated Historical Landmark. The site shall be developed and JJ-
maintained in accordance with the Historic Landmark Alteration Permit No.
. Any further modifications to the site including,but not limited to,exterior alterations and/or
interior alterations which affect the exterior of the buildings or structures,removal of landmark
trees,demolition,relocation,reconstruction of buildings or structures,or changes to the site,
shall require a modification to the Historic Landmark Alteration Permit subject to Historic
Preservation Commission review and approval.
C. Building Design
1. An alternative energy system is required to provide domestic hot water for all dwelling units -JJ_
and for heating any swimming pool or spa, unless other alternative energy systems are
demonstrated to be of equivalent capacity and efficiency. All swimming pools installed at the
time of initial development shall be supplemented with solar heating. Details shall be
included in the building plans and shall be submitted for City Planner review and approval
prior to the issuance of building permits.
2. All dwellings shall have the front, side and rear elevations upgraded with architectural J�-
treatment, detailing and increased delineation of surface treatment subject to City Planner
review and approval prior to issuance of building permits.
SC - 12/93 3 of 12
Protect Roar 9T'44
Completion Date:
3. Standard patio cover plans for use by the Homeowners' Association shall be submitted for / /
City Planner and Building Official review and approval prior to issuance of building permits.
✓ 4. All roof appurtenances,including air conditioners and other roof mounted equipment and/or _I
projections,shall be shielded from view and the sound buffered from adjacent properties and
streets as required by the Planning Division. Such screening shall be architecturally
integrated with the building design and constructed to the satisfaction of the City Planner.
Details shall be included in building plans.
D. Parking and Vehicular Access (indicate details on building plans)
1/ 1. All parking lot landscape islands shall have a minimum outside dimension of 6 feet and shall ��-
contain a 12-inch walk adjacent to the parking stall (including curb).
t/ 2. Textured pedestrian pathways and textured pavement across circulation aisles shall be -J /—
provided throughout the development to connect dwellings/units/buildings with open spaces/
plazas/recreational uses.
3. All parking spaces shall be double striped per City standards and all driveway aisles, J—/—
entrances, and exits shall be striped per City standards.
4. All units shall be provided with garage door openers if driveways are less than 18 feet in
depth from from back of sidewalk.
5. The Covenants,Conditions and Restrictions shall restrict the storage of recreational vehicles J—/—
on this site unless they are the principal source of transportation for the owner and prohibit -
parking on interior circulation aisles other than in designated visitor parking areas.
6. Plans for any security gates shall be submitted for the City Planner, City Engineer, and ��-
Rancho Cucamonga Fire Protection District review and approval prior to issuance of building
permits.
E. Landscaping (for publicly maintained landscape areas, refer to Section N.)
1. A detailed landscape and irrigation plan,including slope planting and model home landscap-
ing in the case of residential development, shall be prepared by a licensed landscape
architect and submitted for City Planner review and approval prior to the issuance of building
permits or prior final map approval in the case of a custom lot subdivision.
2. Existing trees required to be preserved in place shall be protected with a construction barrier
in accordance with the Municipal Code Section 19.08.110,and so noted on the grading plans.
The location of those trees to be preserved in place and new locations for transplanted trees
shall be shown on the detailed landscape plans. The applicant shall follow allot the arborist's
recommendations regarding preservation, transplanting and trimming methods.
3. A minimum of trees per gross acre,comprised of the following sizes,shall be provided ��-
within the project: %-48-inch box or larger, %-36-inch box or larger,
- 24- inch box or larger, % - 15-gallon, and % - 5 gallon.
4. A minimum of 20 %of trees planted within the project shall be specimen size trees - ��-
24-inch box or larger.
5. Within parking lots, trees shall be planted at a rate of one 15-gallon tree for every three _J /-
parking stalls, sufficient to shade 50%of the parking area at solar noon on August 21.
SC - 12/93 4 of 12
Protect\U( l'f'
Cornrleeon Date
6. Trees shall be planted in areas of public view adjacent to and along structures at a rate of one
tree per 30 linear feet of building. ��-
7. All private slope banks 5 feet or less in vertical height and of 5:1 or greater slope,but less than / /
2:1 slope,shall be, at minimum,irrigated and landscaped with appropriate ground cover for
erosion control. Slope planting required by this section shall include a permanent irrigation
system to be installed by the developer prior to occupancy.
8. All private slopes in excess of 5 feet,but less than 8 feet in vertical height and of 2:1 or greater ��-
slope shall be landscaped and irrigated for erosion control and to soften their appearance as
follows:one 15-gallon or larger size tree per each 150 sq.ft.of slope area, 1-gallon or larger
size shrub per each 100 sq.ft.of slope area,and appropriate ground cover.In addition,slope
banks in excess of 8 feet in vertical height and of 2:1 or greater slope shall also include one
5-gallon or larger size tree per each 250 sq. ft. of slope area. Trees and shrubs shall be
planted in staggered clusters to soften and vary slope plane.Slope planting required by this
section shall include a permanent irrigation system to be installed by the developer prior to
occupancy.
9. For single family residential development, all slope planting and irrigation shall be continu- J�
ously maintained in a healthy and thriving condition by the developer until each individual unit
is sold and occupied by the buyer. Prior to releasing occupancy for those units,an inspection
shall be conducted by the Planning Division to determine that they are in satisfactory
condition.
10. For multi-family residential and non-residential development, property owners are respon-
sible for the continual maintenance of all landscaped areas on-site, as well as contiguous
planted areas within the public right-of-way. All landscaped areas shall be kept free from
weeds and debris and maintained in a healthy and thriving condition, and shall receive -
regular pruning, fertilizing, mowing, and trimming. Any damaged, dead, diseased, or
decaying plant material shall be replaced within 30 days from the date of damage.
11. Front yard landscaping shall be required per the Development Code and /or
—J-
. This requirement shall be in addition to the required
street trees and slope planting.
12.The final design of the perimeter parkways, walls, landscaping, and sidewalks shall be / /_
included in the required landscape plans and shall be subject to City Planner review and
approval and coordinated for consistency with any parkway landscaping plan which may be
required by the Engineering Division.
13. Special landscape features such as mounding,alluvial rock,specimen size trees,meander- —/---/-
ing sidewalks (with horizontal change), and intensified landscaping, is required along
14. Landscaping and irrigation systems required to be installed within the public right-of-way on /
the perimeter of this project area shall be continuously maintained by the developer.
✓ 15.All walls shall be provided with decorative treatment.If located in public maintenance areas, /-
the design shall be coordinated with the Engineering Division.
•✓ 16.Tree maintenance criteria shall be developed and submitted for City Planner review and
approval prior to issuance of building permits. These criteria shall encourage the natural
growth characteristics of the selected tree species.
17. Landscaping and irrigation shall be designed to conserve water through the principles of ��-
Xeriscape as defined in Chapter 19.16 of the Rancho Cucamonga Municipal Code.
SC - 12/93 5 of 12
Protect Au g
Comn
F. Signs
✓ 1. The signs indicated on the submitted plans are conceptual only and not a part of this approval. ��-
Any signs proposed for this development shall comply with the Sign Ordinance and shall
require separate application and approval by the Planning Division prior to installation of any
signs.
2. A Uniform Sign Program for this development shall be submitted for City Planner review and
approval prior to issuance of building permits.
3. Directory monument sign(s) shall be provided for apartment, condominium, or townhomes
prior to occupancy and shall require separate application and approval by the Planning
Division prior to issuance of building permits.
G. Environmental
1. The developer shall provide each prospective buyer written notice of the Fourth Street Rock / /-
Crusher project in a standard format as determined by the City Planner,prior to accepting a
cash deposit on any property.
2. The developer shall provide each prospective buyer written notice of the City Adopted —'—'-
Special Studies Zone for the Red Hill Fault, in a standard format as determined by the City
Planner, prior to accepting a cash deposit on any property.
3. The developer shall provide each prospective buyer written notice of the Foothill Freeway ��-
project in a standard format as determined by the City Planner, prior to accepting a cash
deposit on any property.
4. A final acoustical report shall be submitted for City Planner review and approval prior to the / /-
issuance of building permits. The final report shall discuss the level of interior noise
attenuation to below 45 CNEL,the building materials and construction techniques provided,
and if appropriate,verify the adequacy of the mitigation measures.The building plans will be
checked for conformance with the mitigation measures contained in the final report.
H. Other Agencies
✓ 1. Emergency secondary access shall be provided in accordance with Rancho Cucamonga Fire ��-
Protection District Standards.
2. Emergency access shall be provided,maintenance free and clear,a minimum of 26 feet wide —/�-
at all times during construction in accordance with Rancho Cucamonga Fire Protection
District requirements.
✓ 3. Prior to issuance of building permits for combustible construction, evidence shall be
submitted to the Rancho Cucamonga Fire Protection District that temporary water supply for
fire protection is available, pending completion of required tire protection system.
4. The applicant shall contact the U. S. Postal Service to determine the appropriate type and .J_/
location of mail boxes. Multi-family residential developments shall provide a solid overhead
structure for mail boxes with adequate lighting. The final location of the mail boxes and the
design of the overhead structure shall be subject to City Planner review and approval prior
to the issuance of building permits.
5. For projects using septic tank facilities, written certification of acceptability, including all i—J-
supportive information, shall be obtained from the San Bernardino County Department of
Environmental Health and submitted to the Building Official prior to the issuance of Septic
Tank Permits, and prior to issuance of building permits.
SC - 12/93 6 of 12
•
Protect\bTJ+
Completion Date.
APPLICANTS SHALL CONTACT THE BUILDING AND SAFETY DIVISION, (909) 989-1863, FOR
COMPLIANCE WITH THE FOLLOWING CONDITIONS:
I. She Development
1. The applicant shall comply with the latest adopted Uniform Building Code,Uniform Mechani-
cal Code, Uniform Plumbing Code, National Electric Code, and all other applicable codes,
ordinances, and regulations in effect at the time of issuance of relative permits. Please
contact the Building and Safety Division for copies of the Code Adoption Ordinance and
applicable handouts.
2. Prior to issuance of building permits for a new residential dwelling unit(s) or major addition ��-
to existing unit(s),the applicant shall pay developmentfees at the established rate. Such fees
may include,but are not limited to:City Beautification Fee,Park Fee, Drainage Fee,Systems
Development Fee, Permit and Plan Checking Fees, and School Fees.
✓ 3. Prior to issuance of building permits for a new commercial or industrial development or ��-
addition to an existing development, the applicant shall pay development fees at the
established rate. Such fees may include, but are not limited to:Systems Development Fee,
Drainage Fee, School Fees, Permit and Plan Checking Fees.
✓ 4. Street addresses shall be provided by the Building Official,aftertract/parcel map recordation _1_1_
and prior to issuance of building permits.
J. Existing Structures
1. Provide compliance with the Uniform Building Code for the property line clearances _/ /-
considering use, area, and fire-resistiveness of existing buildings.
2. Existing buildings shall be made to comply with correct building and zoning regulations for —I—J-
the intended use or the building shall be demolished.
3. Existing sewage disposal facilities shall be removed,filled and/or capped to comply with the
Uniform Plumbing Code and Uniform Building Code.
✓ 4. Underground on-site utilities are to be located and shown on building plans submitted for
building permit permit application.
K. Grading
1. Grading of the subject property shall be in accordance with the Uniform Building Code, City
Grading Standards,Standards, and accepted grading practices. The final grading plan shall be in
substantial conformance with the approved grading plan.
2. A soils report shall be prepared by a qualified engineer licensed by the State of California to ��-
perform such work.
3. The development is located within the soil erosion control boundaries; a Soil Disturbance
Permit is required.Please contact San Bernardino County Department of Agriculture at(714)
387-2111 for permit application.Documentation of such permit shall be submitted to the City
prior to the issuance of rough grading permit.
4. A geological report shall be prepared by a qualified engineer or geologist and submitted at �—�-
the time of application for grading plan check.
✓ 5. The final grading plans shall be completed and approved prior to issuance of building permits. —J�—
SC - 12/93 7 01 12
Pro,ect'o • 6
Completion D:atc:
6. As a custom-lot subdivision, the following requirements shall be met:
a. Surety shall be posted and an agreement executed guaranteeing completion of all on-site
drainage facilities necessary for dewatering all parcels to the satisfaction of the Building
and Safety Division prior to final map approval and prior to the issuance of grading permits.
b. Appropriate easements for safe disposal of drainage water that are conducted onto
or over adjacent parcels, are to be delineated and recorded to the satisfaction of the
Building and Safety Division prior to issuance of grading and building permits.
c.On-site drainage improvements, necessary for dewatering and protecting the subdivided
properties, are to be installed prior to issuance of building permits for construction upon
any parcel that may be subject to drainage flows entering, leaving, or within a parcel
relative to which a building permit is requested.
d. Final grading plans for each parcel are to be submitted to the Building and Safety —
Division for approval prior to issuance of building and grading permits. (This may be on an
incremental or composite basis.)
e. All slope banks in excess of 5 feet in vertical height shall be seeded with native grasses or planted planted with ground cover for erosion control upon completion of grading or some other
alternative method of erosion control shall be completed to the satisfaction of the Building
Official. In addition a permanent irrigation system shall be provided. This requirement
does not release the applicant/developer from compliance with the slope planting
requirements of Section 17.08.040 I of the Development Code.
APPLICANT SHALL CONTACT THE ENGINEERING DIVISION, (909)989-1862,FOR COMPLIANCE
WITH THE FOLLOWING CONDITIONS:
L. Dedication and Vehicular Access
1. Rights-of-way and easements shall be dedicated to the City for all interior public streets,
community trails, public paseos, public landscape areas, street trees, and public drainage
facilities as shown on the plans and/or tentative map. Private easements for non-public
facilities(cross-lot drainage, local feeder trails,etc.) shall be reserved as shown on the plans
and/or tentative map.
2. Dedication shall be made of the following rights-of-way on the perimeter streets ��-
(measured from street centerline):
See /4l
L$t_ _ total feet on , M%ll ,�/✓o
total feet on
total feet on
•
total feet on
' 3. An irrevocable offer of dedication for -foot wide roadway easement shall be made ��-
for all private streets or drives.
4. Non-vehicular access shall be dedicated to the City for the following streets:
•
17 5. Reciprocal access easements shall be provided ensuring access to all parcels by CC&Rs ��-
or by deeds and shall be recorded concurrently with the map or prior to the issuance of
building permits, where no map is involved.
SC - 12/93 8 or 12
Precct\ • 4
Completion
6. Private drainage easements for cross-lot drainage shall be provided and shall be delineated
or noted on the final map. ��-
7. The final map shall clearly delineate a 10-foot minimum building restriction area on the
neighboring lot adjoining the zero lot line wall and contain the following language:
"I//We hereby dedicate to the City of Rancho Cucamonga the right to prohibit the
construction of(residential) buildings (or other structures) within those areas designated
on the map as building restriction areas."
A maintenance agreement shall also be granted from each lot to the adjacent lot through the
CC&R's.
8. All existing easements lying within future rights-of-way shall be quitclaimed or delineated on —/�-
the final map.
9. Easements for public sidewalks and/or street trees placed outside the public right-of-way
shall be dedicated to the City wherever they encroach onto private property.
10.Additional street right-of-way shall be dedicated along right turn lanes,to provide a minimum Jam_
of 7 feet measured from the face of curbs. If curb adjacent sidewalk is used along the right
turn lane, a parallel street tree maintenance easement shall be provided.
11.The developer shall make a good faith effort to acquire the required off-site property interests
necessary to to construct the required public improvements,and it he/she should fail to do so,
the developer shall, at least 120 days prior to submittal of the final map for approval, enter
into an agreement to complete the improvements pursuant to Government Code Section
66462 at such time as the City acquires the property interests required for the improvements.
Such agreement shall provide for payment by the developer of all costs incurred by the City
to acquire the off-site property interests required in connection with the subdivision.Security
for a portion of these costs shall be in the form of a cash deposit in the amount given in an
appraisal report obtained by the developer, at developer's cost. The appraiser shall have
been approved by the City prior to commencement of the appraisal.
M. Street Improvements
1/ 1. All public improvements (interior streets, drainage facilities, community trails, paseos,
landscaped areas, etc.) shown on the plans and/or tentative map shall be constructed to
City Standards. Interior street improvements shall include, but are not limited to, curb and
gutter, AC pavement, drive approaches, sidewalks, street lights, and street trees.
2. A minimum of 26-foot wide pavement,within a 40 -foot wide dedicated right-of-way shall be / /_
constructed for all half-section streets.
3. Construct the following perimeter street improvements including, but not limited to: /
STREET NAME CURB 8 A.C. SIDE- DRIVE STREET STREET COMM MEDIAN BIKE OTHER
GUTTER PVMT WALK APPR. LIGHTS TREES TRAIL ISLAND TRAIL
- %w'ss ts ✓ ✓ ✓ ✓ ✓ (d) as)
Wo d ✓ ✓ ✓ ✓ ✓ ✓ (e)
SC - 12/93 9 of 12
Protect Ao 95—.,e
Completion Date:
Notes: (a) Median island includes landscaping and irrigation on meter. (b) Pavement
reconstruction and overlays will be determined during plan check. (c) If so marked,side-
walk shall be curvilinear pe TD.304. (d) If so marked, an in-lieu of construction fee shall
be provided for this item 9 l .-•/ -
4 / .i V .. -ri• p
di. )! - a . . A .2_ �L-�1�3�•m'
"Se as rived ed / A#G h/r. Ely)*err.
✓ 4. Improvement plans and construction:
a. Street improvement plans including street trees and street lights, prepared by a regis- —J---/
tered Civil Engineer, shall be submitted to and approved by the City Engineer. Security
shall be posted and an agreement executed to the satisfaction of the City Engineer and
the City Attorney guaranteeing completion of the public and/or private street improve-
ments, prior to final map approval or the issuance of building permits,whichever occurs
first.
b. Prior to any work being performed in public right-of-way, fees shall be paid and a —�—�-
construction permit shall be obtained from the City Engineer's Office in addition to any
other permits required.
c. Pavement striping, marking, traffic, street name signing, and interconnect conduit
shall be installed to the satisfaction of the City Engineer.
d. Signal conduit with pull boxes shall be installed on any new construction or reconstruction ��-
of major, secondary or collector streets which intersect with other major,secondary or
collector streets for future traffic signals. Pull boxes shall be placed on both sides of the _
street at 3 feet outside of BCR, ECR or any other locations approved by the City Engineer.
Notes: _J-J-
(1) All pull boxes shall be No. 6 unless otherwise specified by the City Engineer.
(2) Conduit shall be 3-inch galvanized steel with pullrope.
e. Wheel chair ramps shall be installed on all four corners of intersections per City ��-
Standards or as directed by the City Engineer.
f. Existing City roads requiring construction shall remain open to traffic at all times with
adequate detours during construction. A street closure permit may be required. A cash
deposit shall be provided to cover the cost of grading and paving, which shall be
refunded upon completion of the construction to the satisfaction of the City Engineer.
g. Concentrated drainage flows shall not cross sidewalks. Under sidewalk drains shall be 1_/
installed to City Standards, except for single family lots.
h. Handicap access ramp design shall be as specified by the City Engineer. ��-
i. Street names shall be approved by the City Planner prior to submittal for first plan check. _I_J
5. Street improvement plans per City Standards for all private streets shall be provided for ��-
review and approval by the City Engineer. Prior to any work being performed on the pri-
vate streets, fees shall be paid and construction permits shall be obtained from the City
Engineer's Office in addition to any other permits required.
6. Street trees, a minimum of 15-gallon size or larger, shall be installed per City Standards in ��-
accordance with the City's street tree program.
SC - 12/93 10 of 12
Protect No eltp ,J-erj
Completion Date:
7. Intersection line of site designs shall be reviewed by the City Engineer for conformance with
adopted policy.
a. On collector or larger streets, lines of sight shall be plotted for all project intersections,
including driveways. Walls, signs, and slopes shall be located outside the lines of sight.
Landscaping and other obstructions within the lines of sight shall be approved by the City
Engineer.
b. Local residential street intersections shall have their noticeability improved, usually by /-
moving the 2+/-closest street trees on each side away from the street and placed in a street
tree easement.
8. A permit shall be obtained from CALTRANS for any work within the following right-of-way: —1�-
fitylk// S e./nerj
9. All public improvements on the following streets shall be operationally complete prior to the ��-
issuance of building permits:
N. Public Maintenance Areas
1. A separate set of landscape and irrigation plans per Engineering Public Works Standards ��-
shall be submitted to the City Engineer for review and approval prior to final map approval
or issuance of building permits, whichever occurs first. The following landscape parkways,
medians, paseos, easements, trails, or other areas are required to be annexed into the
Landscape Maintenance District:
2. A signed consent and waiver form to join and/or form the appropriate Landscape and Lighting ��-
Districts shall be filed with the City Engineer prior to final map approval or issuance of building
permits whichever occurs first. Formation costs shall be borne by the developer.
3. All required public landscaping and irrigation systems shall be continuously maintained by the
developer until accepted by the City.
4. Parkway landscaping on the following street(s) shall conform to the results of the respective �—�-
Beautification Master Plan:
O. Drainage and Flood Control
1. The project (or portions thereof) is located within a Flood Hazard Zone:therefore, flood —��-
protection measures shall be provided as certified by a registered Civil Engineer and
approved by the City Engineer.
2. It shall be the developer's responsibility to have the current FIRM Zone �-J-
designation removed from the project area. The developer's engineer shall prepare all
necessary reports, plans, and hydrologic/hydraulic calculations. A Conditional Letter
of Map Revision (CLOMR) shall be obtained from FEMA prior to final map approval or
issuance of building permits,whichever occurs first. A Letter of Map Revision (LOMB) shall
be issued by FEMA prior to occupancy or improvement acceptance,whichever occurs first.
3. A final drainage study shall be submitted to and approved by the City Engineer prior to final J�-
map approval or the issuance of building permits, whichever occurs first. All drainage
facilities shall be installed as required by the City Engineer.
SC - 12/93 I I of 12
Protect N 1en'ael
Complcuun Due:
4. A permit from the County Flood Control District is required for work within its right-of-way.
5. Trees are prohibited within 5 feet of the outside diameter of any public storm drain pipe
measured from the outer edge of a mature tree trunk. _1—/
6. Public storm drain easements shall be graded to convey overflows in the event of a _J_1_
blockage in a sump catch basin on the public street.
P. Utilities
1.Provide separate utility services to each parcel including sanitary sewerage system, water, _ill—
gas, electric power,telephone,and cable TV(all underground) in accordance with the Utility
Standards. Easements shall be provided as required.
2.The developer shall be responsible for the relocation of existing utilities as necessary.
V 3.Water and sewer plans shall be designed and constructed to meet the requirements of the J�-
Cucamonga County Water District (CCWD), Rancho Cucamonga Fire Protection District,
and the Environmental Health Department of the County of San Bernardino. A letter of
compliance from the CCWD is required prior to final map approval or issuance of permits,
whichever occurs first.
0. General Requirements and Approvals
1.The separate parcels contained within the project boundaries shall be legally combined into ��-
one parcel prior to issuance of building permits.
2. An easement for a joint use driveway shall be provided prior to final map approval or J—J-
issuance of building permits, whichever occurs first, for:
_J_1-
3.Prior to approval of the final map a deposit shall be posted with the City covering the
estimated cost of apportioning the assessments under Assessment District
among the newly created parcels.
4. Etiwanda/San Sevaine Area Regional Mainline, Secondary Regional, and Master Plan
Drainage Fees shall be paid prior to final map approval or prior to building permit issuance if
no map is involved.
5. Permits shall be obtained from the following agencies for work within their right-of-way:
6.A signed consent and waiver form to join and/or form the Law Enforcement Community -J�-
Facilities District shall be filed with the City Engineer prior to final map approval or the
issuance of building permits, whichever occurs first. Formation costs shall be borne by the
Developer.
7. Prior to finalization of any development phase, sufficient improvement plans shall be com-
pleted beyond the phase boundaries to assure secondary access and drainage protection to
the satisfaction of the City Engineer. Phase boundaries shall correspond to lot lines shown
on the approved tentative map.
SC - 12/93 12 0112