HomeMy WebLinkAbout20-01 Resolution RESOLUTION NO.20-01
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
RANCHO CUCAMONGA, CALIFORNIA, APPROVING DESIGN REVIEW
DRC2018-00430, A REQUEST FOR SITE PLAN AND ARCHITECTURAL
REVIEW OF A PROPOSED 25,399 SQUARE FOOT INDUSTRIAL
WAREHOUSE BUILDING ON A VACANT SITE TOTALING 1.87 ACRES OF
LAND, LOCATED IN THE GENERAL INDUSTRIAL (GI) DISTRICT, EAST
OF VINEYARD AVENUE AND NORTH OF 8T" STREET, AND MAKING
FINDINGS IN SUPPORT THEREOF -APN: 0209-013-13, -43, -44.
A. Recitals.
1. RC Store Maintenance filed an application for the approval of Design Review DRC2018-
00430 as described in the title of this Resolution. Hereinafter in this Resolution,the subject Design
Review is referred to as "the application."
2. On the 81h day of January 2020, the Planning Commission of the City of Rancho
Cucamonga conducted a duly noticed public hearing on the application at which time the Planning
Commission voted to continue the item to January 22, 2020.
3. All legal prerequisites prior to the adoption of this Resolution have occurred.
B. Resolution.
NOW, THEREFORE, it is hereby found, determined, and resolved by the Planning
Commission of the City of Rancho Cucamonga as follows:
1. This Commission hereby specifically finds that all the facts set forth in the Recitals, Part
A, of this Resolution are true and correct.
2. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing on January 22,2020 including written and oral staff reports,togetherwith
public testimony, this Commission hereby specifically finds as follows:
a. The application applies to property located within the City; and
b. The application applies to a vacant project site located east of Vineyard Avenue
and north of 8t' Street. The General Plan Land Use designation of the project site is General
Industrial. The Development Code zoning designation of the project site is General Industrial (GI)
District; and
C. The project site is bounded to the north and east by the Cucamonga Creek
drainage channel, Vineyard Avenue to the west, and the San Bernardino County Transportation
Authority rail line along the south property line. The site is generally flat and at-grade with Vineyard
Avenue.A slight north to south downward slope exists on the property,with an overall grade change
of roughly 7 feet; and
d. The site is surrounded by industrial warehousing facilities to the north, east and
west of the project site. The site to the south of the project site is currently vacant but is also in the
General Industrial (GI) District.
PLANNING COMMISSION RESOLUTION NO. 20-01
DESIGN REVIEW DRC2018-00430— RC Store Maintenance
January 22, 2020
Page 2
e. The applicant, RC Store Maintenance, is proposing to construct a 25,399 square-
foot industrial warehousing building on the project site.The building consists of 15,430 square feet
of warehousing space and 9,969 square feet of office space.Two access points will be provided to
the property, at the northwest and southwest corner of the project site along Vineyard Avenue. A
single driveway will connect both egress points to provide circulation through the site and access to
the parking lot and two loading docks; and
f. Parking, truck storage and walkway areas line the side of the driveway and wrap
around the north, east and south sides of the building. A total of 47 parking spaces are provided to
meet the minimum parking requirements. The project also includes two truck-well areas near the
loading docks for large truck/trailer parking; and
g. Overall, the project site complies with the applicable Development Standards for
the General Industrial (GI) District. The proposed warehouse building maintains a 35 foot setback
from Vineyard Avenue, 51 foot and 58 foot interior side yard setback, and an 83 foot rear yard
setback. The maximum height of the proposed warehouse facility is 37 feet. Highest point of the
facility is located two (2) feet behind the front setback line. The building conforms with the height
limit of the General Industrial (GI) District,which permits a maximum height of 37 feet when located
37 feet back from the setback line; and
h. The proposed industrial building meets the City's 360-degree design standards.
Architectural articulation and material breaks are used throughout the facade to break up the
building's massing.The front elevation of the building,facing the Vineyard Avenue,consists of large
expanses of glass windows and doorways.The use of metal accents and metal canopies along the
glass facade also distinguishes the glass elements from the concrete walls. The result is an
industrial building with extensive architectural articulation and material breaks that closely mimics
the look of an office building. Glass and metal accents are used extensively throughout the other
elevations of the building, creating visual interest and reducing the amount of blank walls. The
building also incorporates painted and sandblasted concrete,which helps break up the uniform look
of tilt-up concrete walls; and
i. The project also complies with the City's landscape standards. Site landscape
coverage exceeds the minimum requirement of 10%and includes an overall depth of 35 feet along
Vineyard Avenue. The landscaping palette includes a variety of trees, shrubs, and ground cover to
help screen mechanical equipment and enhance the appearance of the building. The project will
also incorporate a 537 square foot employee break area as required by the Development Code for
new industrial buildings.
3. Based upon the substantial evidence presented to this Commission during the above-
referenced public hearing and upon the specific findings of facts set forth in paragraphs 1 and 2
above, this Commission hereby finds and concludes as follows:
a. The proposed project is consistent with the objectives of the General Plan.The site
is located within land designated as General Industrial.The General Industrial designation permits a
wide range of industrial activities that include warehousing and office uses.The project consists of a
25,399 square foot industrial building, including 9,969 square foot dedicated to office space,on 1.87
acre of land. The warehouse building is designed for wholesale warehousing with ancillary office
uses.All site improvements, including parking and landscaped areas,are designed to be consistent
PLANNING COMMISSION RESOLUTION NO. 20-01
DESIGN REVIEW DRC2018-00430— RC Store Maintenance
January 22, 2020
Page 3
with the warehousing use and are consistent with the General Industrial land use as designated in
the General Plan.
b. The proposed use is in accord with the objectives of the Development Code
and the purposes of the district in which the site is located. The Development Code designates the
project site as a General Industrial(GI) District. The potential industrial and warehousing land uses
that would be associated with this project are consistent with the General Industrial(GI)District.The
project site is adjacent to other sites in the General Industrial (GI) District, including an industrial
warehouse building of similar size and scale to the north, west and east of the project site. The
project site has a Floor Area Ratio(FAR)of 0.50 and within the 0.50 to 0.60 FAR range permitted in
the General Industrial (GI) District.
C. The proposed use is in compliance with each of the applicable provisions of
the Development Code. The facility is designed for industrial warehouse operations with ancillary
office space to support the main warehousing use. The facility meets all setbacks, floor area and
height requirements. The facility has also been designed to meet the City's architectural standards.
The facility will also comply with all parking, access and landscaping requirements. Therefore, the
project meets all applicable provisions of the Development Code.
d. The proposed project,together with the conditions applicable thereto,will not
be detrimental to the public health, safety or welfare, or materially injurious to properties or
improvements in the vicinity. The surrounding neighborhood consists of warehousing facilities and
vacant lots zoned for industrial facilities in the General Industrial (GI) District. The proposed project
is a 25,399 square foot industrial warehouse building similar in size and scale to the other
warehousing facilities nearby. The construction and operations of the facility are expected to meet
all Development Code standards regarding noise and odor.The project is therefore not expected to
generate public health, safety or welfare impacts or be detrimental to improvements in the vicinity.
4. Pursuant to the California Environmental Quality Act(CEQA) and the City's local
CEQA Guidelines, the Planning Commission has determined that the project is exempt from the
requirements of the California Environmental Quality Act(CEQA) and the City's CEQA Guidelines.
The project qualifies as a Class 32 exemption under State CEQA Guidelines Section 15332—In-Fill
Development Projects, as the project is a proposed development occurring within city limits on a
project site less than five acres in size and substantially surrounded by urban uses.The project is a
25,399 square foot warehouse building located on 1.87 acres of land within the General Industrial
(GI) District. The warehouse use is consistent with the intent of the General Industrial (GI)
designation in the General Plan and project meets all applicable development standards and zoning
regulations of the Development Code. The warehouse building is similar in scale and is consistent
with industrial buildings in the nearby vicinity. The site can be adequately served all required utilities
and police and fire services.
To demonstrate that the project qualified for the exemption, specific environmental studies were
prepared to assess any potential impacts that the project might have on the environment.As a result
of these studies, staff finds that there is no substantial evidence that the project will have a
significant effect on the environment. The studies prepared analyzed the following topics:
• Phase 1 CEQA Survey (The Planning Associates Group, Inc., August 2018) — The
Survey determined that the project site's habitat consisted of non-native plant species.
The Survey also determined that there were no riparian or wetland habitats that would
PLANNING COMMISSION RESOLUTION NO. 20-01
DESIGN REVIEW DRC2018-00430— RC Store Maintenance
January 22, 2020
Page 4
support sensitive,threatened or endangered species. Lastly,the Survey concluded that
vegetation on the project site does not provide suitable nesting sites for common or
special avian species, such as raptors.
• Air Quality Impact Analysis(Urban Crossroads, September 2018)and Greenhouse Gas
Analysis (Urban Crossroads, September 2018) — Both analyses determined that the
project would not exceed the applicable Southern California Air Quality Management
District's threshold for air quality and greenhouse gas emissions, respectively, during
construction or operational activity.
• Noise Impact Analysis(Urban Crossroads, September 2018)—The Analysis concluded
that the project's noise contribution to adjacent roadways would be less than significant
and that the on-site construction and operation noises levels will be less than the City's
80 dBA maximum noise level standards for industrial use and less than 65 dBA at
nearby residential homes in the City of Ontario.
• Conceptual Water Quality Management Plan (WQMP) (Sake Engineers, Inc., October
2018) --The WQMP was submitted and reviewed by the City's grading engineer. The
City's grading engineer approved the conceptual design and will review the final design
when grading plans are submitted.
• Traffic - The City's traffic engineer also reviewed the proposed development and
concluded that there are no apparent traffic safety or operational concerns with
implementation of the project. Based on the Institute of Transportation Engineers' Trip
Generation Manual,the project is only expected to generate 35 passenger car equivalent
(PCE)daily trips, including 3 PCE trips during the AM peak hour and 4 PCE trips during
the PM peak hour. The City's traffic engineer determined that the PCE trip levels did not
require additional traffic studies to be submitted.
5. Based upon the findings and conclusions set forth Paragraphs 1,2,3 and 4 above,
this Commission hereby approves the applications subject to each and every condition in the
attached Standard Conditions incorporated herein by this reference.
6. The Secretary to this Commission shall certify to the adoption of this Resolution.
APPROVED AND ADOPTED THIS 22"d DAY OF JANUARY 2020.
PLANNING COMMI N OF THE CITY OF RANCHO CUCAMONGA
BY:
Tony glielmo, Chairman
ATTEST:
Anne McIntosh, AICP Secretary
PLANNING COMMISSION RESOLUTION NO. 20-01
DESIGN REVIEW DRC2018-00430--- RC Store Maintenance
January 22, 2020
Page 5
I,Anne Mclntosh,AICP, Secretary of the Planning Commission of the City of Rancho Cucamonga,
do hereby certify that the foregoing Resolution was duly and regularly introduced,_passed,.and
adopted,by the Planning Commission of the City of Rancho Cucamonga, at a regular meeting of the
Planning Commission held on the 22"d day of January 2020, by the following vote-to-wit:
AYES: COMMISSIONERS: GUGLIELMO, OAXACA, DOPP, MORALES, WILLIAMS
NOES: COMMISSIONERS:
ABSENT: COMMISSIONERS:
ABSTAIN: COMMISSIONERS:
Conditions of Approval
CAAhi0iY0A NCNO Community Development Department
UC
Project M DRC2018-00430
Project Name: EDR- DR///Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT:
Planning Department
Please be advised of the following Special Conditions
1. All Double Detector Checks (DDC) and Fire Department Connections (FDC) required and/or
proposed shall be installed at locations that are not within direct view or line-of-sight of the main
entrance. The specific locations of each DDC and FDC shall require the review and approval of the
Planning Department and Fire Construction ServiceslFire Department. All Double Detector Checks
(DDC) and Fire Department Connections (FDC) shall be screened behind a 4-foot high block wall.
These walls shall be constructed of similar material used on-site to match the building.
2. All ground-mounted equipment, including utility boxes, transformers, and back-flow devices, shall be
surrounded by a minimum of two rows of shrubs spaced a minimum of 18 inches on-center. All
ground-mounted equipment shall be painted dark green except as directed otherwise by the Fire
Department.
3. The employee break area shall have an overhead trellis with cross members spaced no more than
18 inches on center with minimum dimensions of 4 inches by 12 inches. Each support column shall
have a decorative base that incorporates the architectural design and finishes/trim used on the
building. The trellis shall be painted to match the building. Tables, chairs/benches, and waste
receptacles shall be provided.
4. All wrought iron fences and sliding gates shall be painted black or similarly dark color.
5. All walls, including retaining walls, exposed to public view shall be constructed of decorative
masonry blocks, i.e., slump stone, split-face, or have a decorative finish such as stucco texture to
match a concrete tilt up wall.
fi. All dock doors shall be painted to match the main color of the building.
7. All downspouts shall be routed through the interior of the building.
8. The applicant shall sign the Statement of Agreement and Acceptance of Conditions of Approval
provided by the Planning Department. The signed Statement of Agreement and Acceptance of
Conditions of Approval shall be returned to the Planning Department prior to the submittal of
grading/construction plans for plan check, request for a business license, and/or commencement of
the approved activity.
Standard Conditions of Approval
Printed 1IM020 www.Cityu(Mus
Project#: DRC2018-00430
Project Name: EDR-DR N Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT:
Planning Department
Standard Conditions of Approval
9. The applicant shall agree to defend at his sole expense any action brought against the City, its
agents, officers, or employees, because of the issuance of such approval, or in the alternative, to
relinquish such approval. The applicant shall reimburse the City, its agents, officers, or employees,
for any Court costs and attorney's fees which the City, its agents, officers, or employees may be
required by a court to pay as a result of such action. The City may, at its sole discretion, participate
at its own expense in the defense of any such action but such participation shall not relieve
applicant of his obligations under this condition.
10. Copies of the signed Planning Commission Resolution of Approval, Conditions of Approval, and all
environmental mitigations shall be included on the plans (full size). The sheet(s) are for information
only to all parties involved in the construction/grading activities and are not required to be wet
sealed/stamped by a licensed Engineer/Architect.
11. The applicant shall be required to pay California Department of Fish and Wildlife Notice of
Exemption fee in the amount of $50.00. All checks are to be made payable to the Clerk of the
Board Supervisors and submitted to the Planning Commission Secretary prior to public hearing or
within 5 days of the date of project approval.
12. Any approval shall expire if Building Permits are not issued or approved use has not commenced
within 5 years from the date of approval or a time extension has been granted.
13.Approval of this request shall not waive compliance with all sections of the Development Code, all
other applicable City Ordinances, and applicable Community, Specific Plans and/or Master Plans in
effect at the time of Building Permit issuance.
14. The site shall be developed and maintained in accordance with the approved plans which include
Site Plans, architectural elevations, exterior materials and colors, landscaping, sign program, and
grading on file in the Planning Department, the conditions contained herein, and the Development
Code regulations.
15. This project is subject to the public art requirement outlined in Chapter 17.124 of the Development
Code. No final approval, such as a final inspection or a certificate of occupancy, for any
development project subject to this chapter shall be granted or issued unless and until the
requirements of this chapter have been met. In consideration of any phasing plan or project
completion schedule, the city may accept bonds or other surety to assist in the completion of the
project, provided they are in a form and manner acceptable to the planning director and city
attorney.
Engineering Services Department
Please be advised of the following Special Conditions
www.CityofRC.us
Printed,112212020 Page 2 of 12
Project#: DRC2018-00430
Project Name: EDR-DR/1/Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT:
Enalineerinai Services Department
Please be advised of the following Special Conditions
1. It shall be the developers responsibility to have the current FIRM Zone designation removed from
the project area. The developer shall provide drainage and/or flood protection facilities sufficient to
obtain a Zone "K' designation. The developer's engineer shall prepare all necessary reports, plans,
and hydrologiclhydraulic calculations. A Conditional Letter of Map Revision (CLOMR) shall be
obtained from FEMA prior to issuance of Building Permits. A Letter of Map Revision (1_OMR) shall
be issued by FEMA prior to occupancy or improvement acceptance, whichever occurs first. If the
developer chooses not to obtain a CLOMRILOMR from FEMA, it shall be the developers
responsibility to comply with section 19.12.050 of the City's Municipal Code and provide all
necessary reports, plans, and hydrologic/hydraulic calculations for the base flood elevation to the
satisfaction of the City Engineer prior to issuance of a building permit. Also, if the developer chooses
not to obtain a CLOMR from FEMA, prior to issuance of a building permit, the developer shall
provide written confirmation that they acknowledge that their property may be subject to flood
insurance requirements.
2. ,
horri the centerline of Vineyeid la the Flued eontml eiiiannei, to the satisfaction of the eity
-Engineer. A 25' publie elfainage easement will be required and a temperefy adiseent 25' tempemfy
eenstfuefien easement). Standeft! df-ainege fees for I.I.— site alial! be eFedited to the east of
with the samie tAbUtffy ffea. If the develepep falls te submit feF said reimbuFaeffieRt B@Feef:ReRt
prgpedy-lines
3. The existing overhead utilities (telecommunications and electrical, except for 66 kV electrical) on the
project side of Vineyard Avenue shall be undergrounded from the first pole offsite on the south side
of the project boundary and to the first pole offsite on the north side of the project boundary, prior to
public improvement acceptance or occupancy, whichever occurs first. All services crossing Vineyard
shall be undergrounded at the same time. The developer may request a reimbursement agreement
to recover one-half the City adopted cost for undergrounding from future development as it occurs
on the opposite side of the street. If the developer fails to submit for said reimbursement agreement
within 6 months of the public improvements being accepted by the City, all rights of the developer to
reimbursement shall terminate.
www.CityofRc.us
Printed 1122/2fl20 Page 3 of 12
Project M DRC2018-00430
Project Name: EDR-DR 111 Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Engineering Services Department
Please be advised of the following Special Conditions
4. An in-lieu fee as contribution to the future undergrounding of the existing overhead utilities, on the
opposite side of Vineyard Avenue shall be paid to the City prior to the issuance of building permits.
The fee shall be one half the City adopted unit amount times the length of the line to the north
property boundary.
5. Public improvement plans shall be 90 percent complete prior to the issuance of grading permits.
Public improvement plans shall be 100 percent complete, signed by the City Engineer, and an
improvement agreement and bonds executed by the developer, prior to building permit issuance.
Standard Conditions of Approval
6. Vineyard Avenue right-of-way shall be either dedicated or vacated on the perimeter streets
(measured from street centerline)to meet the City requirements for a Secondary Street:
44'total feet on Vineyard Avenue.
Show both the monument centerline and the construction centerline on the plans.
7. A final drainage study shall be submitted to and approved by the City Engineer prior to final map
approval or the issuance of Building Permits, whichever occurs first. All drainage facilities shall be
installed as required by the City Engineer. The drainage study shall take into account proposed
(interim) and future (post master plan storm drain installation) hydrologic conditions of the site.
8. An encroachment permit from the San Bernardino County Flood Control District is required for work
within its right-of-way and must be obtained prior to grading permit issuance. The encroachment
permit must be finalized prior to occupancy.
9. The separate parcels contained within the project boundaries shall be legally combined into one
parcel prior to issuance of Building Permits.
10. ** CD Information Required Prior to Sign-Off for Building Permit
Prior to the issuance of building permits, if valuation is greater or equal to $100,000, a Diversion
Deposit and a related administrative fee shall be paid for the Construction and Demolition Diversion
Program. The deposit is fully refundable if at least 65% of all wastes generated during construction
and demolition are diverted from landfills, and appropriate documentation is provided to the City.
Applicant must identify if they are self-hauling or utilizing Burrtec prior to issuance of a building
permit. Proof of diversion must be submitted to the Environmental Engineering Division within 60
days following the completion of the construction and 1 or demolition project.
Contact Marissa Ostos, Environmental Engineering, at(909)7744062 for more information.
Instructions and forms are available at the City's website, www.cltyofrc.us, under City Hall 1
Engineering 1 Environmental Programs 1 Construction & Demolition Diversion Program.
11. Prior to approval of the final map, a deposit shall be posted with the City covering the estimated cost
of apportioning the assessments under Assessment District LMD 3B, SLD 1, and SLID 6, among
the parcel(s).
+w.C1tyofRC.us
Printed:112212020 page 4 of 12
Project#: DRC2018-00430
Project Name. EDR-DR 111 Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Engineering Services Department
Standard Conditions of Approval
12. A signed consent and waiver form to join and/or form the appropriate Landscape and Lighting
Districts shall be filed with the Engineering Services Department prior to final map approval or
issuance of Building Permits whichever occurs first. Formation costs shall be borne by the
developer.
13. Add the following note to any private landscape plans that show street trees: "All improvements
within the public right-of-way, including street trees, shall be installed per the public improvement
plans." If there is a discrepancy between the public and private plans, the street improvement plans
will govern.
14. Construct the following perimeter street improvements including, but not limited to:
Vineyard Avenue
Curb&Gutter(removal and replacement as required)
A.C. Pavement(removal and replacement or overlay as required by the City Engineer)
Side-walk (removal and replacement as required)
Drive Approach (removal and replacement as required)
Street Lights (if required)
Street Trees
South driveway adjacent to tracks shall be right out, exit only, and restrict any truck access.
15. Pursuant to Municipal Code Section 16.37.010, no person shall make connections from a source of
energy, fuel or power to any building or structure which is regulated by technical codes and for
which a permit is required unless, in addition to any and all other codes, regulations and ordinances,
all improvements required by these conditions of development approval have been completed and
accepted by the City Council, except: that in developments containing more than one building,
structure or unit, the development may have energy connections made in equal proportion to the
percentage of completion of all improvements required by these conditions of development
approval, as determined by the City Engineer, provided that reasonable, safe and maintainable
access to the property exists. In no case shall more than 95 percent of the buildings, structures or
units be connected to energy sources prior to completion and acceptance of all improvements
required by these conditions of development approval.
Printed:1/22/2020 www.C1tyofRC.us
Page 5 a(12
Project M DRC2018-00430
Project Name: EDR-DR 111 Industrial Building
Location: —-020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Engineering Services Department
Standard Conditions of Approval
16. Improvement Plans and Construction:
a. Street improvement plans (including revisions to approved street plans), including street trees,
and street lights shall be prepared by a registered Civil Engineer and shall be submitted to and
approved by the City Engineer. Security shall be posted and an agreement executed to thb
satisfaction of the City Engineer and the City Attorney guaranteeing completion of the public and/or
private street improvements the issuance of Building Permits.
b. Prior to any work being performed in public right-of-way, fees shall be paid and a construction
permit shall be obtained from the Engineering Services Department in addition to any other permits
required.
c. Pavement striping, marking, and traffic signing shall be installed to the satisfaction of the City
Engineer.
d. Signal conduit with pull boxes shall be installed with any new construction or reconstruction
project along major or secondary streets and at intersections for future traffic signals and
interconnect wiring. Pull boxes shall be placed on both sides of the street at 3 feet outside of BCR,
ECR,or any other locations approved by the City Engineer.
Notes:
1) Pull boxes shall be No. 6 at intersections and No. 5 along streets, a maximum of 200 feet apart,
unless otherwise specified by the City Engineer.
2)Conduit shall be 3-inch pvc with pull rope or as specified.
e. Existing City roads requiring construction shall remain open to traffic at all times with adequate
detours during construction. Street or lane closure permits are required. A cash deposit shall be
provided to cover the cost of grading and paving, which shall be refunded upon completion of the
construction to the satisfaction of the City Engineer.
f. Concentrated drainage flows shall not cross sidewalks. Under sidewalk drains shall be installed to
City Standards, except for single-family residential lots.
Printed 1122l2g24 www.CityafRC.us Page 6 of 12
Project##: DRC2018-00430
Project Name: EDR-DR 111 Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT:
Engineering Services Department
Standard Conditions of Approval
17. Install street trees per City street tree design guidelines and standards as follows. The completed
legend (box below) and construction notes shall appear on the title page of the street improvement
plans. Street improvement plans shall include a line item within the construction legend stating:
"Street trees shall be installed per the notes and legend on Sheet _ (typically Sheet 1)." Where
public landscape plans are required, tree installation in those areas shall be per the public
landscape improvement plans.
Vineyard Avenue
Botanical Name-Tristaniopsis Laurina
Common Name-Water Gum
Spacing -26 OC
Size - 15 Gallon Minimum
Construction Notes for Street Trees:
1)All street trees are to be planted in accordance with City standard plans.
2) Prior to the commencement of any planting, an agronomic soils report shall be fumished to the
City inspector. Any unusual toxicities or nutrient deficiencies may require backfill soil amendments,
as determined by the City inspector.
3) All street trees are subject to inspection and acceptance by the Engineering Services
Department.
Street trees are to be planted per public improvement plans only.
18. Intersection line of sight designs shall be reviewed by the City Engineer for conformance with
adopted policy. On collector or larger streets, lines of sight shall be plotted for all project
intersections, including driveways. Local residential street intersections and commercial or industrial
driveways may have lines of sight plotted as required.
19. The developer shall be responsible for the relocation of existing utilities as necessary.
20. Provide separate utility services to each parcel including sanitary sewerage system, water, gas,
electric power, telephone, and cable TV (all underground) in accordance with the Utility Standards.
Easements shall be provided as required.
21.Water and sewer plans shall be designed and constructed to meet the requirements of the
Cucamonga Valley Water District (CVWD), Rancho Cucamonga Fire Protection District, and the
Environmental Health Department of the County of San Bernardino. A letter of compliance from the
CVWD is required prior to final map approval or issuance of permits, whichever occurs first. Such
letter must have been issued by the water district within 90 days prior to final map approval in the
case of subdivision or prior to the issuance of permits in the case of all other residential projects.
Building and Safety Services Department
Please be advised of the following Special Conditions
www.CityofRC.us
Printed:1YZ212D20 Page 7 of 12
Project#: DRC2018-00430
Project Name: EDR-DR N Industrial Building
Location: —-020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Building and Safety Services Department
Please be advised of the following Special Conditions
1. When the Entitlement Review is approved submit complete construction drawings including
structural calculations, energy calculations and soils report to Building and Safety for plan review in
accordance with the current edition of the CA Building and Fire Codes including all local ordinances
and standards which are effective at the time of Plan Check Submittal. The new structures are
required to be equipped with automatic fire sprinklers per the CBC and Current RCFPD Ordinance.
Disabled access for the site and building must be in accordance to the State of CA and ADA
regulations.
Grading Section
Please be advised of the following Special Conditions
1. Prior to issuance of a wall permit, a copy of the Grading Special Conditions of Approval shall be
included within the engineered wall plans and calculations.
Standard Conditions of Approval
2. Prior to the issuance of a grading permit the applicant shall submit the proposed plans to the San
Bernardino County Transportation Authority (who whomever has jurisdiction over the railroad
property along the southerly boundary) for review and approval for the disposition of storm water
onto the adjacent railroad property. A copy of said comments shall be provided to the City Engineer,
or his designee,for review.
3. Grading of the subject property shall be in accordance with current adopted California Building Code
and/or the California Residential Code, City Grading Standards, and accepted grading practices.
The Grading and Drainage Plan(s) shall be in substantial conformance with the approved
conceptual Grading and Drainage Plan.
4. A soils report shall be prepared by a qualified Engineer licensed by the State of California to perform
such work. Two copies will be provided at grading and drainage plan submittal for review. Plans
shall implement design recommendations per said report.
5. The final Grading and Drainage Plan, appropriate certifications and compaction reports shall be
completed, submitted, and approved by the Building and Safety Official prior to the issuance of
building permits.
6. A separate Grading and Drainage Plan check submittal is required for all new construction projects
and for existing buildings where improvements being proposed will generate 50 cubic yards or more
of combined cut and fill. The Grading and Drainage Plan shall be prepared, stamped, and wet
signed by a California licensed Civil Engineer prior to the issuance of a grading or building permit.
7. The applicant shall comply with the City of Rancho Cucamonga Dust Control Measures and place a
dust control sign on the project site prior to the issuance of a grading permit. All dust control sign(s)
shall be located outside of the public right of way.
8. If a Rough Grading and Drainage Plan/Permit are submitted to the Building and Safety Official for
review, the rough grading plan shall be a separate plan submittal and permit from Precise Grading
and Drainage Plan/Permit.
Printed:1/2212020 www.CityofRC.us
Page 8 of 12
Project M DRC2018-00430
Project Name: EDR-DR 111 Industrial Building
Location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Gradinal Section
Standard Conditions of Approval
9. Prior to the issuance of a grading permit the applicant shall obtain written permission from the
adjacent property owner(s) to construct wall(s) on property line(s) or provide a detail(s) showing the
perimeter wall(s)to be constructed offset from the property line.
10. Prior to issuance of a grading permit the Final Grading and Drainage Plan shall show the
accessibility path from the public right of way and the accessibility parking stalls to the building
doors in conformance with the current adopted California Building Code. All accessibility ramps
shall show sufficient detail including gradients, elevations, and dimensions and comply with the
current adopted California Building Code.
11. The Grading and Drainage Plan shall implement City Standards for on-site construction where
possible, and shall provide details for all work not covered by City Standard Drawings.
12. Prior to issuance of a grading permit the grading plan shall show that all manufactured slopes shall
be a minimum 2-foot offset from the public right of way, permitted line, or the adjacent private
property. All slope offsets shall meet the requirements of the current adopted California Building
Code.
13. Prior to issuance of a grading permit, the grading and drainage plan shall show the maximum
parking stall gradient at 5 percent. Accessibility parking stall grades shall be constructed per the,
current adopted California Building Code.
14.The applicant shall provide a grading agreement and grading bond for all cut and fill combined
exceeding 5,000 cubic yards prior to issuance of a grading permit. The grading agreement and
bond shall be approved by the Building and Safety Official.
15. The final grading and drainage plan shall show existing topography a minimum of 100-feet beyond
project boundary.
16. This project shall comply with the accessibility requirements of the current adopted California
Building Code.
Phnted:1IM020 www.CltyofRC.us Page 9 of 12
Project#: DRC2018-00430
Project Name: EDR-DR N industrial Building
location: ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Grading Section
Standard Conditions of Approval
17. Grading Inspections:
a) Prior to the start of grading operations the owner and grading contractor shall request a
pre-grading meeting. The . meeting shall be attended by the project own erlrepresentative, the
grading contractor and the Building Inspector to discuss about grading requirements and preventive
measures, etc. If a pre-grading meeting is not held within 24 hours from the start of grading
operations, the grading permit may be subject to suspension by the Building Inspector;
b) The grading contractor shall call into the City of Rancho Cucamonga Building and Safety
Department at least 1 working day in advance to request the following grading inspections prior to
continuing grading operations:
i) The bottom of the over-excavation;
ii) Completion of Rough Grading, prior to issuance of the building permit;
iii) At the completion of Rough Grading, the grading contractor or owner shall submit to the Permit
Technicians (Building and Safety Front Counter) an original and a copy of the Pad Certifications to
be prepared by and properly wet signed and sealed by the Civil Engineer and Soils Engineer of
Record;
iv) The rough grading certificates and the compaction reports will be reviewed by the Associate
Engineer or a designated person and approved prior to the issuance of a building permit.
18. Prior to issuance of a wall permit, on engineered combination garden/retaining walls along the
property boundary the structural calculations for the wall shall assume a level toe/heel at the
adjacent off-site property (i.e. a manufactured slope is not present). This shall be shown in the
typical sections of the grading and drainage plan.
19. Prior to issuance of a grading or building permit, the permitted grading plan (or architectural site
plan) set shall show in each of the typical sections and the plan view show how the separations
between the building exterior and exterior ground surface meet the requirements of Sections
CBC1804.31CRC R401.3, CBC2304.11.2.21CRC R317.1(2) and CBC2512.1.21CRC R703.6.2.1 of
the current adopted California Building Code/Residential Code.
20. Prior to issuance of a grading permit, the applicant shall obtain a signed and notarized letter from
the adjacent property owner(s) for ALL work proposed on the adjacent property. The letter shall be
scanned and pasted onto the permitted grading plan set. The letter shall show on either the title
sheet or a detail sheet of the grading and drainage plan set.
21. Prior to approval of the project-specific storm water quality management plan, the applicant shall
submit to the Building Official, or his designee, a precise grading plan showing the location and
elevations of existing topographical features, and showing the location and proposed elevations of
proposed structures and drainage of the site.
22. A drainage study showing a 100-year, AMC 3 design storm event for on-site drainage shall be
prepared and submitted to the Building and Safety Official for review and approval for on-site storm
water drainage prior to issuance of a grading permit. The report shall contain water surface profile
gradient calculations for all storm drain pipes 12-inches and larger in diameter. All reports shall be
wet signed and sealed by the Engineer of Record. In addition, the project specific drainage study
shall provide inlet calculations showing the proper sizing of the water quality management plan
storm water flows into the proposed structural storm water treatment devices.
www.CRYO RC.us
Printed 1122/2020 Page 10 of 12
Project#: DRC2018-00430
Project Name; EDR-DR 111 Industrial Building
Location; ---020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Grading Section
Standard Conditions of Approval
23. It shall be the responsibility of the applicant to acquire any required off-site drainage easements
prior to the issuance of a grading permit.
24. Private sewer, water, and storm drain improvements will be designed per the latest adopted
California Plumbing Code. Private storm drain improvements shall be shown on the grading and
drainage plan.
25. Prior to the issuance of the Certificate of Occupancy or final sign off by the Building Inspector the
engineer of record shall certify the functionality of the storm water quality management plan
(WQMP) storm water treatment devices and best management practices (BMP).
26. Prior to approval of the Water Quality Management Plan (WQMP), the WQMP shall include a copy
of the project Conditions of Approval.
27. Prior to the issuance of a Grading Permit the City of Rancho Cucamonga's "Memorandum of
Agreement of Storm Water Quality Management Plan" shall be submitted for review and approval
by the Building Official and recorded with the County Recorder's Office.
28. Prior to issuance of a Grading Permit the applicant shall obtain a Waste Discharge Identification
Number (WDID). The WDID number shall also be shown on the WQMP Site and Drainage Plan
document.
29.The applicant shall provide a copy of a completed EPA Form 7520-16 (Inventory of Injection Wells)
for each underground infiltration device, with the Facility ID Number assigned, to the Building and
Safety Services Department Official prior to issuance of the Grading Permit and/or approval of the
project-specific Water Quality Management Plan. A copy of EPA Form 7520-16 shall be scanned
and pasted onto the permitted grading plan set, and a copy of said form shall be included in the
project-specific Water Quality Management Plan.
30. The land owner shall provide an inspection report on a biennial basis for the structural storm water
treatment devices, commonly referred to as BMPs, to the City of Rancho Cucamonga
Environmental Program Manager. The land owner shall maintain on a regular basis as described in
the Storm Water Quality Management Plan prepared for the subject project. All costs associated
with the underground infiltration chamber are the responsibility of the land owner.
31. The land/property owner shall follow the inspection and maintenance requirements of the approved
project specific Water Quality Management Plan and shall provide a copy of the inspection reports
on a biennial basis to the City of Rancho Cucamonga Environmental Program Manager.
32. A final project-specific Storm Water Quality Management Plan (WQMP) shall be approved by the
Building and Safety Director, or his designee, and the City of Rancho Cucamonga's "Memorandum
of Storm Water Quality Management Plan" shall be recorded prior to the issuance of a grading
permit or any building permit.
33. The Site and Drainage Plan in the final project-specific Water Quality Management Plan shall show
the locations of all roof downspout drains. if required for storm water quality purposes, the
downspouts shall include filters.
Printed 1/2212020 www.CltyofRC,us Page 11 of 12
Project#: DRC2018-00430
Project Name: EDR-DR 111 Industrial Building
Location: —-020901313-0000
Project Type: Design Review
ALL OF THE FOLLOWING CONDITIONS APPLY TO YOUR PROJECT.
Grading Section
Standard Conditions of Approval
34. Prior to issuance of a grading permit and approval of the project specific water quality management
plan all private storm water catch basin inlets shall include insert filters to capture those pollutants of
concern as addressed in the in the final project-specific water quality management plan (WQMP). At
a minimum catch basin insert filters to capture trash and other floating debris. All catch basin insert
filters shall be maintained on a regular basis as described in the "Inspection and Maintenance
Responsibility for Post Construction BMP" section of the final project-specific water quality
management plan.
35. Prior to issuance of a grading permit the Final Project-Specific Water Quality Management Plan
shall include a completed copy of "Worksheet H: Factor of Safety and Design Infiltration Worksheet"
located in Appendix D "Section VII — Infiltration Rate Evaluation Protocol and Factor of Safety
Recommendations, ..." of the San Bernardino County Technical Guidance Document for Water
Quality Management Plans. The infiltration study shall include the Soil Engineer's recommendations
for Appendix D, Table VI1.3: Suitability Assessment Related Considerations for Infiltration Facility
Safety Factors".
36. Prior to approval of the final project-specific water quality management plan the applicant shall have
a soils engineer prepare a project-specific infiltration study for the project for the purposes of storm
water quality treatment. The infiltration study and recommendations shall follow the guidelines in the
current adopted "San Bernardino County Technical Guidance Document for Water Quality
Management Plans".
37. Prior to the issuance of a certificate of occupancy by the Building Official, or his designee, the civil
engineer of record shall file a Water Quality Management Plan (WQMP) Post Construction Storm
Water Treatment Devices As-Built Certificate with the Environmental Programs Coordinator, City of
Rancho Cucamonga Engineering Services Department.
38. NONRESIDENTIAL MANDATORY MEASURES — CALIFORNIA GREEN BUILDING STANDARDS
CODE — Prior to issuance of a grading permit the applicant shall show on the site plan and the
permitted grading plan set for non-residential projects the designated parking for clean air vehicles
per the current adopted California Green Building Standards Code, section 5.106.5.2 (and CBC
11B-812.3). NOTE- 10-scale details may be required to show that the parking stall(s) meet the
requirements of Chapter 11 of the current adopted California Building Code.
39. NONRESIDENTIAL MANDATORY MEASURES — CALIFORNIA GREEN BUILDING STANDARDS
CODE — Prior to issuance of a grading permit for non-residential projects the applicant shall show
on the electrical plans and the permitted grading plan set the location for a future installation of an
Electric Vehicle (EV) charging station/parking area per the current adopted California Green Building
Standards Code, section 5.106.5.3 (and CBC 118812.3). NOTE: 10-scale details may be required
to show that the parking stall(s) meet the requirements of Chapter 11 of the current adopted
California Building Code.
Printed:1/22/2020 www,cityofRc.us Page 92 of 12